ROADSTAB LAYER CONSTRUCTION
1
Methodology
RoadstaB Layer Construction
2. DESCRIPTION OF ACTIVITY:
2.1. The activity includes Mixing and compaction of RoadstaB layer with approved material from borrow
area satisfying the requirements of RoadstaB-Q manual as indicated in the soil test report
submitted to Oriental Structure Engineers.
3. REFERENCES:
3.1. Ref. other related works prior to this activity:
3.1.1. Level sheet of Subgrade Top
3.1.2. Subgrade compaction up-to MDD 98%
3.2. Ref. to Drawing(s):
3.2.1. Approved good for construction Drawings
3.3. Soil test report and pavement design reports submission.
3.3.1. Approval of both the submitted reports from the all the designated authorities.
3.3.2. Approval letter from the Authority Engineer.
4. CONSTRUCTION METHOD:
Task-1 suitability. Labor and basic lab equipment from -NA- -NA-
required at site, to be provided by client. RoadstaB.
Labor by As required
client
2
Methodology
RoadstaB Layer Construction
Equipment
Task-2 area of construction. Material shall comply
with material test report, with natural Plant/ 01 No. 120 TPH 01
moisture content or dry condition. Hopper WMM
shall be filled by JCB plant.
Preparation of RoadstaB-Q compound Water 1 No.
solution in water tanker or water reservoir Reservoir
with the quantity of 3000-10000 liters. This
water tanker or water reservoir shall be
Equipment
attached to plant, to inject compound in
Task-3
specific quantity of solution (water +
RoadstaB-Q) to reach Optimal moisture
contents to raw material. Moisture content
is to be assessed by RoadstaB team at
regular basis.
Subgrade preparation: It is required to Laboratory 1 No.
complete compaction process of subgrade Subgrade
before starting production of RoadstaB Test team
3
Methodology
RoadstaB Layer Construction
Transportation
Trucks, as per the production capacity of Batch mix
construction site in trucks. Regular
availability of trucks is required to furnish plant, and distance from the construction site.
regular supply on site.
Pavement: Pavement 1 No
Ready mix shall be paved by paver Engineering
considering camber/crossfall. Client’s Site team
Pavement Engineer and his team shall take
Pavement Resources
4
Methodology
RoadstaB Layer Construction
Compaction
Task-8 effective compaction. Rolling shall be done
from lower edge towards the upper edge.
Minimum
Overlapping in each pass shall not be less Tandem 1 No.
8 tons
than 1/3 of Drum width. Minimum of 8-ton Roller
compactor shall be used with vibratory
function.
Final compaction
5
Methodology
RoadstaB Layer Construction
Completion
Task 10 of disturbance in formation of structural
skeleton.
If it is required, light weight vehicles
movement can be started after 12 hours
curing time after final compaction.
Ready non-cured structure shall be handed
over to client or its representatives for
further construction of structure Layer.
Testing:
For every 1000 cubic meter RoadstaB layer,
3 testing samples shall be transported for
UCS mould compaction from the ready mix.
Mould preparation for assessment.
These samples shall be taken air tight bags, UTM machine – 1 No.
and taken to field laboratory for UCS mould UCS Mould (minimum of 50 mm dia) – 1 No.
compaction. Mould compaction shall be
Task-11 done in UTM machine at 200 kg / sq cm Base plate and load plate for compaction.
6
Methodology
RoadstaB Layer Construction
Curing
TasK-12 shall be taken out and left open in shade at
room temperature for another 21 days.
These cured moulds are ready for counter
testing and shall be handed over to
authority engineer for assessment
a) Caution Boards shall be placed at the beginning and end of working site and also at risky
locations.
b) Barricading tape will be placed at risky locations, turning etc.
c) Signal man will be placed at heavy traffic locations at the time of Execution.
d) Reflective sign boards will be placed during night near risky locations.
e) Regular sprinkling of water shall be done to minimize dust emission.
f) All necessary measures shall be taken to maintain all plants and silencing equipment’s in good
conditions so as to maintain air and noise emission during the operation.
g) All necessary measures shall be taken to control the disposal of all forms of waste generated by
the construction operations and in all associated activities.
h) All necessary measures and precautions shall be taken to avoid any nuisance or disturbance
arising from the execution of the work.
a) The manpower & machinery proposed is indicative only. The requisite qty. of resources may
vary based upon site condition.
b) Any modification in execution of activity shall be done with prior information with consultant.