Jilani Project Time Line
Jilani Project Time Line
Jilani Project Time Line
16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22
1 Jilani Project Time Line 173 days '24 Jul 01
2 Civil Foundation 40 days '24 Jul 01
3 ESP Installation 20 days '24 Aug 10
4 Water Scrubber Placement 3 days '24 Aug 10
5 Cyclone Placement 3 days '24 Aug 10
6 Ducting From Chimney to Cyclone
15 days '24 Aug 30
7 Coal Silo Fabrication 30 days '24 Aug 10
8 ID &FD Fans & Pump Placement 3 days '24 Sep 14
9 Silo Installation 5 days '24 Sep 09
10 Coal Feeders Installation 5 days '24 Sep 14
11 Boiler Body Frame Installation
20 days '24 Sep 14
12 Drum Placement 1 day '24 Oct 04
13 Tube Wall Installation 10 days '24 Oct 05
14 Steam Connection Tube Welding15 days '24 Oct 15
15 Hydraulic Testing 3 days '24 Oct 30
16 Insulation Installation 10 days '24 Nov 02
17 Water&Steam Pipeline Connection
26 days '24 Nov 12
18 Power Cables& Instruments 26 days '24 Nov 12
Cable Connection
19 Furnace Drying 10 days '24 Dec 08
20 Boiling Out 3 days '24 Dec 18