SINDALAH NON-MANAGERIAL STAFF

ACCOMMODATION

REGION
NEOM
KINGDOM OF SAUDI ARABIA

DINING HALL BUILDING 031

BILL OF QUANTITIES
FOR
SKELETON & FINISHING PACKAGE

CLIENT DESIGN CONSULTANT CONTRACTOR

FEB. 2024
REV.01
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
SKELETON & FINISHING PACKAGE
DINING HALL BUILDING - (31) - GENERAL CONTENTS
Div. DIVISION BOQ PAGES
FROM PAGE TO PAGE
GENERAL SUMMARY
00 GENERAL PROJECT REQUIREMENTS
01 GENERAL REQUIREMENTS
02 EXISTING CONDITIONS
03 CONCRETE 031/DIV.03/01 031/DIV.03/05
04 MASONRY 031/DIV.04/01 031/DIV.04/02
05 METALS - NON-STRUCTURE 031/DIV.05/01 031/DIV.05/04
06 METALS - STRUCTURE 031/DIV.05/01 031/DIV.05/04
06 WOOD, PLASTICS, AND COMPOSITES
07 THERMAL AND MOISTURE PROTECTION 031/DIV.07/01 031/DIV.07/05
08 OPENINGS 031/DIV.08/01 031/DIV.08/06
09 FINISHES 031/DIV.09/01 031/DIV.09/06
10 SPECIALTIES 031/DIV.10/01 031/DIV.10/03
11 EQUIPMENT
12 FURNISHINGS
13 SPECIAL CONSTRUCTION
14 CONVEYING EQUIPMENT
21 FIRE SUPPRESSION 031/DIV.21/01 031/DIV.21/03
22 PLUMBING 031/DIV.22/01 031/DIV.22/04
23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) 031/DIV.23/01 031/DIV.23/04
25 INTEGRATED AUTOMATIONS
26 ELECTRICAL 031/DIV.26/01 031/DIV.26/05
27 COMMUNICATIONS 031/DIV.27/01 031/DIV.27/04
28 ELECTRONIC SAFETY AND SECURITY 031/DIV.28/01 031/DIV.28/04
31 EARTHWORKS 031/DIV.31/01 031/DIV.31/03
32 EXTERIOR IMPROVEMENTS
33 UTILITIES
34 TRANSPORTATIONS
35 WATERWAY AND MARINE CONSTRUCTION
40 PROCESS INTEGRATION
41 MATERIAL PROCESSING AND HANDLING EQUIPMENT
42 PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND
43
STORAGE EQUIPMENT
44 POLLUTION AND WASTE CONTROL EQUIPMENT
45 INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
46 WATER AND WASTEWATER EQUIPMENT
48 ELECTRICAL POWER GENERATION

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION General Summary - 031
Division 03 – Concrete,
Steel Reinforcement
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 03 - CONCRETE WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
A. Supply of materials and equipment.
Off loading and handling from trucks on
B. site to place of installation (including
carnage, unpacking, erecting in place).
On-site material protection and storage
C
before installation.
D Installation of materials and equipment
All civil works required and related to the
landscape works, such as: equipment,
tools, concrete bases and supports, cutting
and chasing through block and concrete
E walls and slabs for passage of conduits,
sleeves, trays, trunking and ladders,
excavation and back-fillings, riggings,
hoisting, waterproofing, cleaning &
protection
All labor, materials, tools, instruments,
electric power, water supply, fuel and
F
water required for work executions,
testing, and commissioning
Preparation of the shop-drawings and As-
G
built drawings
Preparation of the operation and
H
maintenance manuals
J Samples as required by the Engineer
Maintenance as per the Contract
K
Conditions
Coordination with other specialty
L contractors, such as special equipment
supplier(s) and subcontractor(s) etc.

****** *******

SINDALAH NON MANAGERIAL 031 / Div. 03 / 1


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

DIVISION 03 - CONCRETE WORK


SUB- STRUCTURE WORK

032000 - Concrete Reinforcement

Supply and install deformed high tensile


yield steel bars reinforcement grade 60 (fy
≥ 414 Mpa) minimum yield characteristic
strength, including all necessary preparation
work, complete as shown on drawings and
as specified (Reinforcement shall comply
with BS4449, BS4461 & BS4483)

Steel reinforcement various diameters, for


A Sub structure work, including steel reinf.
For slab on grade 44 TON

03100 - Concrete formwork


03300 - Cast in place concrete
03370 - Concrete Curing

Supply and cast-in-situ ready-mix plain


concrete of minimum compressive
characteristic cube strength equal to (15
MPA), 150 kg/cm2 based on 28 day test,
including all necessary formwork,
preparation work & curing, complete as
shown on drawings and as specified

(Quantity given in Cubic meters)


100 mm thick, plain concrete blinding,
B
below footings 50 M3

To Collection SAR

SINDALAH NON MANAGERIAL 031 / Div. 03 / 2


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

CONCRETE WORK ( Cont'd )


SUB- STRUCTURE WORK (Cont'd)
031000 - Concrete formwork
03300 - Cast in place concrete
03370 - Concrete Curing

Supply and cast-in-situ ready-mix


Reinforced Concrete of minimum
compressive characteristic cube strength
equal to (35 Mpa) 350 kg/cm2 based on 28
day test, including all necessary formwork,
preparation works & curing, complete as
shown on drawings and as specified
Structural drawings:
STR.DRG. 131001
STR.DRG. 531003
STR.DRG. 631001

(By Cubic Meters)


A Single footings (F1 to F7) - isolated 96 M3
B Tie beams (TB.1, TB.2, TB.3, TB.4 & TB.5) 48 M3
C Column necks (C1 & C2) 36 M3

031000 - Concrete formwork


03300 - Cast in place concrete
03370 - Concrete Curing

Supply and cast-in-situ ready-mix


Reinforced Concrete of minimum
compressive characteristic cube strength
equal to (35 Mpa) 350 kg/cm2 based on 28
day test, including all necessary formwork,
preparation works & curing, complete as
shown on drawings and as specified
Structural drawing:
DWG. STR. DRG. 131003
DWG. STR. DRG. 531002
(By Cubic Meters)
Slab On Grade (SOG)
150mm thick, slab on grade (Area = 1,270
D
m2) (at level 22850) 191 M3
E 3
Ditto; ramp on grade (Area = 176 m2) 26 M

To Collection SAR

SINDALAH NON MANAGERIAL 031 / Div. 03 / 3


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

CONCRETE WORK ( Cont'd )


SUPER - STRUCTURE WORK

03530 - CONCRETE TOPPING


Cement sand screed trowelled surface
smooth finish, including mesh
reinforcement; including water curing,
jointing and pointing, complete as shown
on drawings and as per specifications
A 90mm thick to internal flooring 1,270 M2

03 40 00 Precast Concrete

Precast Concrete shaft covers (topping),


sloped, including steel reinforcement, rain
water drip, with fixing, jointing, supporting,
and pointing, complete as shown on
drawings and as per specifications

DWG. STR. DRG. 131003


(Quantity enumerated)
D OVERAL SIZE 950x300mm 1 No.
B OVERAL SIZE 1000x350mm 4 No.
C OVERAL SIZE 1185x350mm 1 No.
D OVERAL SIZE 1330x300mm 1 No.
E OVERAL SIZE 500x500mm 2 No.
F OVERAL SIZE 550x350mm 10 No.
G OVERAL SIZE 300x250mm 6 No.
H OVERAL SIZE 200x200mm 3 No.
J OVERAL SIZE 300x300mm 1 No.

To Collection SAR

SINDALAH NON MANAGERIAL 031 / Div. 03 / 4


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION - CONCRETE & STEEL REINFORCEMENT WORK

CARRIED FROM PAGE DIV.03 /01 Preambles ******


CARRIED FROM PAGE DIV.03 /02

CARRIED FROM PAGE DIV.03 /03

CARRIED FROM PAGE DIV.03 /04

Total Carried to Summary (Division 03)


GRAND TOTAL (SAR)

SINDALAH NON MANAGERIAL 031 / Div. 03 / 5


STAFF ACCOMMODATION
Division 04 – Masonry
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 4 - MASONRY WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned
items in the B.O.Q;
A. Supply of materials and equipment.
Off loading and handling from trucks
on site to place of installation
B.
(including carnage, unpacking,
erecting in place).
On-site material protection and
C
storage before installation.
D Installation of materials and equipment
All civil works required and related to
the landscape works, such as:
equipment, tools, concrete bases and
supports, cutting and chasing through
E block and concrete walls and slabs for
passage of conduits, sleeves, trays,
trunking and ladders, excavation and
back-fillings, riggings, hoisting,
waterproofing, cleaning & protection
All labor, materials, tools,
instruments, electric power, water
F supply, fuel and water required for
work executions, testing, and
commissioning
Preparation of the shop-drawings and
G
As-built drawings
Preparation of the operation and
H
maintenance manuals
J Samples as required by the Engineer
Maintenance as per the Contract
K
Conditions
Coordination with other specialty
contractors, such as special
L
equipment supplier(s) and
subcontractor(s) etc.

