Professional Documents
Culture Documents
MTC 4 OTg 5
MTC 4 OTg 5
No.4127 of 2022
CORAM:
Shri Ashok Member
APPEARAN
Shri Nitin J Complainant
Shri. Nitin Respondent
PaEe I of 2l'^/'
-
HAR
GURUGRAM No.4127 of 2022
Sr. I Particulais
No.
lDetairs
the project Esencia", Sector-67,
Nature ofproject
17.t0.2077
", Block-D
of complaintl
2198.00 sq.ft.
Allotment ietter
of complaint)
1B of complaint)
nt and
PaEe 2 of 21
RA
No.4127 of 2022
w ;'" ;laim
extension of time for
struction of the Unit
by
of delay coused
reosons Stated above.
wqy of
sholl lie against
of deloy in honding
Unit on occount of
reasons.......(to be
of complaint.)
ofpossession I 22.06.L0r6
Page 3 of 2t
MHARERA
#- ounuennv Complaint No. 4127 of 2022
Page 4 of27
ffiHARERA
HeunuennH,r Complaint No. 4127 of 2022
IV, That on 31.03 016 as per the demand of the respondent, the
complainant d an amount of Rs.7,23,04,632/-. The complainant
in order to I her part of obligation and making the balance
payment took a home loan of Rs.16,1,9,549/- from ICICI Bank, which
was sanctioned and the loan was then disbursed by the bank in the
name ofthe res ondent.
That Builder Buyer ement was executed between the
complainant Ans ructure Pvt. Ltd. on 22.06.2013.
As per clause 5 of the sa ment, the respondent was bound
to handover p no \rnit within 36 months with an
extended peri mo m the date of execution of the
builder buv ent.
VI. It is pertinen mention t thb work at the project site started
with a very ce. U n noticing such delay in work the
complainant s sln nldence upon the credibility ot
of the
th
l.ta,-^
respondent. Fo was no communication from the
respondent al ut the of the project. When the
complainant de verific r about the progress of the said
project, to the ock of the plainant, the said project was much
delayed. But responde .t kept on demanding the instalments,
keeping the co plainant i dark about the actual progress of the
unit.
VII, That on 15. .2018, th complainant's husband Mr. Atul
Dhandhania th wrote an mail enquiring about the delivery and
status of the co ction. e sa[d e-mail was then replied by the
respondent on 6.07.20L8 the most vague manner and with an
Page 5 of 21
HARERA
MGURUGRAM Com1laint No. 4727 of 2022
Page 6 ofZl
HARERA
MGURUGRAM Complaint No. 4127 of 2022
PageT of 21
|
ffi HARERA
#- eunuennvr Complaint No. 4727 of 2022
the occupanry rtificate has not been issued. That as on date, the
unit is comple in all aspect and the respondent has already offered
possession to e complainant subject to payment of the due after
adjustment of e delay possession charges in terms of the floor
buyer agreem t. Therefore, in such circumstances where the
construction of e unit is already complete and the consideration
paid by the co plainant in lieu of the floor buyer agreement has
been utilized in constr unit, the direction for refund of
the considerati n paid by e complainant towards the unit would
be against the i erest ofjustice and settled proposition of Iaw.
VII. It is submitted at due to license granted for additional land, the
layout plan of t e housing prorect developed by the respondent was
Page 8 of21
HARERA
P-GURUG:IAI/ complaint No. 4127 of 2022
respondent.
x. Other than th e r6a3ons, the delay in handing over the
possession o has been caused due to the various reasons
which were nd the control of the respondent. Following
important a are relevant which are submitted for the kind
consideration o eau thority:
I El^^--,/ rlhi+- -^-i^.,-t.,
I
PaEe 9 of 27
HARERA
MGURUGRAM Complaint No. 4127 of 2022
Page 10 of21
ffiHARERA
S-eunLLennH,r Complaint No. 4127 of 2022
6. Copies of all the rel nt documpnts have been filed and placed on the
record. Their authen city is not [n dispute. Hence, the complaint can be
Page 11 ol21
ffiHAR
ffi eunui Cornplaint No. 4127 of 2022
E. furisd ofthe
7. The thority that it well as subject matter
juri on to ad, icate the mp t for the reasons given
bel
E. I erritorial ction
8. As per notification 1/e d 74.12.2077 issued by
'fown d Country Pl th e sdiction of Real Estate
Regula ry Authority, urugram District for all
purp with the present case, the
project inq ng area of Gurugram
Di torial jurisdiction to
deal the
E. II
9. Section 11(a)(a) of the promoter shall be
respo le to the Section 11(4)(a) is
reprod ash
77
(4) The RU
(a) be responsible functions under
e provisions ol Act or the made thereunder
to the allottees per the to the qssociation of
lottees, as the may be, all the aportment'
or as the case or the common
to the ofa quthoriD), os the
may be;
3 oJ the
PaEe 12 of 2l
ffiHARERA
#- eunuennH,r complaint No. 4127 of 2022
later stage.
