In order to submit a technically sound and workable solution for the critical defect rectifications for
the subject work to MEA on Monday following responsibilities are distributed:
Apart from above regarding defect rectification works following officers to keep regular follow up
with AFCONS for early/ timely completion of the same :
1) A5 built drawings - Sh Bishen, Sr. Manager/C
2) Jetty/ airstrip defect rectification works - Sh Ashish Srivastav, Sr. Manager/C
3) Building repair works - ~ .~zAc,vl ~ , ~ ~ {c,
For finalisation of rates of 330 defect rectification items, Sh Mahesh from AFOCNS will be available
in RITES HQ on Friday 24-05-2024. Ms Manviya, JGM/Buildings & Sh Guiab Prajapati, Ms Manviya,
JGM/Airports from HQ alongwith Sh N.S Rawat, GM/C (& his team from Agalega) to undertake this
exercise for early conclusion.