****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. 04/1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
DIVISION 4 - MASONRY WORKS
04 20 00 Unit Masonry
04 21 00 Clay Unit Masonry
Block Work
Hollow concrete blockwork in cement
and sand mortar (1:4) including but not
limited to all cutting, fire rated gap at
top level with mastic sealant, bonding
beams, control and expansion joints,
and bond beams, complete as shown
on drawings and as per specifications

( By square meters )
Interior blockwork
A 100mm thick 124 M2
B 150mm thick 793 M2
C Ditto; 60 Min. fire rating 356 M2
D Ditto; 120 Min. fire rating 120 M2

E 200mm thick 22 M2
F Ditto; 60 Min. fire rating 48 M2
G Ditto; 120 Min. fire rating 37 M2

Solid concrete blockwork in cement


and sand mortar (1:4) including but not
limited to all cutting, fire rated gap at
top level with mastic sealant, bonding,
control and expansion joints, and bond
beams, complete as shown on
drawings and as per specifications.
External, main building facades

H 200mm thick, W6-EXT-430 495 M2


J 200mm thick, W6-EXT-650 250 M2
200mm thick, W6-EXT-430, 60 Min. fire
K
rating 5 M2

Total Carried to Summary (Division 04)


GRAND TOTAL (SAR)
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. 04/2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION - CONCRETE & STEEL REINFORCEMENT WORK

CARRIED FROM PAGE DIV.04 /01 Preambles ******


CARRIED FROM PAGE DIV.04 /02

Total Carried to Summary (Division 04)


GRAND TOTAL (SAR)
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. 04/3
Division 05 – Metals
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 5 - METALS MANUFACTURERS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A. Supply of materials and equipment.

Off loading and handling from trucks on site to place of


B.
installation (including carnage, unpacking, erecting in place).

C On-site material protection and storage before installation.


D Installation of materials and equipment

All civil works required and related to the landscape works,


such as: equipment, tools, concrete bases and supports, cutting
and chasing through block and concrete walls and slabs for
E
passage of conduits, sleeves, trays, trunking and ladders,
excavation and back-fillings, riggings, hoisting, waterproofing,
cleaning & protection

All labor, materials, tools, instruments, electric power, water


F supply, fuel and water required for work executions, testing,
and commissioning
G Preparation of the shop-drawings and As-built drawings
H Preparation of the operation and maintenance manuals
J Samples as required by the Engineer
K Maintenance as per the Contract Conditions
Coordination with other specialty contractors, such as special
L
equipment supplier(s) and subcontractor(s) etc.

****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 31 / Div. 05 / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
METAL WORK
05 50 00 Metal Fabrications
Composite Aluminum Cladding

GREY PVDF coated 100mm composit aluminum cladding fixed to


modular porta cabines structural system, complete with all
fittings and accessores as per drawings and specifications

Quantity in SQM.
To facades, W6 - Wall Type-Exterior Aluminum cladding
A
(EALUM 002) - Light Grey Color 280 m2

YELLOW PVDF coated 100mm composite aluminum cladding to


building facades fixed to modular porta cabines structural
system, complete with all fittings and accessores as per
drawings and specifications

Quantity in SQM.
To facades, W6 - Wall Type-Exterior Aluminum cladding
B
(EALUM 003) - Yellow Color 506 m2

Aluminium Coping
Detail (6) , DWG. STR. DRG. 822001
(By linear meters)
4mm ACP with non combustible mineral core, 450mm approx.
C
width 152 lm
05 51 00 - Metal Stairs
Stainless Steel cat ladder, comprising of side rail and rungs,
flat plate & support brackets, including welding, bolts, steel
angles, fixings, fittings, accessories and epoxy painting,
complete as shown on drawings & specifications

Quantity enumerated
D 6000mm high, safty cage steel ladder 1 No.
05 52 00 Metal Railings
Metal railings including but not limited to all necessary posts,
raking, brackets, support system, fittings, painting, complete as
shown on drawings and specifications
(by linear meters)
E 915mm high. to side of exterior steps, ramps, & pathways 72 LM

TOTAL PAGE (2) - (METAL WORK) - (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 31 / Div. 05 / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION
CARRIED FROM PAGE #1 (PREAMBLES)
********
CARRIED FROM PAGE #2

Total Carried to Summary (Division 05)


GRAND TOTAL (SAR)
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 31 / Div. 05 / 3
Division 05 – Structural Metals
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 05 - STRUCTURAL METAL WORK
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
Supply of materials and equipment.
Off loading and handling from trucks on site
to place of installation (including carnage,
unpacking, erecting in place).
On-site material protection and storage
before installation.
Installation of materials and equipment
All civil works required and related to the
landscape works, such as: equipment, tools,
concrete bases and supports, cutting and
chasing through block and concrete walls
and slabs for passage of conduits, sleeves,
trays, trunking and ladders, excavation and
back-fillings, riggings, hoisting,
waterproofing, cleaning & protection

All labor, materials, tools, instruments,


electric power, water supply, fuel and water
required for work executions, testing, and
commissioning
Preparation of the shop-drawings and As-
built drawings
Preparation of the operation and
maintenance manuals
Samples as required by the Engineer
Maintenance as per the Contract Conditions

Coordination with other specialty


contractors, such as special equipment
supplier(s) and subcontractor(s) etc.

****** *******

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV.5B / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

STRUCTURAL METAL WORK


05 10 00 Structural Metal Framing
Design, Supply, Fabricate, install and carry out
load test by third party Steel Structural
skeleton as shown on the design structural
drawings, consisting of steel structure
members such as Steel columns, Steel
beams, Steel tubes, anchor bolts, brackets,
screws, plates and the like, including drilling
in the column necks as per the structural
details, including stiffeners, brackets, joints,
full strength welding and fixation with
anchorage system, with all necessary fittings,
accessories, conduits and supporting,
complete as shown on specifications
Structural drawings:
DWG. STR. DRG. 131004
DWG. STR. DRG. 131005
DWG. STR. DRG. 231001
DWG. STR. DRG. 331001
DWG. STR. DRG. 531001
DWG. STR. DRG. 631001
(PER TON)
A HEA160 Steel structural columns 1.00 Ton
B HEA240 Steel structural columns 11.50 Ton
C HEA300 Steel structural columns 3.50 Ton

Steel Strutural for suspended slabs

IPE180, IPE200, IPE220, IPE240, IPE270,


IPE300, IPE330, IPE400, IPE450, IPE500
Steel structural beams, including steel
Bracing RHS 160*10 & SHS 200*5 64 Ton

DWG. STR. DRG. 128003


DWG. STR. DRG. 128004
DWG. STR. DRG. 528001
Steel Plates to Concrete Bases, including
non-shrink grout material
(By Numbers)
PLATE SIZE 400*400 MM, PL30MM , 8M20-
D
PL125 F1554 GRADE 105 (DET. 1) 33 No.
PLATE SIZE 500*500 MM, PL35MM , 8M24-
E
PL125 F1554 GRADE 105 (DET. 2) 14 No.
PLATE SIZE 600*600 MM, PL40MM , 8M36-
F
PL125 F1554 GRADE 105 (DET. 3) 8 No.

To Collection SAR

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV.5B / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

STRUCTURAL METAL WORK (Cont'd)


05 10 00 Structural Metal Framing
05 30 00 Metal Decking
Steel Structural Slab Deck Covering
(Topping)

Steel structural slab deck covering,


consisting of 0.6 mm galvanized corrugated
sheets, 10 cm thick concrete deck topping
with compressive concrete strength of
21N/mm2 in 28 days & steel reinforcement
mesh T10mm/ 150mm, with all necessary
sheet overlabs and all related work

DWG. STR. DRG. 131004


DWG. STR. DRG. 131005
(PER SQM.)
A 100mm thick steel slab decking 1,310 M2

Steel Structural Canopies


Steel structural canopies, consisting of steel
tubes RHS 80*40*3, galvanized steel rods,
steel plates and brackets, with powder
coated aluminium sheet cladding, with all
necessary sheet overlabs and all related
work
DWG. STR. DRG. 131004
DWG. STR. DRG. 131005

(Quantity enumerated)
B OVERAL SIZE 5970x2920 MM 1 No.
C OVERAL SIZE 2820x3870 MM 1 No.
D OVERAL SIZE 26795x3870 MM 1 No.

To Collection SAR

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV.5B / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Item Description Total Amount (SAR)

STRUCTURAL METAL WORK (Cont'd)

COLLECTION

CARRIED FROM PAGE DIV.05 /01 Preambles ***** *****


CARRIED FROM PAGE DIV.05 /02
CARRIED FROM PAGE DIV.05 /03

Total Carried to Summary (Division 05)


GRAND TOTAL (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV.5B / 4
Division 06
Wood, Plastics, and Composites

(N/A)
Division 07
Thermal and Moisture Protection
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 07 - THERMAL & MOISTURE PROTECTION
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
A. Supply of materials and equipment.
Off loading and handling from trucks on
B. site to place of installation (including
carnage, unpacking, erecting in place).
On-site material protection and storage
C
before installation.
D Installation of materials and equipment
All civil works required and related to the
landscape works, such as: equipment,
tools, concrete bases and supports, cutting
and chasing through block and concrete
E walls and slabs for passage of conduits,
sleeves, trays, trunking and ladders,
excavation and back-fillings, riggings,
hoisting, waterproofing, cleaning &
protection
All labor, materials, tools, instruments,
electric power, water supply, fuel and
F
water required for work executions,
testing, and commissioning
Preparation of the shop-drawings and As-
G
built drawings
Preparation of the operation and
H
maintenance manuals
J Samples as required by the Engineer
Maintenance as per the Contract
K
Conditions
Coordination with other specialty
L contractors, such as special equipment
supplier(s) and subcontractor(s) etc.