11. Further, the authority has no hitch in proceeding with the complaint and
l
Ilnion of lndia & others SLP (Civil) No. 73005 of 2020 decided on
12.05,2022wherein it has been laid down as under:
l
"86. From the sclfume of the Act ofwhich a detailed reference has been
made ond taking note of power of oqjudication delineated with the
regulatory authority ond adjudtcating olfrcer, what finally culls out is
that although the Act indicatet the dlstinct expressions like refund',
'interest', 'penaly' ond 'compenffition', o conjoint reoding ofSectrcns 1B
ond 19 cleorly mpnifesB that yhen it comes to refund of the omounL
and interest on the refund omoqn| or directing paymenl of interest for
delayed delivery lf possession, dr penolty ond interest thereon, it is the
regulotory autholi\t which hos tfe powbr to exomine and determine the
ouLcome of o colplainL At the lome time, when it comes to o quesLion
of seeking the relief of adjudging compensation qnd interest thereon
under Sections 12, 14, 1B and 19, the adjudicating ofJicer exclusively has
the power to determine, keeping in view the collective reqding ofSection
71 reod with Sectlon 72 ofthe Act. if the adjudication under Sections 12,
14, 18 ond 19 other thon compensqtion as envisaged, if extended to the
adjuclicating oJficer as proyed that, in our view, may intend to expand
the ambit ond scope of the powers and functions of the adjudicating
offrcer under Secfion 71 and thqt would be agqinst the mandate of the
Act 2016."
Page 13 of 21
ffiHARERA
S-eunuennnt Complaint No. 4127 of 202 2
bserved as under:
obs
)nstruction of the project and handover the possession of the said unit by
con
8.09.2019.
18.( It is clairding the benefit of lockdown which came into effect
onn 23.03.2020 whereas the due date of handing over of possession was
tuch
mur prior to the event of outbreak of Covid-19 pandemic. Therefore, the
authority is of the vief that outbfak of a pandemic cannot be used as an
excuse for non-perfo/mance of a contract for which the deadlines were
much before the outfireaL itsef [nd fqr the said reason, rhe said time
Pa9e 14 af21
MHARERA
S- eunuenRvr Complaint No. 4127 of 2022
15. In the present compl int, the complainant intends to withdraw from the
project and is seeki return of the amount paid by her in respect of
subject unit along wi interest at the prescribed rate as provided under
section 18(1J of the I of the Act is reproduced below for
ready reference.
"Section 78: - n
18(1). tfthe is unable to give possession of
on aportment,
(a) in accordo
case may b
(b) due to
suspension
ony other
he shsll be I on deman to the qllottees, in cose the qllottee
wishes to withcl the ect, without prejudice to any other
remedv availab t received by him in respect of
that apartment, plot, as the case may be, with interest at
such rate qs may be prescribed in this behalf including compensqtion
in the monner as provided under this Act:
Provided that where an all does not intend to withdrqw from the
project, he shall be paid, by the promoter, interest for every month of
deloy, till the halding over of the possession, at such rate as may be
pre scribe d. " @m[ h o si s supp ti ed)
16. Clause 5.1 of the ent provirdes for handing over of possession and
is reproduced below:
" 5.1
Subject to Clause 5.2 infro ond further subject to ctll the buyers of the
Floors in the I Colony making tinely payment, the Company
shall endeavour complete the develofiment oI Residentiql Colony ond
the Floor as far possible wit in 36 rionths with on extcnded period
of (6) six mon from the dhte of execution of this Floor buyer
a
Page l5 of21
ffiHARERA
S- ounuennr,,r Complaint No. 4127 of2022
17. At the outset, it is rel ant to comment on the preset possession clause of
the agreement wh the possession has been subjected to all kinds ol
terms and conditio of this agreement and application, and the
complainant not be g in
default under any provisions of these
agreements and co pliance with all provisions, formalities and
documentation as pre ibed by the promoter. The drafting of this clause
and incorporation of ;uch conditions are not only vague and uncertain
but so heavily loaded in favour of the promoter and against the allottee
that even a single fault by the allottee in fulfilling formalities and
d
documentations etc. prescribed by the promoter may make the
possession clause ir elevant fol the purpose of allottee and the
commitment date for handing over possession loses its meaning. The
incorporation of such lause in the buyer's agreement by the promoter is
just to evade the liabi ity towards timely delivery of subject unit and to
Page 16 of 2l v
ffiHARERA
#-eunuennn,l Complaint No. 4127 of 2022
deprive the allottee o his right accruing after delay in possession. This is
just to comment as to ow the builder has misused his dominant position
and drafted such mi ievous clause in the agreement and the allottee is
left with no option but to sign on the dotted lines.
