Professional Documents
Culture Documents
6 - Project Management - Lecture 6 - Chapter 8 - Scheduling Resources
6 - Project Management - Lecture 6 - Chapter 8 - Scheduling Resources
6 - Project Management - Lecture 6 - Chapter 8 - Scheduling Resources
Project Management
Chapter 8
Scheduling Resources and Costs
1
4/13/2024
The Resource
ExampleProblem (cont’d)
1 (cont’d)
• Resource Smoothing (or Leveling)
– Involves attempting to even out varying demands
on resources by using slack (delaying noncritical
activities) to manage resource utilization when
resources are adequate over the life of the project.
• Resource-Constrained Scheduling
– The duration of a project may be increased by
delaying the late start of some of its activities if
resources are not adequate to meet peak demands.
2
4/13/2024
3
4/13/2024
Botanical
Garden
FIGURE 8.3
4
4/13/2024
5
4/13/2024
FIGURE 8.4
6
4/13/2024
7
4/13/2024
Allocation of
Resources, EXAMPLE 2
8
4/13/2024
Activity A B C D E F G H I J K L M
Time (hours) 2 4 4 3 1 2 3 1 5 5 4 1 2
Workers 3 2 2 1 3 2 3 3 2 3 1 4 4
a. Draw a Gantt chart based on the earliest start times. How many
hours are required to complete the project? Identify the critical
path?
b. Suppose that the machine is needed for activity “C” is damaged.
How much extra time is available for repair without delaying the
project.
c. Knowing that the number of workers available is 7 workers.
Draw a Gantt chart and determine how many hours are added to
the project time?
d. Knowing that Activities (J, L) use the same machine, of which
only one unit is available. Draw a Gantt chart, and determine the
minimum time required to complete the project when resource
requirements are considered?
March, 2024 Chapter 8, Scheduling Resources 18
9
4/13/2024
Activity 1,2 1,3 1,4 2,5 2,8 3,5 4,5 4,6 5,7 6,8 6,9 7,8 8,9
Time (days) 5 5 7 4 3 3 3 6 7 4 5 2 1
Workers 2 1 3 2 2 1 1 1 2 3 1 2 2
a. Draw a Gantt chart based on the earliest start times. How many days are required
to complete the project?
b. What is the longest path in the network and what is its relation by the critical
path?
c. Suppose that the machine is needed for activity “6,8” is damaged. How much
extra time is available for repair without delaying the project?
d. Knowing that Activities (5,7& 6,8 & 6,9) use the same equipment, of which only
two units are available. Draw Gantt chart and determine how many days are
added to the project time when resource requirements are considered.
e. Knowing that the number of workers available is 6 workers. Draw a Gantt chart,
and determine the minimum time required to complete the project
10
4/13/2024
11