****** *******

SINDALAH NON MANAGERIAL 031/ Div. 07 / 1


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

DIVISION 07 - MOISTURE PROTECTION

07535 - Modified Bitumen Membrane


07 10 00 - Dampproofing and Waterproofing

Waterproofing insulation to underground


structural elements
Supply and lay-on two layers of roll
applied waterproofing membrain, including
all necessary preparation works, primer
coat, applying horizontally and vertically,
overlaps, including testing and cleaning,
complete as shown on related drawings,
specifications and as Engineer's
instructions

Quantities given by square meters


Laid horizontally & vertically to
A
foundations in any type & column necks 1,077 M2

To Collection SAR

SINDALAH NON MANAGERIAL 031/ Div. 07 / 2


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
DIVISION 07 - MOISTURE PROTECTION
07535 - Modified Bitumen Membrane
07 120 - Bitumenous waterproofing
07 22 00 - Roof and Deck Insulation
ROOFING PROTECTION
03530 - CONCRETE TOPPING

Cement sand screed including pouring,


curing & smooth finish, complete as shown
on drawings and as per specifications

A 100mm thick screed, to slope 1,290 M2


2mm thick EPDM membrane water
proofing including but not limited to all
necessary fixings, complete as shown on
drawings and as per Technical
Specifications.
B To main roof, horizontally 1,290 M2
C To main roof, vertically 77 M2

Roof protection layers, including all


necessary cuttings, jointing and the like,
complete as shown on drawings and as
per specifications.
D 80mm thick thermal insulation, horizontally 1,290 M2
E 48mm thick Geotextile Protection layer 1,290 M2
F 50-100mm thick gravel layer, horizontally 1,290 M2

07620- SHEET METAL FLASHING AND TRIM


Aluminum continuous flashing, including
but not limited to anchors, cut-off mastic
and all necessary accessories, complete
as shown on drawings and as per
specifications.
G To perimeter of parapet/upstands at roof 152 lm
H Cement/sand angle fillet 152 lm

07900 - JOINT SEALANTS


Mastic sealant including making grooves,
prepare surface to receive sealant and
closed cell backing cord, complete
J To perimeter of parapet/upstands at roof 152 lm

To Collection SAR

SINDALAH NON MANAGERIAL 031/ Div. 07 / 3


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

DIVISION 07 - MOISTURE PROTECTION


07535 - Modified Bitumen Membrane
07120 - BITUMENOUS WATERPROOFING

07 20 00 - Thermal Protection
Rock-wool thermal insulation, including
all necessary fixing, cuttings, and
accessories complete as shown on
drawings and as per Technical
Specifications.
(Refer to detailed drawing # 822001)
Quantities given by square meters
150mm thick, to building facades, vertically
A (EIFS), COVERED WITH
BREATHABLE FACER 790 M2

Waterproofing to wet areas


2mm thick EPDM Rubber membrane water
proofing including all necessary surface
preparation, complete as shown on
drawings and as per specifications
Quantities given by square meters
C To wet area flooring, horizontally 61 M2
D Ditto; vertically applied on wet area walls 38 M2
To exterior building elevations behind
E 2
aluminium cladding, applied vertically 750 M
To floors and walls of cold & freezer rooms,
F 2
behind the sandwich panels 320 M

Protection below Slab On Grade


POLYTHENE SHEET (250 Microns),
including all necessary surface
preparation, cuttings, overlapping, jointing
and the like, complete as shown on
drawings and as per specifications
Quantities given by square meters
G Laid horizontally 1,270 M2

To Collection SAR

SINDALAH NON MANAGERIAL 031/ Div. 07 / 4


STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION - MOISTURE PROTECTION

CARRIED FROM PAGE DIV.07 /01 Preambles ******


CARRIED FROM PAGE DIV.07 /02

CARRIED FROM PAGE DIV.07 /03

CARRIED FROM PAGE DIV.07 /04

Total Carried to Summary (Division 07)


GRAND TOTAL (SAR)

SINDALAH NON MANAGERIAL 031/ Div. 07 / 5


STAFF ACCOMMODATION
Division 08
Openings
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 8 - OPENINGS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A. Supply of materials and equipment.

Off loading and handling from trucks on site to place of


B.
installation (including carnage, unpacking, erecting in place).

C On-site material protection and storage before installation.


D Installation of materials and equipment

All civil works required and related to the landscape works,


such as: equipment, tools, concrete bases and supports, cutting
and chasing through block and concrete walls and slabs for
E
passage of conduits, sleeves, trays, trunking and ladders,
excavation and back-fillings, riggings, hoisting, waterproofing,
cleaning & protection

All labor, materials, tools, instruments, electric power, water


F supply, fuel and water required for work executions, testing,
and commissioning
G Preparation of the shop-drawings and As-built drawings
H Preparation of the operation and maintenance manuals
J Samples as required by the Engineer
K Maintenance as per the Contract Conditions
Coordination with other specialty contractors, such as special
L
equipment supplier(s) and subcontractor(s) etc.

****** *******

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031/ DIV. (8) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

DIVISION (8) - OPENINGS


08 10 00 Doors and Frames
08 11 13 Hollow Metal Doors and Frames
REFER TO DWG ARC. 625001 & ARC. 625003

Flush steel doors, comprising steel frames and steel leaf,


including all necessary fixings, fittings, accessories, openings
to grills, glass vision panels, heavy duty hardware
(Ironmongery), foam filling, locking bolt, heavy duty overhead
door closer and epoxy paint, complete as shown on drawings
and as per specifications

By Numbers
Single leaf Metal Doors - One way hinged
A S01 size 1000x 2200 mm high, H.M. PTD 1 No.
B S04 size 1000x 2200 mm high, H.M. PTD 4 No.

Double leaf Metal Doors - One way hinged


C S10 size 1900x 2200 mm high, H.M. PTD 2 No.
D S13 size 1800x 2200 mm high, H.M. PTD 2 No.

Double leaf Metal Doors - One way hinged


60 MIN. FIRE RATING
E S012 size 1600x 2200 mm high, H.M. PTD 2 No.
F S015 size 1800x 2200 mm high, H.M. PTD 1 No.
G S016 size 1500x 2200 mm high, H.M. PTD 1 No.

Single leaf Metal Doors - One way hinged


90 MIN. FIRE RATING
H S05 size 1000x 2200 mm high, H.M. PTD 1 No.

TOTAL PAGE (2) - (OPENINGS) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031/ DIV. (8) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

DIVISION (8) - OPENINGS (Cont'd):

08 14 00 - Wood Doors

Supply and install HDF flush laminated wooden doors,


comprising steel door frames and flush laminated wood leaf,
including all necessary fixings, fittings, accessories, openings
to grills, heavy duty hardware (Ironmongery), foam filling,
locking bolt, heavy duty overhead door closer and epoxy paint,
complete as shown on drawings and as per specifications

By Numbers
Single leaf Metal Doors - One way hinged
A W01 size VAR W.x 2200 mm high, S.W, PTD 11 No.

Doors (without tags), for rooms (chef's room, cold kitchen,


B
finishing bakery, fruit and veg prep area, & heat preperation room)
5 No.

Single leaf Metal Doors - One way hinged


90 MIN. FIRE RATING
C W02 size VAR W.x 2200 mm high, S.W, PTD 1 No.

Double leaf Metal Doors - One way hinged


D W10 size 1900x 2200 mm high, S.W, PTD 2 No.

08 30 00 - Specialty Doors and Frames

Electrical operated galvanized metal shutter doors & frames,


comprising metal box covers, electrical Motors, bottom rail,
chains and the like, including all necessary fixings, accessories,
hardware (Ironmongery), bottom rubber, sensors, foam filling,
locking bolt, and powder coated paint, complete as shown on
drawings and as per specifications

E Size 7000x 3000 mm high 1 No.

TOTAL PAGE (3) - (OPENINGS) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031/ DIV. (8) / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

DIVISION (8) - OPENINGS (Cont'd):

08 40 00 - Entrances, Storefronts, and Curtain Walls

Supply and install double glazed powder coated aluminum


curtain walls, special section aluminium profile, consisting of
double glazing - 6mm thick clear float toughened glass inner
pane, 12mm air gap and 6mm thick reflective float toughened
glass exterior pane, including aluminium frames, trims,
flashing, mastic sealants, weather stripping, architrave, sills,
thresholds, fly screen, hardware and caulking, complete as
shown on drawings and as specified, to Engineer's approval

Quantity enumerated
A CO1, (W. 6000 x H 3000 mm) 1 No.
B CO2, (W. 3900 x H 3000 mm), with double leaf door 1950*3000 1 No.
C CO3, (W. 3600 x H 3000 mm) 1 No.
D CO4, (W. 3500 x H 3000 mm), with double leaf door 2000*3000
1 No.
E CO5, (W. 817 x H 3000 mm) 1 No.
F CO6, (W. 5650 x H 3000 mm) 3 No.
G CO7, (W. 5650 x H 3000 mm), with single leaf door 1200*3000 1 No.
H CO8, (W. 5650 x H 3000 mm) 1 No.

