Total Cost of the Project (Crs.) 188.

91
Appointed Date 14-10-2022
Sr. Cost (Crore) Start date as per handover date as Completion Handover date of Delay in handover New start New finish Remarks
No. (Stretches of the submitted schedule per submitted duration as per location of location
work eligible for schedule submitted schedule date date
extension and Appointed
Item Description Particulars of hindrance Stretches Effected price adjustment.) date

Interchange 0+000 Tree Cutting Permission (Slip Road The delay was due to land issue
1.175km) due to forest trees.) Slip road and forest clearance. The
construction was essential for diverting traffic contractor has given 475 days
for whole interchange to be constructed.
Only Interchange at to complete the interchange, but
1
0+000
38.81 15/12/2022 3/04/2024 430 29/08/2023 319 29/08/2023 1/11/2024 430 days has been assumed to
Down exit loop ramp at 0+000 be appropriate for the
(Rampur to Moradabad (1.000 km) due to completion of the interchange
non-acquisition of land
accordingly the date has been
given.
2 MCW at 0.800 to Houses and temple. Temple not shifted yet,
1+020 LHS
0.800 to 1+020 2.024 1/12/2022 31/03/2024 486 Not handover yet but likely to be
completed within the
3 Kavad Yatra: 0.00 to 10.19
EOT given under item 3.
0.000 to 10.190 The whole project was
(Entire stretch)
20.99 1/12/2022 15/04/2024 501 NA 59 13/06/2024 closed because of the
4 Slip Road 1 at Land & Tree cutting Permission Slip Road
14/10/2022 closure of the road during
Only Slip Road 1 at
Interchange 8.400 1 Interchange 8.400
15/12/2022 31/05/2024 60 27/06/2023 256 28/08/2023 27/10/2023 Kavad yatra.
Change Of Scope at Tree Cutting Permission Slip road 8. Slip Tree cutting permission
Interchange 8+400: road construction was essential for diverting
traffic for whole interchange to be 15/12/2022 31/05/2024 60 Pending still pending
constructed.

COS at 8+400 interchange for MCW from COS Pending


Moradabad to Bareilly. 17.87 15/12/2022 31/05/2024 430 23/02/2024 497 25/04/2024 29/06/2025
5 8.100 to 8+760
COS at 8+400 Interchange for Minor Minor bridge permission
Bridge
4/04/2023 31/05/2024 423 Pending pending

COS 33 KVA Line Crossing (This was not


23/02/2024 497 COS Pending
included in Schedule A)

Note- Other stretches will have EOT but without damage and with price adjustment freeze of indices.
No Claim by the contractor to be given.
Price adjustment shall be applicable for the entire stretch of works for the EOT for Kavad Yatra
The cost of interchange at 8.400 has been taken only effected due to 33KVA line which has been recommended as COS from AE
The time completion as submitted by programme was 475 days, but AE has assumed 430 days appropriate for the completion of both the interchange
The approval of COS is assumed to be 31st May and accordingly the start date has been taken for the interchange at 8+400