Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Phone: 61 2 9624 1944

“Simple Logistics Fax: 61 2 9624 1233

for Complex Lifting” PO Box 299, Winston Hills NSW 2153


info@melrosecranes.com.au
www.melrosecranes.com.au
ABN 73 083 164 845

8- 450 TO N N E M OB IL E CR AN E H IR E 24 H OU R S / 7 DA Y S  S IT E I N S P ECT IO N S  C OM P UT ER A N AL Y SI S  O H& S  CIT Y & RT CR A N ES  TR A N S PO RT SO LUT IO N S

MAN BOX – SAFE WORK METHOD STATEMENT – PART 1


Company: SWMS Prepared By: Date:

Project: SWMS Approved By: Ref No:


Work Activity/Task: Accepted By:
Area/Zone:
CRANE AND MAN BOX USE
Mobile Crane Type: Unit No:

Residual
Procedures (in steps) Possible Hazards Risk Rate Safety Controls Responsibility
Risk
1. Pre-start check. Travel Slip, trip, fall. 3 Maintain three points of contact and adequate 5 Driver/Operator
to site grip on safety boots free of mud or oils when
completing daily pre-start logbook.
Poor visibility, tyre conditions. 3 Clean windows and mirrors before driving. 6 Driver/Operator

Oil, water, fuel leaks. 3 Spill kits kept in cranes to contain spills. 6 Driver/Operator

Vehicular collisions. 1 Travel as per Statutory Road Rules & Permits. 5 Driver/Operator

Fire hazard. 2 Check condition of fire extinguisher. 6 Driver/Operator

2. Arrive on site Collisions with other site plant. 1 Park plant/crane in safe area. 6 Driver/Operator

Unfamiliar with site, unstable ground, 2 Complete site induction and site inspection. 6 Crane crew/client
overhead obstacles, underground Obey all site safety rules and signage.
services.
Personal injury. 2 Minimum PPE to be worn is hard hat, safety 5 Crane crew/client
glasses, high visibility clothing and steel capped
boots.
3. Plan work strategy Confusion over work to be performed. 2 Crane crew to have tool box meeting with client, 6 Client/crane crew/
supervisor. supervisor
Injury to workers or public. 2 Approved traffic control, permits, barricades and 5 Client/crane crew/
signage. supervisor
D:\106754372.doc Version 2 Issued: 3-Mar-16 Page 1 of 6
Residual
Procedures (in steps) Possible Hazards Risk Rate Safety Controls Responsibility
Risk
Unable to set up crane safely. 1 Specific site inspection. 5 Crane crew

4. Set up crane, (with fly jib Collisions with other plant, crushing. 1 Dogman/rigger to guide crane into position. 6 Crane crew
as required)
Soft, uneven, unstable ground, 1 Site inspection. Extra timber pads or road plates 5 Crane crew
suspended slab – outriggers sinking. under outrigger pads. Engineers report required
Crushing when extending outriggers, 1 Co-ordinate all functions with dogman/rigger. 5 Crane crew
slewing or placing counterweights. Keep clear of crush zones ie; articulation point of
Franna cranes.
Possible manual handling injuries when 3 Share load if too heavy, use proper manual 5 Crane crew
packing under outriggers. handling technique.
Collisions to plant or obstacles when 1 Clear tail swing area, watch for overhead 5 Crane crew
slewing crane, electrocution. obstacles and keep mandatory distances from
powerlines. Distance from 132,000 volts 3m,
132,000 to 330,000 volts 6m, 330,000 volts and
over 8m.
Placing rigging gear on hook – hand, 3 Wear riggers gloves. Share load using proper 5 Crane crew
finger and/or manual handling injuries. manual handling technique.
Incorrect boom length, working radius 2 Check crane computer and all crane functions. 5 Crane crew
and configuration. Crane malfunction. Critical radius check by doing ‘empty hook’ test
lift and refer to crane chart.
Crush injuries and/or damage to plant 1 Configure crane and attachments by 5 Dogman/rigger
due to incorrect fly installation. manufacturer’s procedures by competent
dogman/rigger only.
5. Rig load to be lifted Lifting gear not suitable. Defective lifting 2 Crane crew to ascertain loads to be lifted 5 Crane crew
gear eg; cuts, gouges, nicks, bends, (known weight, engineer etc) ensure correct,
twists, excessive rust, missing tags, certified lifting gear used only. Lifting gear must
broken safety catches, links stretched, be checked for defects before use, if defective
uncertified. withdraw from use immediately.
Trapping of hands or fingers. 2 No crane functions without clear signalling from 5 Crane crew
dogman/rigger.
Slip, trip, fall. 2 Maintain three points of contact and ensure 5 Dogman/rigger
footwear has sufficient grip when walking on
load. If a fall distance of 2m or more is likely
then fall arrest is required eg; safety railing,
safety harness worn.
6. Lift and control load Load tipping, sliding. 2 Dogman/rigger to ensure crane hook is plumb 5 Dogman/rigger
with load, no dragging.
Falling loads, crushing injury. 1 Loads not to be lifted over personnel. All 5 Crane crew/client/
personnel except dogman/rigger to keep clear supervisor/foreman
until load positioned.
Not understanding signals – collisions, 1 Only dogman/rigger to signal crane. Check radio 5 Dogman/rigger
crushing injuries. operation if using and carry whistle for backup.