(08520) - ALUMINUM DOORS AND WINDOWS


Powder coated aluminum doors double glazing, complete
including frames, angles, mullions, channels, rubber strips,
mastic pointing, ironmongery, cover joints where required
and all necessary fixing accessories; as specified and as
shown on drawings

J W01 - sliding window ( W. 840 x H. 2100 mm) 2 No.

TOTAL PAGE (4) - (OPENINGS) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031/ DIV. (8) / 4
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION

CARRIED FROM PAGE #1 (PREAMBLES)


********
CARRIED FROM PAGE #2
CARRIED FROM PAGE #3
CARRIED FROM PAGE #4

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031/ DIV. (8) / 5
Division 09
Finishes
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 9 - FINISHING WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A Supply of materials and equipment.

Off loading and handling from trucks on site to place of


B
installation (including carnage, unpacking, erecting in place).

C On-site material protection and storage before installation.


D Installation of materials and equipment

All civil works required and related to the landscape works,


such as: equipment, tools, concrete bases and supports,
cutting and chasing through block and concrete walls and
E
slabs for passage of conduits, sleeves, trays, trunking and
ladders, excavation and back-fillings, riggings, hoisting,
waterproofing, cleaning & protection

All labor, materials, tools, instruments, electric power, water


F supply, fuel and water required for work executions, testing,
and commissioning
G Preparation of the shop-drawings and As-built drawings
H Preparation of the operation and maintenance manuals
J Samples as required by the Engineer
K Maintenance as per the Contract Conditions
Coordination with other specialty contractors, such as special
L
equipment supplier(s) and subcontractor(s) etc.

****** *******

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 31 / DIV. (9) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

FINISHING WORK
09 20 00 - Plaster and Gypsum Board
09 24 00 Cement Plastering

Three coats of cement/sand mix plasterwork to walls, edges,


parapets and the like, including all necessary accessories,
sccaffolding, water-curing, alignement, and all related work,
complete as shown on drawings and specifications

Items given in square meters


A To interior block and concrete walls 2
733 m
B To exterior block walls for parapets and toppings 2
220 m
C To walls behind ceramic work 265 m2

09 21 16 - GYPSUM BOARD ASSEMBLIES


09 22 00 Supports for Plaster and Gypsum Board
09 29 00 Gypsum Board
Item given in square meters
Moisture resistant Gypsum board suspended ceiling 12.5mm
thick with decorative texture white paint including but not
limited to suspension system, fittings, accessories and skim
coat, complete as shown on drawings and as per
specifications

D Gypsum board horizontally, IGYP-01 46 m2


E Ditto; IGYP-02, Water resistant 60 m2

TOTAL PAGE (2) - (FINISHING WORK) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 31 / DIV. (9) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

FINISHING WORK (Cont'd):


09 30 00 - Tiling
Laser cut ceramic floor tiles, including cement/ sand mortar
bed, adhesive material, cuttings, grouting, jointing and
pointing, complete as shown in drawings and as per
specifications.
Floor tile items are given in square meters
Skirting tile items are given in linear meters

ICT-01 - Anti-slip barefoot ceramic floor tiles, size 300x600


A 2
mm (light grey) 3 m
ICT-02 - Anti-slip barefoot ceramic floor tiles, size 300x600
B
mm (light grey) 58 m2
C ICT-04 - Concrete look matt size 600*600mm 502 m2
D ICTB-02 - Concrete look skirting tiles, size 600 x 100mm 98 lm

QUARRY TILES

Quarry floor tiles, including cement/ sand mortar bed,


adhesive material, cuttings, grouting, jointing and pointing,
complete as shown in drawings and as per specifications.

E At dining hall flooring 381 m2

09 30 00 - Tiling

Porcelain floor tiles, including cement/ sand mortar bed,


adhesive material, cuttings, grouting, jointing and pointing,
complete as shown in drawings and as per specifications.
Floor tile items are given in square meters

F IPT-01 - 600*600mm, wood look matt porcelain floor tiles 43 m2


G IPTB-01 - wood look skirting tiles, size 600 x 100mm 53 lm

TOTAL PAGE (3) - (FINISHING WORK) - (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 31 / DIV. (9) / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

FINISHING WORK (Cont'd):


09 30 00 - Tiling
09 63 00 Masonry Flooring
09 63 40.14 Marble Flooring
Marbel flooring tiles, including cement/sand mortar, cuttings,
grouting, jointing polishing and pointing, complete as shown in
drawings and as per specifications.
A 25mm thick marble threshold marfil marble to wet areas 5 lm
B 20mm thick marble threshold, generally 42 lm

09 70 00 Wall Finishes
09 72 00 Wall Coverings
Porcelain wall tiles, including adhesive material, cuttings,
grouting, jointing and pointing, complete as shown in drawings
and as per specifications
C ICT-02 to walls, Crème matt, size 600x600 mm 263 m2

CEILING FINISHES
09 51 00 Acoustical Ceilings
09 53 00 Acoustical Ceiling Suspension Assemblies
09 51 23 Acoustical Tile Ceilings

Acoustic mineral fiber tile ceiling, including galvaized metal


grids, suspension system, accessories, fixing, complete as
shown on drawings and as per specifications

D Size 600x600x15mm , ACT-01 500 m2

TOTAL PAGE (4) - (FINISHING WORK) - (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 31 / DIV. (9) / 4
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

FINISHING WORK (Cont'd):

09 90 00 - Painting and Coating


09 91 00 Painting
(FENOMASTIC HYGIENE OIL PAINT)
Three coats of Anti-bacterial and anti-fungus, stain resistant
based emulsion paint, including but not limited to preparation
works, under-coat, tapes, complete as per drawings and
specifications
Item given by square meters
Paint colors to Engineer approvals
(IPNT-01) (RAL 9010 pure white silk finish paint to interior
A
plastered walls 601 m2
B (IPNT-04) (TAUPE MATT) to interior plastered walls 2
132 m
C To interior gypsum false ceiling & bulkheads 106 m2

Heavy duty high glossy epoxy wall coating to be applied on


smoothed plastered wall finish, complete as shown on
drawings and as per specifications
Item given in square meters
Colors to Engineer approvals
(Ref. 01) To smooth finished plastered walls, externally,
D
parapet walls 220 m2

TRAFFIC COATING

Aliphatic Urethan traffic coating system, applied on reinforced


concrete screed at receiving area, including preparation work,
surface cleaning, grouting, jointing and pointing, complete as
shown in drawings and as per specifications.

Item given by square meters


E To exterior landings, ramps and pathways 90 m2
F To exterior steps 15 m
2

G To exterior loading bay 90 m2

TOTAL PAGE (5) - (FINISHING WORK) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 31 / DIV. (9) / 5
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
CARRIED PAGES GRAND TOTAL (RAL)

COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2
CARRIED FROM PAGE #3
CARRIED FROM PAGE #4
CARRIED FROM PAGE #5

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 31 / DIV. (9) / 6
DIVISION (10) - SPECIALTIES
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 10 - SPECIALTIES
Unit Rate Total Amount
Item Description Quantity Unit
JOD JOD

Preambles:
The item unit rate shall include the followings:
The following requirements are
complementary to the mentioned items in
the B.O.Q;
Supply of materials and equipment.
Off loading and handling from trucks on site
to place of installation (including carnage,
unpacking, erecting in place).
On-site material protection and storage
before installation.
Installation of materials and equipment

All civil works required and related to the


landscape works, such as: equipment, tools,
concrete bases and supports, cutting and
chasing through block and concrete walls
and slabs for passage of conduits, sleeves,
trays, trunking and ladders, excavation and
back-fillings, riggings, hoisting,
waterproofing, cleaning & protection
All labor, materials, tools, instruments,
electric power, water supply, fuel and water
required for work executions, testing, and
commissioning
Preparation of the shop-drawings and As-
built drawings
Preparation of the operation and
maintenance manuals
Samples as required by the Engineer

Maintenance as per the Contract Conditions

Coordination with other specialty


contractors, such as special equipment
supplier(s) and subcontractor(s) etc.

****** *******
SINDALAH NON MANAGERIAL 31 / DIV.10 / 1
STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
JOD JOD
SPECIALTIES
10 21 00 Compartments and Cubicles
10 21 13 Toilet Compartments
Supply and install full package of toilet
cubicles, from TRESPA Panels or approved
equally, (13mm thick), consisting of high-
pressure laminated melamine surfaces
partitions, fixed on a moisture-resistant
particleboard core, with internal supporting
frames and pilasters, including side hinged
openable single leaf laminated doors in
proprietary toilet cubicles, swing type,
comprising hot pressed laminated on both
sides with hardwood lipping and timber jambs
frames, including all necessary fixings,
fittings, accessories, anti-fungus rubber
silicon, supporting system, heavy gauge
stainless steel hardware, stainless steel foot
support, stainless steel mortised lever-turn
indicator bolt with external emergency
released facility, and door closers, complete
as shown on drawings, specifications, and
Engineer's approval of samples
Complete package of Toilets Cubicles
partitions, including:

(By Numbers)
Front Partitions
Overall size 1074mm width x 1950 mm high,
A
Including (1) single leaf hinged door 2 No.
Overall size 2049mm width x 1950 mm high,
B
Including (2) single leaf hinged doors 2 No.
Side partitions
C Size 1400mm width x 1950 mm high 6 No.

