SE-SCI-CON-S-55 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

ISOLATOR

ISOLATOR

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P1 of 6
Document No. Solution Centre India
SE-SCI-CON-S-55 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

1.0 Introduction
The following test procedure has been prepared for the testing and commissioning of the Isolator
at ………………………………………………. project India.
All Testing and Commissioning documentation must be produced in accordance with all relevant
codes of practice of India and international standard.

2.0 Test Equipment

The following test instrumentation & tools will be required to undertake the tests detailed within
this procedure:
A Megger (5 KV)
B Micro Ohm Meter/CRM Meter

3.0 Testing and Commissioning


 The installation of equipment is substantially complete, and is live. Equipment and System
Testing and Commissioning documentation must be provided to verify the following tests
and inspections have been carried out.
 All testing and commissioning documentation, including manufacturers recommended
procedures, shall be supplied to the commissioning management team to confirmed
 Wear insulating gloves. Perform the discharge and grounding of the circuit at the
conclusion of each test.
 The following steps shall have been carried out:

4.0 Visual Checks – General.


CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P2 of 6
Document No. Solution Centre India
SE-SCI-CON-S-55 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

 Visual checks for physical installation against Approved drawings.


 Check the Isolator ratings are in accordance with the approved working drawings
 Check general construction and standard of finishing are acceptable.
 Check leveling and alignment are correct and acceptable.
 Check equipment properly mounted as per manufacturers recommendations,
 Check warning labels and signage are fitted
 Check maintenance access provided for equipment.
 Check earthing bar and connections are provided and correct.
 Check bolts, nuts, screws etc for supports, insulators and connections have been tightened
correctly and torque tightened where applicable.
 Check operating handles and keys c/w mounting cabinet have been provided.
 Check rubber insulating mats have been provided to front and rear of panels.
 Check ‘As Built’ record schematic diagrams have been installed in the room. The
schematics to be framed and wall mounted.
 Check operation sequence instructions have been provided for interlock facilities.

5.0 Commissioning Test


CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P3 of 6
Document No. Solution Centre India
SE-SCI-CON-S-55 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

5.1 I R Value Test


5.1.1 Circuit Diagram:

5.1.2 Procedure:
The measurement of insulation resistance is a common routine test performed on all types of
electrical wires and cables. As a production test, this test is often used as a customer
acceptance test, with minimum insulation resistance per unit length often specified by the
customer. The results obtained from IR Test are not intended to be useful in finding localized
defects in the insulation as in a true HIPOT test, but rather give information on the quality of
the bulk material used as the insulation.

Even when not required by the end customer, many wire and cable manufacturers use the
insulation resistance test to track their insulation manufacturing processes, and spot
developing problems before process variables drift outside of allowed limits.

Insulation resistance test of the isolator using by 5000 Volt Megger.


Isolator closed condition R pole to Earth and Y pole to Earth and B pole to Earth.
Isolator open condition R pole to Earth and Y pole to Earth and B pole to Earth
The above value all noted and recorded on site register / test report. The value should be in
Meg Ohms.
5.1.3 Testing Report:

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P4 of 6
Document No. Solution Centre India
SE-SCI-CON-S-55 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

Insulation Resistance Test Values in Meg Ohms


Description RY YB BR
Ph To Ph (Isolator Closed)
Ph To Earth (Isolator
Closed)
Ph To Earth (Isolator
Opened)

5.2 Contact Resistance Test


5.2.1 Circuit Diagram:

5.2.2 Procedure:
Contact Resistance is found using a Micro-ohm meter, which applies Voltage, and current to the
contacts for Isolator in closed position and directly gives reading on its display
Contact resistance of the Isolator R ph, Y ph and B ph pole by measuring CRM Kit injected 100 A DC
correspondence resistance will show direct reading to recorded each pole. It should be less than 100
micro ohms. The above value all noted and recorded on site register / test report.
5.2.3 Testing Report:

Contact resistance Values in Micro Ohms

Sl. no Description “R” PH “Y” PH “B” PH

(I) Contact Resistance value

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P5 of 6
Document No. Solution Centre India
SE-SCI-CON-S-55 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

5.3 Operation and Functional Test


5.3.1 Procedure:
The following all operation and function checked local / remote up to Control panel Lamp indication,
Semaphore Indication and Interlock also. The below are noted and recorded on site register / test
report.
Manual Operation Checked (Close and Open) :
Motor Operation checked (Local/Remote) :
Inter lock operation checked (Mechanical/Electrical) :
Indication Lamp circuit checked (Close and Open) :
Semaphore indication Circuit Checked (Close and open) :

6.0 RECORDS
 Isolator Test Report
 Pre Commissioning Check List
 Loto Check Sheet
 Energizing Protocol

7.0 DOCUMENT CONTROL

Revision No Revision Changes Prepared By Reviewed By Approved By


Date

00 Original HOD Head-BPE GM-


Release Construction Operations

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P6 of 6

You might also like