D:\106754372.doc Version 2 Issued: 3-Mar-16 Page 2 of 6


Residual
Procedures (in steps) Possible Hazards Risk Rate Safety Controls Responsibility
Risk
Swinging loads. 2 Taglines attached must be 16mm dia rope. 5 Dogman/rigger

6. Lift and control load Windy conditions. 2 Crane operator’s decision on use. 5 Operator
(cont)
Electrocution. 1 Crane and load to keep mandatory distances 5 Crane crew/spotter
from live power. Vigilance of live cables at all
times.
Tipping while mobilising crane onsite. 2 Keep boom short and load close to ground, 5 Crane crew
bridle load to crane. Vigilance for other plant or
obstructions.
7. Place load Load out of sight of operator – possible 1 Use radios where possible. Check clarity of 5 Crane crew
collision, crushing injury. radio with operator. Carry spare full battery and
whistle.
Trapping body injuries. 1 Crane operator to take signals from 5 Operator
dogman/rigger only.
Toppling or slipping of load. 1 Load stability to be checked by dogman/rigger 5 Dogman/rigger
before de-rigging.
8. De-rig crane Trapping of hands or fingers. 2 Dogman/rigger only to signal crane operator and 5 Operator
co-ordinate retraction of outriggers.
Manual handling injuries. 2 Share load handling ie; rigging gear, outrigger 5 Crane crew
pads, timbers, etc.
Slips, trips, falsl. 2 Maintain three points of contact when accessing 5 Crane crew
crane deck, cabin or support vehicles.
9. Leave site Collisions with obstacles/ personnel or 2 Obey site safety rules/speed limits. 6 Crane crew
plant. Dogman/rigger or competent person to guide
crane off site.
Vehicular, pedestrian collisions. 1 Travel as per Statutory Road Rules and Permits. 5 Driver/operator

D:\106754372.doc Version 2 Issued: 3-Mar-16 Page 3 of 6


SWMS ANALYSIS OR EXTRA PROCEDURES REQUIRED (MAN BOX)
Residual
Procedures (in steps) Possible Hazards Risk Rate Safety Controls Responsibility
Risk
10. Safe Operation of a Man Inappropriate man box. 1 Only a certified man box/work box to AS1418.17 5 Supervisor/crane crew
Box is to be used.
Crane tip over/two block hook/over 1 All crane function limiting switches are to be 5 Crane crew.
wind winch drum. active and tested before use.
Freefall crane winch. 1 A crane with freefall must have a positive lock 5 Operator/supervisor
out fitted to prevent freefall. All winching is to be
by power up or down only.
Crane tip over. 1 Crane capacity to be a minimum of 1000kg at 5 Supervisor/operator
its furthest radius of the task performed. No
other lifting by crane is allowed whilst the
workbox is attached.
Falling from height. 1 Man box inducted personnel only. Safety 5 Supervisor/crane crew/
harnesses to be worn and fixed to anchor points. client
Falling objects. 1 All materials to be secured within the work box. 5 Dogman/rigger
All tools to be fitted with lanyards and attached
when used. Control working area, eg;
barricading, bunting or vigilance. Wear safety
helmets at all times.
Collision with overhead hazards. 1 Secure radio communications and vigilance. 5 Crane crew

Equipment failure. 1 Inspect all plant is in good order before use. 5 Crane crew

Overload man box or crane. 1 Do not exceed WLL of man box or crane. 5 Crane crew

Incorrect crane signalling. 1 Competent dogman/rigger only to signal crane 5 Crane crew
operator.
Adverse conditions. 1 The man box is not to be used when wind 5 Supervisor/crane crew
speeds are in excess of 25km/h, electrical
storms or any other adverse weather conditions
that could compromise the safety of personnel.
Fall from height. 1 Personnel do not enter or leave the man box 5 Supervisor/crane crew
when elevated except in an emergency or when
a risk analysis shows this is the safest way to
access a structure (procedure to be developed).