10 14 00 Interior Signage
Interior Signage shall be Good rigidity and
tensile strength. Resistant to chemicals and
corrosion and incorporates UV inhibitors to
reduce fading of colors, including fixing,
fittings, accessories, supporting and cleaning,
complete as shown on drawings and as per
specifications
Interior Signage
Quantity enumerated
D SR01 20 No.
E SR02 3 No.
F SR03 4 No.

TOTAL PAGE (2) - (JOD)


SINDALAH NON MANAGERIAL 31 / DIV.10 / 2
STAFF ACCOMMODATION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Item Description Total Amount / JD

COLLECTION

CARRIED FROM PAGE DIV.10 /01 Preambles


CARRIED FROM PAGE DIV.10 /02

Total Carried to Summary (Division 10)


GRAND TOTAL (JOD)
SINDALAH NON MANAGERIAL 31 / DIV.10 / 3
STAFF ACCOMMODATION
DIVISION (21)
FIRE SUPRESSION
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR FIRE SUPPRESSION PACKAGE
DIVISION 21 - FIRE SUPPRESSION WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
The rates and prices for plant, equipment and installations are
to be all inclusive of supply, installation, testing,
commissioning and all associated builders work required for
A. the full operation of such plant, equipment and installations, to
comply in all respects with the Specifications, Drawings and to
the complete satisfaction of Municipality, Local Authorities and
the Engineer.
Builder’s Work shall include for all secondary steelwork
B. supports for plant, equipment, trunking and the like not
specifically shown or indicated on the drawings.
Rates for pipes and ducts generally are to include for all
cuttings, short lengths, back stops, couplers, wooden plugs
and retaining and alignment pegs required in laying and for the
C extra involved over normal trench excavating in hand packing
and tamping selected fine material around the lower half of
the pipes to buttress them against the side of the trench.
Rates are to include for leaving all pipes clean and clear.

Pipes are measured nett as laid and are to include for all
fittings on all types of pipes, extra joints of all types, cuttings,
D waste, fixing with approved holderbats or pipe clips, sleeves
through walls, thrust blocks, etc., for laying in trenches of any
depth, and building in to sides of inspection chambers.

Rates for accessories shall include for concrete surrounds


E
and any additional excavation and disposal.

The total cost for the services shall include for the detail
design, together with the preparation of all necessary
calculations and workshop drawings which, together with all
F manufacturing data shall be submitted to the Consultant for
approval before purchase, manufacture or installation.
Generally including spares for all Mechanical Installation item
as recommended by the manufacturer.

****** *******

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV. (21) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR FIRE SUPPRESSION PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

FIRE SUPPRESSION WORK


21 13 00 Wet-Pipe Sprinkler Systems
A Pendent type Sprinkler 78 No
B Upright type Sprinkler 56 No

21 13 13 Fire Fighting Pipes


C 25mm Dia 309 lm
D 32mm Dia 55 lm
E 40mm Dia 21 lm
F 50mm Dia 30 lm
G 65mm Dia 25 lm
H 80mm Dia 37 lm
J 100mm Dia 11 lm
K 150mm Dia 11 lm

21 12 00 Fire Extinguishers
L FE-1 11 No
M FE-2 4 No

21 05 23 Zone Control Valves


N 31-M-ZCV-01 1 No

21 11 19 Fire-Departments Connections
P SIAMESE CONNECTION 1 No

21 22 16 Clean-Agent Fire-Extinguishing Equipment (Novec


System)
Q MDB room 1 No
R UPS room 1 No
S Transformer room 1 No

TOTAL PAGE (2) - (FIRE SUPPRESSION WORK) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (21) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR FIRE SUPPRESSION PACKAGE
CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (21) / 3
DIVISION (22)
PLUMBING WORK
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR PLUMBING PACKAGE
DIVISION 22 - PLUMBING WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
The rates and prices for plant, equipment and installations are
to be all inclusive of supply, installation, testing,
commissioning and all associated builders work required for
A. the full operation of such plant, equipment and installations, to
comply in all respects with the Specifications, Drawings and to
the complete satisfaction of Municipality, Local Authorities and
the Engineer.
Builder’s Work shall include for all secondary steelwork
B. supports for plant, equipment, trunking and the like not
specifically shown or indicated on the drawings.
The rates for trenches for pipes shall include for disposal and
C backfilling. The rates for drains, inspection chambers, etc., are
to allow for testing.
Rates for pipes and ducts generally are to include for all
cuttings, short lengths, back stops, couplers, wooden plugs
and retaining and alignment pegs required in laying and for the
D extra involved over normal trench excavating in hand packing
and tamping selected fine material around the lower half of the
pipes to buttress them against the side of the trench. Rates are
to include for leaving all pipes clean and clear.

Pipes are measured nett as laid and are to include for all
fittings on all types of pipes, extra joints of all types, cuttings,
E waste, fixing with approved holderbats or pipe clips, sleeves
through walls, thrust blocks, etc., for laying in trenches of any
depth, and building in to sides of inspection chambers.

Rates for fittings on all types of drain pipes are to include for
F
extra joints of all types and cutting and waste on all pipes.

Rates for accessories shall include for concrete surrounds and


G
any additional excavation and disposal.
Prices and rates for insulation shall include for insulation to all
H
fittings, flange boxes, valve boxes, etc and around all supports.

The rates for sanitary fittings and the like, unless otherwise
described, shall be deemed to include all accessories,
assembling component parts including suitable bedding
compounds, all necessary plugging and brass screwing, fixing
I accessories, joints to water services with straight or bent
proprietary connectors, joints to waste soils or drain pipes
with approved proprietary connectors, cleaning off all
protective wrappers and leaving ready for use and leaving taps
and valves greased, clean and in full working order.

****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (22) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR PLUMBING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
PLUMBING WORK
22 13 16 - Sanitary Soil, Waste, Vent, and CDP pipes
Above Ground Pipes
Waste Pipe
A 50mm dia 45 ml
B 82mm dia 12 ml
Soil Pipe
C 50mm dia 6 ml
D 110mm dia 12 ml
Vent Pipe
E 50mm dia 230 ml
F 82mm dia 17 ml
Rain Pipe
G 110mm dia 53 ml
Condesate Drain Pipe
H 32mm dia 23 ml
Below Ground Pipes
Waste Pipe
J 50mm dia 63 ml
K 82mm dia 23 ml
L 110mm dia 188 ml
Soil Pipe
M 110mm dia 41 ml
Vent Pipe
N 50mm dia 21 ml
Condesate Drain Pipe
P 32mm dia 19 ml
Q 50mm dia 3 ml

22 14 26 - Roof Drains
R Rain Water Outlet 4'' 6 No.
S Emergency Rain Water Outlet 4'' 6 No.
22 05 76 - Facility Drainage Piping Cleanouts
T 4'' Floor Clean Out 12 No.
22 13 16 - Traps
U Floor Drain 3'' 11 No.
V Kitchen Drain 350X350 18 No.
W Kitchen Drain 450X350 18 No.
X Kitchen Drain 1000X300 1 No.
Y Kitchen Drain 1350X350 2 No.
Z Kitchen Drain 1550X350 2 No.
AA Kitchen Drain 950X650 2 No.
22 13 19 - Sanitary Drains
BB Funnel drain 17 No.
TOTAL PAGE (2) - (PLUMBING WORK) - (SAR)
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (22) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR PLUMBING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

PLUMBING WORK (Cont'd):


22 00 00 - Manholes
A 31-M-MH-01 (600x600mm) 1 No.
B 31-M-MH-02 (600x600mm) 1 No.

22 00 00 - Gully Trap
C Gully Trap 1 No.

22 33 33 - Electric Domestic Water Heaters


D 31-M-EWH-01 1 No.
E 31-M-EWH-02 1 No.

22 13 23 - GREACE INTERCEPTOR
F Greace Interceptor 1 No.

22 11 13 - Facility Water Distribution Piping


Above Ground Cold Water Pipes
G 20mm Dia 228 ml
H 25mm Dia 33 ml
J 32mm Dia 46 ml
K 40mm Dia 20 ml
L 50mm Dia 20 ml
M 63mm Dia 16 ml
N 75mm Dia 18 ml
P 90mm Dia 4 ml
Above Ground Hot Water Pipes
Q 20mm Dia 277 ml
R 25mm Dia 55 ml
S 32mm Dia 12 ml
T 40mm Dia 22 ml
U 50mm Dia 12 ml
V 63mm Dia 12 ml

22 13 16 - Vent Flashings and Caps


W Vent cap ( Vent Cowl ) 4 No.

22 31 00 - Water Softener
X 31-M-SF-01 1 No.

TOTAL PAGE (3) - (PLUMBING WORK) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (22) / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR PLUMBING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit SAR SAR

PLUMBING WORK (Cont'd):

22 42 00 - Commercial Plumbing Fixtures


Sanitary Fixtures
A Wash Basin 10 No.
B WC 6 No.
C Sink 12 No.
D Hand spray 6 No.
Sanitary Mixers
E Wash Basin 10 No.
F Sink 12 No.

22 11 23 - CIrculation Pumps
G 31-M-HWRP-01 1 No.
H 31-M-HWRP-02 1 No.