18. Admissibility of r nd along with prescribed rate of interest: The
allottee intends to wi draw from the project and is seeking refund of the
amount paid by her in respect of the subject unit with interest at
prescribed rate as pr nder rule 15 of the rules. Rule 15 has been
ded und
reproduced as under:
R le 15. ratu of ,t-'lProviso to section 72, section
18 qnd sub (7) of section 791
(1) For the 12; section 18; ond sub-
sections (, 'td (7) ol section 19, the ","interest
'interest ot th
the rate
prescribed" ll be the Stote Bank of lndio highest margindl cost
of lending rt +20k.:
Provided t in case the Stote Bank of Indio tnarginql cost of
lending (MCLR) is not in use, it sholl be replaced by such
benchmark nding rotes which the State Bank of lndia moy ftx
from time time for lending to the general public.
19. The Iegislature in its wisdom in the subordinate legislation under the
provision of rule 15 f the rules, has determined the prescribed rate of
interest. The rate interest so determined by the legislature, is
reasonable and if the said rule is followed to award the interest, it will
ensure uniform practi :e in all the cases.
;"*!b:# Y tr# sil
" i-, I \ t", \,,!. I \, r,
20. Consequently, as p Bank or rndia i.e.,
https://sbi.co.in. the arginal cost of lending rate [in short, MCLR] as on
date i.e.,20.03.2024 i 8.85o/o. Accordingly, the prescribed rate of interest
21. The definition of te 'interest' a$ defined under section 2(za) of the Act
provides that the ra of interest chargeable from the allottee by the
promoter, in case of efault, shall be equal to the rate of interest which
the promoter shall b liable to pay the allottee, in case of default. The
relevant section is roduced below:
"(zo) "interest" eans the rotes of interest payqble by the promoter or
the allottee, as th case may be.
Explanation. r the purpose ofthis clause-
(i) -Fl
the rote of terest chargeable from the allottee by the promoter, in
case of defo lC sholl be quol to the rate of interest which the
promoter ll be liable to poy the allottee, in cose ofdefoult;
(ii) the interest ryable by the promoter to the allottee shall be from
the date the romoter received the amount or any port thereof till
the dote amount o|ipart thereof qnd interest thereon is
refunded, an the interesil,byabb by the allottee to the promoter
shall be n the clctte the allottee defaults in payment to the
promoter til the clate it is Daid:"
1
22. 0n consideration of a"."rfi,r l*ilable on record and submissions
"
made by both the
Act, the authority is
the section 11(4)(a) the Act by not handing over possession by the due
date as per the
la ent. By virtue of clause 5.1 of the agreement dated
22.06.20L3, the posl of the subject apartment was to be delivered
within a period of 36
the date of executio
calculated 36 month from date of the agreement dated 22.06,2013.
Accordingly, the du rte of possession comes out to be 22.06.2016, It is
pertinent to mention rr here that even after a passage of more than 7
years [i.e., from the te of BBA till date) neither the construction is
complete nor the offe of possession of the allotted unit has been made to
the allottee by the ondent /promoter. The authority is of the view
that the allottee ca not be expected to wait endlessly for taking
possession of the uni which is allotted to her and for which she has paid
unit and for which hd has paid a considerable amount towards the sale
consideration and as {bserved by Hon'ble Supreme Court of India in Ireo
Grace RealtechPvt. ltd, Vs. Abhishek Khanna &Ors., civil appeal no,
5785 of 2019, decided on 17.07.2027:
Page 19 of 21
ffiHARERA
#*eunuennnr Complaint No. 4727 of 2022
r
Page 20 of 2l
ffiHAR
#- eunr.r plahtNo.4127 of 2022
27. Hence, the authority hereby pas ord and issues the following
directi ns under n 37 of the Act en compliance of obligations
cast u n the pro as per fu ction trusted to the authority
under n 34(f);
promoter i di refund the entire paid-up
unt i.e., Rs. ,39,22,807 / re ved it from the complainant
ng with in at the of 0.8 5 p.a. as prescribed under
e 15 of the ryana ( tion and Development)
es, 20t7 the t till the actual realization
the amount.
ii. A eriod of 90 ent to comply with the
di ons gi ch legal consequences
uld follow.
lll. respo te third party right
the u amount paid by the
plainant. If respect to the subiect
it, the recei shall be first utilized for
ng dues
\-'-
20.03.2024 (Ashok
PaEe 21 of 21