Project Scope

Project Name: FMV 60,000 Liters modular water storage installation


Project Manager: Aires Luzada

1. Project Purpose Statement:


The purpose of the FMV 60,000 Liters modular water storage project is to provide a
reliable and efficient solution for the storage and supply of water. This system is designed
to meet the needs of communities or industries requiring large-scale water storage
capabilities. With its modular design, the project aims to offer flexibility in installation and
expansion, ensuring adaptability to various site conditions and demands. The use of
durable materials guarantees longevity and minimal maintenance, making it a cost-
effective investment for sustainable water management. The project is committed to
delivering a water storage solution that is both functional and environmentally responsible,
contributing to better resource conservation and management.

2. Background:
FIRSTANK has established itself as a leader in the water storage industry, particularly with
its innovative Fiber Reinforced Modular Water Storage (FMV) systems. These modular
tanks, constructed from fiberglass reinforced polyester, are known for their lightweight,
versatile design, allowing for easy adaptation to meet any customer's specific needs. The
FMV tanks boast a range of advantages, including corrosion resistance, leak-proof design,
and complete drainage capabilities, ensuring a reliable and cost-effective maintenance
solution. With a commitment to quality and customer satisfaction, FIRSTANK's FMV
systems represent a significant advancement in water storage technology.

3. Objectives:
The primary objective of FIRSTANK in creating Fiber Reinforced Modular Water Storage
(FMV) is to provide a durable, reliable, and versatile water storage solution. These tanks
are designed with strength and long-term reliability in mind, sealing properties for water
tightness, and complete drainage capabilities. Additionally, they offer corrosion resistance
and a flexible design, which simplifies handling and site installation, making them a cost-
effective maintenance solution for various applications such as water supply, irrigation,
and rain harvesting.

7. Timeframe & Milestones

Panel Fabrication – 20 days


Mobilization - 1 day
Installation – 28 days

Item WORK DESIGNATIONS # Days Responsible


A LOT A: PREPARATION
I PRELIMINARY & GENERAL
I.1 SITE PREPARATION
I.1.1 Mobilization and Demobilization of contractor 1 day FIRSTANK
II FOUNDATIONS (3rd party)

III PANEL STRUCTURE (FIRSTANK)


III.1 Assembly of Panels 3 days FIRSTANK
III.2 Panel Stiffeners Installation 3 days FIRSTANK
III.3 1st lamination 3 days FIRSTANK
III.4 Internal Support welding structure 5 days FIRSTANK
III.5 2nd lamination 3 days FIRSTANK
rd
III.6 3 lamination and Finalization of hole outlets/inlets 3 days FIRSTANK
III.7 Final lamination 5 days FIRSTANK
III.8 Hydrotesting 3 days FIRSTANK

9. Exclusions

Exclusions:

Concrete Plinth – to be handled by a 3rd party


Plumbing works – to be handled by the client

10. Critical Success Factors

These include ensuring accurate design and early design freeze, fostering good working
collaboration and effective communication among project participants, and implementing
effective supply chain management. Additionally, involving key project participants
throughout the project, adopting a suitable procurement strategy and contracting, and
standardizing and benchmarking best practices are essential for the successful
implementation of FMV projects. These factors contribute to the strength, reliability, and
versatility of FMV systems, which are designed to be light, corrosion-resistant, and easily
adaptable to meet customer requirements.

Prepared By:

AIRES G. LUZADA
PROJECT MANAGER