Professional Documents
Culture Documents
Sf6 Testing Procedure
Sf6 Testing Procedure
SF6 CIRCUIT
BREAKER
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P1 of 9
Document No. Solution Centre India
SE-SCI-CON-S-59 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013
1.0 Introduction
The following test procedure has been prepared for the testing and commissioning of the SF6
Circuit Breaker at …………………………………………… project India.
All Testing and Commissioning documentation must be produced in accordance with all relevant
codes of practice of India and international standard.
The following test instrumentation & tools will be required to undertake the tests detailed within this
procedure:
A Megger (5KV)
B CRM Kit
C Timing Test Kit
D Gas Leakage Detector Test Kit
5.1.2 Procedure:
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P4 of 9
Document No. Solution Centre India
SE-SCI-CON-S-59 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013
IR test of breaker is done using 5 KV Megger. Meggering is generally done under specified
conditions namely, when CB is closed and when CB is opened. During these conditions, Megger
value is noted down for all the phases. The values thus measured are preferably in giga ohms.
The breaker closed condition R pole to Earth and Y pole to Earth and B pole to Earth.
The breaker open condition R pole to Earth and Y pole to Earth and B pole to Earth
The breaker open condition R-R pole and Y-Y pole and B-B pole. The above values are noted and
recorded on site register / test report. The value should be in Meg Ohms.
5.2.2 Procedure:
Contact resistance of the breaker R ph, Y ph and B ph pole is seen by injecting 100A dc current
with the help of CRM Kit and thus the corresponding resistance is displayed. The value thus
shown should ideally be less than 100 micro ohms.
Stationary & Moving Contacts are built from materials that provide good resistance from arcing.
However if contacts are not maintained on a regular basis, resistance due to repeated arcing
builds up resulting in the contacts disability to carry currents
5.3.2 Procedure:
It is necessary to time each breaker, in order to have its functional signature. Incorrect operation
can have disastrous consequences on the equipment or the substation personnel. Not to mention
the out of service losses of revenue and the repair costs. Timing tests are done first in the factory
during the routine tests and after installation, during the commissioning tests. They have to be done
periodically in order to validate the good working order and reliability of the breaker. Timing tests
are also a powerful tool for troubleshooting faulty breakers.
Data interpretation
Data analysis
5.4.1 Procedure:
The gas is filled in the gas leakage detector test kit and it is kept for 24hrs under observation.
Then after 24 hours the pipe joints are checked for any detection of leakage of gas
If the pressure drop is more than 1KV then the gas leakage detector detects it
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P8 of 9
Document No. Solution Centre India
SE-SCI-CON-S-59 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013
CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures may
be changed with out notification. The controlled procedures are those only on the SCI server. P9 of 9