PROJECT: G+4+11 TYPICAL Agreement No.

FLOOR
METHOD STATATEMENT Ref. No. MS-0001
Rev. No. 00
FOR TOWER CRANE ERECTION Date: 01-04-19
TC-1 Page 5 of 19

4.5 THE HSE ENGINEER is responsible for ensuring the activities are carried
out as per project specific safety rules and regulations.

4.6 THE SURVEY ENGINEER is responsible for the setting out.

4.7 THE THIRD PARTY shall be responsible for testing certifying the use of
tower crane before operation.

5. TOOLS

 Spanner
 Hammer
 Safety PPE

6. MATERIALS

 Concrete MSRC 20/20, C40/20 (55% GGBS + 45% OPC)


 Steel rebar as per approved shop drawing
 4” PVC Sleeves
 Crane sections and accessories

7. PROCEDURE