D:\106754372.doc Version 2 Issued: 3-Mar-16 Page 4 of 6


RISK ASSESSMENT MATRIX

Likelihood of injury or illness

Very Very
Severity of injury or illness Likely Unlikely
Likely Unlikely

Fatality/permanent disability or ill health 1 1 2 3


Long term illness or serious injury 1 2 3 4
Medical attention and several days off work 2 3 4 5
First aid needed 3 4 5 6

1 – top priority; act immediately 4 – slight; within 24 hours


2 – priority; before continuing 5 – minor; within one week
3 – serious; by end of shift 6 – low priority; act when possible

1. ELIMINATION
Can the work process, substances or plant creating the hazard be eliminated?
2. SUBSTITUTION
Can the work process, substance or plant be substituted for something safer?
3. ISOLATION
Enclosing the hazard, eg; placing barricades around the perimeter of the cranes operating area.
4. ENGINEERING CONTROLS
Means changing process, equipment or tools to minimise the hazard exposure.
5. ADMINISTRATION CONTROLS
Develop measures to ensure that the work is performed safely through safe work procedures to reduce exposure to hazards.
6. PPE
Personal protective equipment is the last resort in responding to work place hazards and should be used only as an interim measure.

D:\106754372.doc Version 2 Issued: 3-Mar-16 Page 5 of 6


SAFE WORK METHOD STATEMENT – PART 2
Personnel & Qualifications: Safety duties and responsibilities: Training required to complete work:
Crane Operator/Driver W/cover ticket / general OH&S induction / site induction / tool box meet/
W/cover ticket & heavy vehicle licence Drive, operate crane safely; obey site safety rules man box induction
Dogman/Rigger W/cover ticket / general OH&S induction / site induction / tool box meet/
W/cover ticket Guide crane, rig and place loads safely; obey site safety rules man box induction
Dogman/Rigger W/cover ticket / general OH&S induction / site induction / tool box meet/
W/cover ticket Guide crane, rig and place loads safely; obey site safety rules man box induction

Engineers Details / W/cover Approvals / Permits: References:


OH&S Act, 2000. OH&S Regulations, 2001.
AS 2550.-2002 Parts 1-5 (Safe Use of Cranes)
AS 1418.-2002 (Crane, Hoist & Winch – general requirements)
Plant/Equipment: Crane Type: AS 3775.2.-2004 (Chain Slings – care and use)
AS1666.2.-1995 (Wire-rope Slings – care and use)
Certified lifting gear, ie; chains, slings, shackles, equalizers, brick cages, man boxes, AS4497.2-1997 (Round slings, Synthetic Fibre – care and use)
spreader bars. COP Moving Plant Onsite. COP Working at Heights
Maintenance Checks: To manufacturer’s specifications Crane Industry Council of Australia (CICA) “Crane Safety Manual”
Additional References:
Daily pre-start checks, monthly routine maintenance checks, annual CraneSafe
inspection, logs kept in crane.

Read, agreed and signed below by all employees on site:

I have read and clearly understand the details contained in this document. As a responsible person, I am aware of my obligations towards ensuring that all works will be carried out in a safe and
appropriate manner and in compliance with the details of this SWMS. I am also the person responsible for implementing, monitoring and controlling each hazard as identified in the SWMS.

Crane Operator: ...................................................................................... Sign: ................................................................................. Date: ..........................................................


WorkCover: ............................................................................................. Green Card: .....................................................................

Crane Operator: ...................................................................................... Sign: ................................................................................. Date: ..........................................................


WorkCover: ............................................................................................. Green Card: .....................................................................

Crane Operator: ...................................................................................... Sign: ................................................................................. Date: ..........................................................


WorkCover: ............................................................................................. Green Card: .....................................................................

Crane Operator: ...................................................................................... Sign: ................................................................................. Date: ..........................................................


WorkCover: ............................................................................................. Green Card: .....................................................................

D:\106754372.doc Version 2 Issued: 3-Mar-16 Page 6 of 6

You might also like