TOTAL PAGE (4) - (PLUMBING WORK) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (22) / 4
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR PLUMBING PACKAGE
CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2

CARRIED FROM PAGE #3

CARRIED FROM PAGE #4

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (22) / 5
DIVISION (23)
HEATING, VENTILATION & AIR CONDITIONING
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR MECHANICAL PACKAGE
DIVISION 23 - HEATING, VENTILATING AND AIR CONDITIONING WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
The rates and prices for plant, equipment and installations are
to be all inclusive of supply, installation, testing,
commissioning and all associated builders work required for
A. the full operation of such plant, equipment and installations, to
comply in all respects with the Specifications, Drawings and to
the complete satisfaction of Municipality, Local Authorities and
the Engineer.
Builder’s Work shall include for all secondary steelwork
B. supports for plant, equipment, trunking and the like not
specifically shown or indicated on the drawings.

Rates for pipes and ducts generally are to include for all
cuttings, short lengths, back stops, couplers, wooden plugs
and retaining and alignment pegs required in laying and for the
C extra involved over normal trench excavating in hand packing
and tamping selected fine material around the lower half of
the pipes to buttress them against the side of the trench.
Rates are to include for leaving all pipes clean and clear.

A Prices and rates for ductwork shall include for all bends,
hangers, vanes, Splitters, dampers, accessories flexible
D connections, joints, waste, seams, stiffeners, bracing, access
doors, sleeves, acoustic sleeves and all items include in the
sections of the specifications.
Prices and rates for insulation shall include for insulation to
E all fittings, flange boxes, valve boxes, etc and around all
supports.
The total cost for the services shall include for the detail
design, together with the preparation of all necessary
calculations and workshop drawings which, together with all
F manufacturing data shall be submitted to the Consultant for
approval before purchase, manufacture or installation.
Generally including spares for all Mechanical Installation item
as recommended by the manufacturer.

****** *******

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 032 / DIV. (23) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR HEATING, VENTILATING AND AIR CONDITIONING WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

HEATING, VENTILATING AND AIR CONDITIONING WORK


23 73 13 Air Handling Unit (AHU)
A 31-M-AHU-01 1 No
B 31-M-AHU-02 1 No
C 31-M-AHU-03 1 No
D 31-M-AHU-04 1 No
E 31-M-EAHU-01 1 No
F 31-M-FAHU-01 1 No
23 62 00 - Condensing Unit
G 31-M-CU-01 1 No
H 31-M-CU-02 1 No
J 31-M-CU-03 1 No
K 31-M-CU-04 1 No
L 31-M-CU-05 1 No
M 31-M-CU-06 1 No

23 34 16 Exhaust and Fresh Fans


N 31-M-EF-01 1 No
P 31-M-EF-02 1 No
Q 31-M-EF-03 1 No
R 31-M-EF-04 1 No
S 31-M-EF-05 1 No
T 31-M-EF-06 1 No
U 31-M-EF-07 1 No
V 31-M-FF-01 1 No
W 31-M-FF-02 1 No
23 34 16 Ecology Unit
X 31-M-ECU-01 1 No
23 09 23 Variable Air Volume Box
Y 31-M-VAV-01 1 No
Z 31-M-VAV-02 1 No
AA 31-M-VAV-03 1 No
BB 31-M-VAV-04 1 No
CC 31-M-VAV-05 1 No
DD 31-M-VAV-06 1 No
EE 31-M-VAV-07 1 No
FF 31-M-VAV-08 1 No
GG 31-M-VAV-09 1 No
HH 31-M-VAV-10 1 No
JJ 31-M-VAV-11 1 No
KK 31-M-VAV-12 1 No
LL 31-M-VAV-13 1 No
MM 31-M-VAV-14 1 No
NN 31-M-VAV-15 1 No
PP 31-M-VAV-16 1 No
QQ 31-M-VAV-17 1 No
TOTAL PAGE (2) - (MECHANICAL WORK) - (SAR)
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 032 / DIV. (23) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR HEATING, VENTILATING AND AIR CONDITIONING WORKS
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
MECHANICAL WORK (Cont'd):
23 62 13 DX Type Air Conditioning Unit (Indoor/Outdoor)
A 31-M-SRAC-01 4 No
B 31-M-SRAC-02 3 No
23 31 13 Rectangular Metal Ducts
C Gauge 22 1,889 Kg
D Gauge 24 3,027 Kg
E Gauge 26 957 Kg
23 07 13 Insulation ductwork
F Indoor insulation 816 m2
G Outdoor insulation 284 m2
23 37 13 Air Outlets
Supply Diffuser
H 31-M-SD-01 (150x150) 6 No
J 31-M-SD-02 (230x230) 12 No
K 31-M-SD-03 (300x300) 4 No
L 31-M-SD-04 (380x380) 35 No
Return Diffuser
M 31-M-RD-01 (230x230) 6 No
N 31-M-RD-02 (300x300) 2 No
31-M-RD-03 (380x380) 20 No
Exhaust Grille
P 31-M-EG-01 (150x150) 10 No
Q 31-M-EG-02 (200x200) 1 No
R 31-M-EG-03 (250x250) 1 No
Exhaust Side Grille
S 31-M-SEG-01 (400x200) 2 No
Supply Side Grille
T 31-M-SSG-01 (400x200) 2 No
23 37 15 Fresh and Exhust Air Louver
U 500x500 FAL (Sand Trap) 2 No
V 1500x1200 FAL (Sand Trap) 1 No
W 1300x700 FAL (Sand Trap) 1 No
X 3000x1300 FAL (Sand Trap) 1 No
Y 1000x250 FAL (Sand Trap) 1 No
Z 1000x700 FAL (Sand Trap) 1 No
AA 3000x1600 EAL 1 No
LPG Piping Network
BB 20mm Dia 11 lm
CC 25mm Dia 32 lm
DD 23 05 02 BMS LS LS
TOTAL PAGE (3) - (MECHANICAL WORK) - (SAR)
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 032 / DIV. (23) / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR HEATING, VENTILATING AND AIR CONDITIONING WORKS

CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2

CARRIED FROM PAGE #3

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 032 / DIV. (23) / 4
DIVISION (26)
ELECTRICAL WORK
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ELECTRICAL PACKAGE
ELECTRICAL DIVISION 26 - ELECTRICAL

Item Description Quantity Unit Unit Rate Total Amount


SAR SAR
Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the mentioned items
in the B.O.Q;
The rates and prices for plant, equipment and installations are to be all
inclusive of supply, installation, testing, commissioning and all
associated builders work required for the full operation of such plant,
A
equipment and installations, to comply in all respects with the
Specifications, Bill of Quantities, Drawings and to the complete
satisfaction of Municipality, Local Authorities and the Engineer.
B Prices and rates shall include for the following:
a) Marking positions of holes, mortices, chases, etc.
b) Cutting and pinning ends of supports to structures.
c) Painting as required.
d) Fixings, including all steelwork, supports, slips holderbats and
hanges.
e) Joints, bolts, washers, nuts, junctions and everything necessary for
the satisfactory jointing of pipes or ducts to each other, to items of
equipment or connecting ducts to voids, shafts etc.

f) All waste, cuttings, short lengths etc.


g) Labels, nameplates, belt guards and all accessories called for in the
specification.
h) Rates for conduit are to include for all necessary accessories
including conduit Boxes
i) Pipe sleeves through walls.
j) Draw wires in empty conduits.
Cable trunking and tray items are to include for complete installation
C
as required.

Rates for cable terminations are to include for terminations are to


D include for Termination glands, lock nuts, drilling entries into
equipment, lugs, earth tags, spreader boxes, etc. where applicable.

All items containing equipment, accessories and fittings shall include


E
for earth Terminals and bonding as necessary.
Rates for main voltage sub-circuits shall include for each continuity
F
conductor.
Rates for main and sub-main distribution boards shall include for all
G
spares as Specified.
The total cost for the services shall include for the detail design,
together with the preparation of all necessary calculations and
H workshop drawings which, together with all manufacturing data shall
be submitted to the Consultant for approval before purchase,
manufacture or installation.
The cable and conduit to sub-main circuits are to be enumerated and
any vertical or horizontal cable required for connections, loops, etc. at
I
equipment, appliances, control gear or the like will be deemed to be
included.
The Tenderer shall include for the supply of manufacturers
recommended spares in accordance with the Specification for all
J Electrical/ Mechanical Engineering Installations to be handed to the
Engineer and shall submit details of spares to be provided by him on a
separate sheet accompanying his tender submission.

TOTAL PAGE (1) - (ELECTRICAL) - (SAR) ****** *******


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (26) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ELECTRICAL PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
26 12 00-MEDIUM-VOLTAGE TRANSFORMERS
A Transformer-1, 1000 KVA,33KV/0.400KV,dry type 1 No.
26 13 00-MEDIUM-VOLTAGE SWITCHGEAR
B Medium-Voltage Switchgear 1 No.

26 24 00-SWITCHBOARDS AND PANELBOARDS


26 24 13-Incoming Switchboards
C MDB-31-01 1 No.
26 24 16-Panelboards
D LP-31-01 1 No.
E PP-31-01 1 No.
F PPK-31-01 1 No.
G PPK-31-02 1 No.
H PPK-31-03 1 No.
J PPK-31-04 1 No.
K UPP-31-01 1 No.
L ECBS-31-01 1 No.
M DP-31-01 1 No.
N DPK-31-01 1 No.
P UDP-31-01 1 No.

