KINSKAN HOMES ESTIMA

ESTIMATE
TE

EST0130
10820938 CANADA INC
GST # 808442156 RT0001 DATE

23 Mumberson street cookstown ON. 01/21/2024


L0L1L0
TOTAL
(647) 686-5667
CAD $58,454.90
www.kinskanhomes.com
uchenna@kinskanhomes.com

TO

Past
astor
or Amos Dada
Kenhar Dr
4166162425

DESCRIPTION RA
RATE
TE QTY AMOUNT

*CHURCH STAGE CONSTRUCTION $21,210.00 1 $21,210.00


Build back wall 20.4x21 framed on 2x6 spruce lumber
Drywall backwall with 1/2x4x8
Taped, plaster, and sand wall make good for painting
Paint wall primer and 2 coats wall paint
Cost $6500
* STAGE 12’ x 21’ 2 levels platforms
2x8 Construction of 2 stage platform
Osb tongue and groove plywood nailed and glued
2 risers stairs
Stair Nosing and side skirts as necessary
Total $7560
(Carpet by others)
(Drum Glass enclosure and sliding door by others)
(Sound, led, electrical wiring by others)
* 2 Wall partitioning,
2x4 construction, sound proof wall with Roxul insulation, 1/2” drywall
both sides, 2 x 30x80” steel door, 2x2 ceiling light, separate new light
switches
* Removable wall partitioning made with mdf plywood
Taped, plaster, and sand make good for painting,
Total $6200
INSULATION
Purchase R12 and Insulate rear high wall value $950- FREE

Thanks for your business!


DESCRIPTION RA
RATE
TE QTY AMOUNT

ELECTRICAL FOR SOUND, LIGHTING, snd LED INSTALLATION. $14,170.00 1 $14,170.00

Materials to be purchased.
Purchase 28 xlr cable 1680$
6xlr p cable 380$
hdmi cable 280$
4 network cable 400$
bx12/3 cable 580.
8 port xlr wall plats 660$
2 port xlr wall plates 320$
220v discount box 120$
108 resptical. 60$
12 feet light pole 390$
8 number DMX lights. 1120$
DMX cable 480 $
DMX 10mt cable. 90$
speaker cable 210$
installation matrial. 500$
installation works. 6500$
TOTAL INCLUDING INSTALLATION 14170. + tex

LED AND INSULATION $14900 $14,900.00 1 $14,900.00


See attached image

MEDIA ROOM $4,700.00 1 $4,700.00


Construction of an accessible work table in media room as shown with
electrical outlets usb & C outlet $1200 - (Discounted no charge)

HIGH CEILING PAINTING


Paint galvanized ceiling,
Paint exposed Main ducts
2 coats of Black flat acrylic paint $3500
Scissors Lift Rental 1month $1100 (Discount)

Project Duration 2-1/2 weeks


February 27 - March 16 2024
Payment schedule
50% on Feb 27
25% on March 5
25% on completion 16

Thanks for your business!


SUBT
SUBTO
OTAL $54,980.00
DISCOUNT -$3,250.00
TAX ((13
13%)
%) $6,724.90

TOTAL CAD $58,454.90