26 24 19-Motor Control Centers


Q MCP-31-01 1 No.
R MCPK-31-01 1 No.
26 43 13-Surge Protective Devices
S 4 POLE 100KA SURGE ARRESTOR 1 No.
26 35 00-POWER FILTERS AND CONDITIONERS
26 35 13-Capacitors
T Capacitor Bank -300KVAR 1 No.
26 09 00-INSTRUMENTATION AND CONTROL FOR ELECTRICAL SYSTEMS
26 09 13-Electrical Power Monitoring
U Digital Meter 6 No.
26 05 00-COMMON WORK RESULTS FOR ELECTRICAL
26 05 13-Medium Voltage Cables
V 3C x 70mm2CU/ XLPE/SWA/PVC 40 m
26 05 00-COMMON WORK RESULTS FOR ELECTRICAL
26 05 19-Low Voltage Cables
W 4X6+1X6mm2 CU/XLPE/PVC 130 m
X 4X10+1X10mm2 CU/XLPE/PVC 100 m
Y 4X16+1X16mm2 CU/XLPE/PVC 50 m
Z 4X35+1X16mm2 CU/XLPE/PVC 50 m
AA 4X25+1X16mm2 CU/XLPE/PVCC 110 m
BB 4X70+1X35mm2 CU/XLPE/PVC 23 m
CC 4X300+1X150mm2 CU/XLPE/PVC 10 m
DD 1X630mm2 CU/XLPE/AWA/PVC 95 m
EE 4X120+1X70mm2 CU/XLPE/PVC 35 m
FF 4X95+1X50mm2 CU/XLPE/PVC 5 m
GG 3X4mm2 CU/XLPE/PVC 330 m
HH 5X4mm2 CU/XLPE/PVC 53 m
JJ 150mm CU/XLPE/PVC 14 m

TOTAL PAGE (2) - (ELECTRICAL) - (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV. (26) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ELECTRICAL PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

26 05 26-Grounding and Bonding for Electrical Systems LS

26 05 36-Cable Trays For Electrical Systems


A 900 mmx 100 mm GI Cable Tray 15 m
B 600 mmx 100 mm GI Cable Tray 25 m

26 41 00-FACILITY LIGHTING PROTECTION


26 41 13-Lightning Protection For Structure LS

26 27 00-LOW-VOLTAGE DISTRIBUTION EQUIPMENT


26 27 26-Wiring Devices
26 27 26.10-Low Voltage Switching
C 1-gang, 1-way light switch 34 No.
D 1-gang, 2-way light switch 20 No.
E 2-gang, 1-way light switch 1 No.
F Grid Switch 1 No.
26 27 26.20-Switch Points
G Switch Points 55 No.
26 27 26.30-Wiring Devices Elements
H 13A Single Switched Socket Outlet 118 No.
I 13A Twin Switched Socket Outlet 4 No.
J 13A Single Switched Socket Outlet W/P 59 No.
20A ceiling mounted industrial socket outlet 2P+E220V,IPA,60 HZ,IP44,
K 4 No.
plug
L Feeding for chiller and freezer rooms control panels 12 No.
M 20A, spur outlet, ceiling mounted, switched, IP-20 18 No.
N 20A, spur outlet, wall mounted, switched, IP-20 7 No.
P Power feeding point 26 No.

26 28 16-Enclosed Switches and Circuit Breakers


Q 32A 1 Phase Isolator, IP65, pedestial type 4 No.
R 63A 3 Phase Isolator, IP65, pedestial type 1 No.
S 20A 1 Phase Isolator, IP65, pedestial type 17 No.
T 20A 3 Phase Isolator, IP65, pedestial type 6 No.
U 100A 3 Phase Isolator, IP65, pedestial type 1 No.
V 150A 3 Phase Isolator, IP65, pedestial type 1 No.
W 20A 1 Phase Isolator, IP54 11 No.
X 20A 3 Phase Isolator, IP54 10 No.
Y 32A 3 Phase Isolator, IP54 4 No.
Z 40A 3 Phase Isolator, IP54 2 No.
AA 80A 3 Phase Isolator, IP54 3 No.
BB 63A 3 Phase Isolator, IP54 1 No.
CC 250A 3 Phase Isolator, IP54

TOTAL PAGE (3) - (ELECTRICAL) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (26) / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ELECTRICAL PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

26 33 00-BATTERY EQUIPMENT
26 33 24-DC Central Battery System Equipment For Emergency Lighting
A 3 KVA Electrical Central Pattery 1 No.
26 33 53-Static Uninterruptible Power Supply
B 40 KVA UPS 1 No.

26 51 00-INTERIOR LIGHTING
26 51 19.10-Led Interior Lighting
C L2S 41 No.
D L3S 1 No.
E L5S 18 No.
F D1 8 No.
G D2 14 No.
H D7 3 No.
J B2 17 No.
K B3 2 No.
L L12 33 No.
M L2SE 24 No.
N L5SE 6 No.
P D1E 2 No.
Q D2E 9 No.
R B2E 9 No.
S B3E 2 No.
T L3SE 1 No.
U L12E 12 No.
V 8w led, Ceiling mounted exit sign with indicates the escape direction 10 No.
W 8w led, wall mounted exit sign with indicates the escape direction 7 No.

26 51 19.20-Wiring (Interior Lighting Points)


X Interior Lighting Points 149 No.

26 52 00-SAFTY LIGHTING
26 52 13-Emergency and Exit Signs
26 52 13.13.10-Wiring(Emergency Lighting Points)
Y Emergency Lighting Points 65 No.
26 52 13.13.20-Wiring(Emergency Lighting Points)
Exit Lighting Points 17 No.

26 56 00-EXTERIOR LIGHTING
26 56 13.10-Lighting Poles and Standards
Z BH1 9 No.
26 56 13.20-Wiring (Exterior Lighting Points)
AA External Lighting Points 9 No.

26 09 00-INSTRUMENT AND CONTROL FOR ELECTRICAL SYSTEM


26 09 23-Lighting Control Devices
AB Occupancy sensor 21 No.
TOTAL PAGE (4) - (ELECTRICAL) - (SAR)
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (26) / 4
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR PLUMBING PACKAGE

CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2

CARRIED FROM PAGE #3

CARRIED FROM PAGE #4

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (26) / 5
DIVISION (27)
COMMUNICATIONS
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ICT\ELV PACKAGE
ELECTRICAL DIVISION 27 - COMMUNICATION
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
27 COMMUNICATIONS

271105 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS


(TIA)

Supply, installation, testing, commissioning, putting into


satisfactory operation and handing over complete
Communication Equipment Room Fittings ; including all
necessary accessories, fittings, Support, fixation, cable
bonding and labelling, cable management, licenses and all
required software ; complete; As shown on drawings and
described in specifications

Telecommunications Equipment Racks

Freestanding Cabinet, door & ventilation provisions as specified;


A 2 No.
800 x 1000 mm; 42 RU ;

271305 - COMMUNICATIONS BACKBONE CABLING (TIA)

Supply, installation, testing, commissioning, putting into


satisfactory operation and handing over complete
communication backbone cabling ; including all necessary
accessories, fittings, Support, fixation, cable bonding and
labelling, cable management, licenses and all required
software ; complete; As shown on drawings and described
in specifications

Backbone Cables: SMF Fiber Optic; Type OS2; suitable for


indoor use as specified;

12-Core; SMF Type OS2; as specified; for the Connection


B from the Telecom Room to Tie-in Connection with Infra
package

4-Core; SMF Type OS2; from FACP to Tie-in Connection with


C
Infra Package

Main and Intermediate Cross-Connects, as specified

D 12-Port, SMF, Fiber Optic Patch Panels; 4 No.

TOTAL PAGE (1) - ( COMMUNICATION) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (27) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR COMMUNICATION
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
271505 - COMMUNICATIONS HORIZONTAL CABLING (TIA)

Supply, installation, testing, commissioning, putting into


satisfactory operation and handing over complete
communication horizontal cabling ; including all necessary
accessories, fittings, Support, fixation, cable bonding and
labelling, cable management, licenses and all required
software ; complete; As shown on drawings and described
in specifications

Telecommunications Outlets/Connectors

A Simplex (1) Data Outlet ; Wall Mounted 14 No.

B Duplex (2) Data Outlet ; Wall Mounted 29 No.

C Duplex (2) Data Outlet ; Ceiling Mounted 29 No.

C Duplex (2) Data Outlet ; Floor Mounted 2 No.

D Horizontal Cross-connects:

E 48-Port, Cat 6A, RJ45; fully equipped; Patch Panels; 2 No.

F 24-Port, Cat 6A, RJ45; fully equipped; Patch Panels; 1 No.

272109 - DATA COMMUNICATIONS

Supply, installation, testing, commissioning, putting into


satisfactory operation and handing over complete
communication horizontal cabling ; including all necessary
accessories, fittings, Support, fixation, cable bonding and
labelling, cable management, licenses and all required
software ; complete; As shown on drawings and described
in specifications

Active Communications and Data Processing Equipment

G 48-Ports Access data switches ; 2 No.

H 24-Ports Access data switches ; 1 No.

TOTAL PAGE (2) - ( COMMUNICATION) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (27) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR COMMUNICATION
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
272133 - WIRELESS DATA NETWORK

Supply, installation, testing, commissioning, putting into


satisfactory operation and handing over complete Wireless
Data Network ; including all necessary accessories, fittings,
Support, fixation, cable bonding and labelling, cable
management, licenses and all required software ; complete;
As shown on drawings and described in specifications

Wireless data network components

A Wireless Radio Access points; Pendant 11 No.

273123 - IP-BASED TELEPHONY COMMUNICATIONS SYSTEM

Supply, installation, testing, commissioning, putting into


satisfactory operation and handing over complete IP-
Telephony System ; including all necessary accessories,
fittings, Support, fixation, cable bonding and labelling, cable
management, licenses and all required software ; complete;
As shown on drawings and described in specifications

IP Phones

B IP Phone, Standard Phone; as specified; 2 No.

C IP Phone, Wall-Mounted Phone; as specified; 14 No.

TOTAL PAGE (3) - ( COMMUNICATION) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (27) / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR COMMUNICATION

CARRIED PAGES GRAND TOTAL (SAR)

COLLECTION

CARRIED FROM PAGE #1


********
CARRIED FROM PAGE #2

CARRIED FROM PAGE #3

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV. (27) / 4
DIVISION (28)
ELECTRONIC SAFETY & SECURITY
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SEC\FPR PACKAGE
ELECTRICAL DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
28 ELECTRONIC SAFETY AND SECURITY

281300 - ACCESS CONTROL SOFTWARE AND DATABASE


MANAGEMENT &
281500 - ACCESS CONTROL HARDWARE DEVICES

Central (Headend) System Components;

Supply, install, testing, commissioning, put into operation


Access Control System components complete with cables,
wires, as indicated in related plans, specifications and all
related contract documents including all necessary
accessories for fully functional integrated system.

Controllers: (ACP’s);

A Main Controller; 3 No.

B Entry-Control Annunciation Controller 11 No.

Card readers

C Proximity Readers 6 No.

D Biometric Readers 5 No.

Miscellaneous Access Control Devices & Sub-systems;

E Door and gate hardware interface; Item

F Door Contact 15 No.

TOTAL PAGE (1) - (ELECTRONIC SAFETY AND SECURITY) - (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV. (28) / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ELECTRONIC SAFETY AND SECURITY
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
282000 - VIDEO SURVEILLANCE

Supply, install, testing, commissioning, put into operation


Video Surveillance System components complete with
cables, wires, as indicated in related plans, specifications
and all related contract documents including all necessary
accessories for fully functional integrated system.

CCTV cameras & accessories


Fixed camera, 5 Megapixel Resolution; Wall Mounted;
A 10 No.
Weather Proof;
PTZ camera, 5 Megapixel Resolution; Wall Mounted; Weather
B 4 No.
Proof;
Fixed camera, 5 Megapixel Resolution; Ceiling/Pendant
C 22 No.
Mounted;

284621.11 - DIGITAL, ADDRESSABLE FIRE ALARM SYSTEMS


Control Panels;

Supply, install, testing, commissioning, put into operation


Fire Alarm System components complete with cables,
wires, as indicated in related plans, specifications and all
related contract documents including all necessary
accessories for fully functional integrated system.
D Fire Alarm Control Panel (FACP); with NAC 1 No.

Miscellaneous system components

E Network communications; as specified; Item


F Digital alarm communicator transmitter (Auto Dialer); Item

G Interface to PA/VA system, as specified; Item

Fire-alarm signal initiation devices and systems;


H Manual fire alarm stations; 10 No.
J Smoke detectors, photoelectric type; 51 No.
K Heat Detector, 4 No.
K Carbon Monoxide Detector, 6 No.
L Duct smoke detectors; 1 No.
M Multicriteria Detector 1 No.
Audiovisual notification appliances,

N Combination device: Horn/Strobe unit; 15 No.


P Strobe lights; 2 No.

TOTAL PAGE (2) - (ELECTRONIC SAFETY AND SECURITY) - (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV. (28) / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ELECTRONIC SAFETY AND SECURITY
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Addressable interface devices


A Control modules; 3 No.

B Monitoring modules; 12 No.

C Line isolation modules; 7 No.

285111 - DISABLED PERSON TOILET ALARM SYSTEM

Supply, install, testing, commissioning, put into operation


Disabled person toilet alarm system components complete
with cables, wires, as indicated in related plans,
specifications and all related contract documents including
all necessary accessories for fully functional integrated
system.

D Handy Capped Toilet Alarm Panel (HTAP) 2 No.


E Pull cord 2 No.
F Reset Point 2 No.
G Overdoor Light and Sounder Unit 2 No.
H Panic Bar 2 No.

TOTAL PAGE (3) - (ELECTRONIC SAFETY AND SECURITY) - (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / DIV. (28) / 3
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR ELECTRONIC SAFETY AND SECURITY

CARRIED PAGES GRAND TOTAL (RAL)

COLLECTION
CARRIED FROM PAGE #1 ********
CARRIED FROM PAGE #2

CARRIED FROM PAGE #3

GRAND TOTAL CARRIED TO GRAND SUMMARY (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / DIV. (28) / 4
Division 31 - Earthwork
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
DIVISION 31 - EARTHWORK
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

Preambles:
The item unit rate shall include the followings:
The following requirements are complementary to the
mentioned items in the B.O.Q;
A. Supply of materials and equipment.

Off loading and handling from trucks on site to place of


B.
installation (including carnage, unpacking, erecting in place).

C On-site material protection and storage before installation.


D Installation of materials and equipment

All civil works required and related to the landscape works,


such as: equipment, tools, concrete bases and supports,
cutting and chasing through block and concrete walls and
E
slabs for passage of conduits, sleeves, trays, trunking and
ladders, excavation and back-fillings, riggings, hoisting,
waterproofing, cleaning & protection

All labor, materials, tools, instruments, electric power, water


F supply, fuel and water required for work executions, testing,
and commissioning
G Preparation of the shop-drawings and As-built drawings
H Preparation of the operation and maintenance manuals
J Samples as required by the Engineer
K Maintenance as per the Contract Conditions
Coordination with other specialty contractors, such as special
L
equipment supplier(s) and subcontractor(s) etc.

****** *******
SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / Div. 31 / 1
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR

EARTHWORK

31 23 16 Excavation

General Excavation Work


General Excavation in any kind of soil & rocks and the like, for
pits, footings and the like, starting from natural ground level
(NGL) down to the level of base course level below slab on
grade down & to bottom of plain concrete blinding of footings,
price should including hand excavation where necessary to
design levels, with cart-away the surplus material from site
to an approved dumping area, complete as shown on
drawings and as specifications

Quantity given by qubic meters


General excavation work for foundation, pits, trenches and
A
the like, starting from natural ground level (NGL) 1,060 M3

31 23 23 Fill
31 23 23.13 Backfill

Supply, lay-on and compact well selected & Engineering


approved filling materials, price should include filling in
layers, 20 cm each layer, (Compaction to 95% according to
AASHTO T-199), the Lab test results should be submit to
Engineer for approval, filling should be to the required level
according to design drawings, and as per specifications

Quantity given by qubic meters


Selected & approved filling materials between footings &
B
walls to reduce levels 525 M3
250mm thick, crushed stone sub-base filling below concrete
C
SOG. & Ramp on grade 362 M3
Backfill shall not be executed unless the waterproofing layer
for concrete walls and its protection shall be officially taking-
over by the Engineer

TOTAL PAGE (2) - (SAR)


SINDALAH NON MANAGERIAL
STAFF ACCOMMODATION 031 / Div. 31 / 2
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
BILL OF QUANTITIES FOR SKELETON & FINISHING PACKAGE
Unit Rate Total Amount
Item Description Quantity Unit
SAR SAR
COLLECTION - EXCAVATION & BACKFILL
CARRIED FROM PAGE DIV.31 /01 ******** ********

CARRIED FROM PAGE DIV.31 /02

Total Carried to Summary (Division 31)


GRAND TOTAL (SAR)

SINDALAH NON MANAGERIAL


STAFF ACCOMMODATION 031 / Div. 31 / 3
GENERAL SUMMARY
DINING HALL BUILDING
(031)
SINDALAH NON MANAGERIAL STAFF ACCOMMODATION
NEOM - KINGDOM OF SAUDI ARABIA
SKELETON & FINISHING PACKAGE
DINING HALL BUILDING (031) - GENERAL SUMMARY
Div. Description Total Amount (SAR)

GENERAL SUMMARY
00 GENERAL PROJECT REQUIREMENTS
01 GENERAL REQUIREMENTS
02 EXISTING CONDITIONS
03 CONCRETE
04 MASONRY
05 METALS
06 WOOD, PLASTICS, AND COMPOSITES
07 THERMAL AND MOISTURE PROTECTION
08 OPENINGS
09 FINISHES
10 SPECIALTIES
11 EQUIPMENT
12 FURNISHINGS
13 SPECIAL CONSTRUCTION
14 CONVEYING EQUIPMENT
21 FIRE SUPPRESSION
22 PLUMBING
23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
25 INTEGRATED AUTOMATIONS
26 ELECTRICAL
27 COMMUNICATIONS
28 ELECTRONIC SAFETY AND SECURITY
31 EARTHWORKS
32 EXTERIOR IMPROVEMENTS
33 UTILITIES
34 TRANSPORTATIONS
35 WATERWAY AND MARINE CONSTRUCTION
40 PROCESS INTEGRATION
41 MATERIAL PROCESSING AND HANDLING EQUIPMENT
42 PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
43 PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE EQUIPMENT
44 POLLUTION AND WASTE CONTROL EQUIPMENT
45 INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT
46 WATER AND WASTEWATER EQUIPMENT
48 ELECTRICAL POWER GENERATION

Total Carried to Grand Summary (SAR)