Methodology

RoadstaB Layer Construction

Methodology
ROADSTAB LAYER CONSTRUCTION

RoadstaB India | Working Methodology | May 2017

1
Methodology
RoadstaB Layer Construction

1. NAME OF ACTIVITY : ROADSTAB LAYER PRODUCTION AND CONSTRUCTION

2. DESCRIPTION OF ACTIVITY:
2.1. The activity includes Mixing and compaction of RoadstaB layer with approved material from borrow
area satisfying the requirements of RoadstaB-Q manual as indicated in the soil test report
submitted to Oriental Structure Engineers.

3. REFERENCES:
3.1. Ref. other related works prior to this activity:
3.1.1. Level sheet of Subgrade Top
3.1.2. Subgrade compaction up-to MDD 98%
3.2. Ref. to Drawing(s):
3.2.1. Approved good for construction Drawings
3.3. Soil test report and pavement design reports submission.
3.3.1. Approval of both the submitted reports from the all the designated authorities.
3.3.2. Approval letter from the Authority Engineer.

4. CONSTRUCTION METHOD:

Resources for implementation and quality control

Tasks Construction Method Category/ Proposed Stand


Capacity
Type No. by Unit

It shall be the responsibility of RoadstaB Lab 01


team that before commencement of mixing Engineer
and construction ensure that the soil / and Site
material to be used have been tested for the Engineer
Manpower

Task-1 suitability. Labor and basic lab equipment from -NA- -NA-
required at site, to be provided by client. RoadstaB.

Labor by As required
client

2
Methodology
RoadstaB Layer Construction

Material shall be dumped in batch mix


plant/WMM plant, shall be carried out JCB 01 No. 01
according to the quantity required for the

Equipment
Task-2 area of construction. Material shall comply
with material test report, with natural Plant/ 01 No. 120 TPH 01
moisture content or dry condition. Hopper WMM
shall be filled by JCB plant.
Preparation of RoadstaB-Q compound Water 1 No.
solution in water tanker or water reservoir Reservoir
with the quantity of 3000-10000 liters. This
water tanker or water reservoir shall be

Equipment
attached to plant, to inject compound in
Task-3
specific quantity of solution (water +
RoadstaB-Q) to reach Optimal moisture
contents to raw material. Moisture content
is to be assessed by RoadstaB team at
regular basis.
Subgrade preparation: It is required to Laboratory 1 No.
complete compaction process of subgrade Subgrade
before starting production of RoadstaB Test team

layer. Subgrade should be compacted in the


Pre-pavement activities.

required MDD and checked before RoadstaB


Soil 1 No. 12 Tone
Layer pavement. Client’s Lab team shall test
Task -4 Compactor Vibratory
and get the data registered, provide a signed
Roller
copy of subgrade compaction data to
RoadstaB’s engineering team. Minimum
98% of the laboratory achieved MDD shall Water 1 No.
be achieved on site after compaction of Sprinkler
subgrade.

3
Methodology
RoadstaB Layer Construction

RoadstaB material Mixing: Material shall be Electricity

Quality Control / Test Facilities


mixed in the ratio specified in material test point 1 No.
report at OMC. Moisture contents shall be
checked regularly. Electricity point and 5 sq
Task-5 m area is required for assessment of
moisture contents near plant.
Table near 1 No
mixing
plant
Task-6 Transportation of Material to Site:
Ready mix material shall be transported to

Transportation
Trucks, as per the production capacity of Batch mix
construction site in trucks. Regular
availability of trucks is required to furnish plant, and distance from the construction site.
regular supply on site.

Pavement: Pavement 1 No
Ready mix shall be paved by paver Engineering
considering camber/crossfall. Client’s Site team
Pavement Engineer and his team shall take
Pavement Resources

decision about height, width, and length of Paver 1 No.


Task 7 structure, satisfying design, drawing,
reports, and assessing capacity of Drawing 1 No.
production and pavement of client’s
pavement machineries. Client’s Engineering Pavement 1 No.
team shall consider all aspect of drawing, Design
construction, and level of structure. Report

4
Methodology
RoadstaB Layer Construction

Compaction: Vibratory 1 No. Minimum


12 tons
RoadstaB’s compaction specialist ensures Soil
the degree of compaction, movement of Compactor
compactor, requirement of vibration, and
required passes of compactor. It shall be
ensured that roller does not move at the Compaction 1 No.
speed more than 5 Km/hr, to have more Specialist:

Compaction
Task-8 effective compaction. Rolling shall be done
from lower edge towards the upper edge.
Minimum
Overlapping in each pass shall not be less Tandem 1 No.
8 tons
than 1/3 of Drum width. Minimum of 8-ton Roller
compactor shall be used with vibratory
function.
Final compaction

Final compaction shall be done by PTR, and


Task 9 left for curing process. PTR 1 No.

5
Methodology
RoadstaB Layer Construction

After final compaction, structure is ready for


further structural construction. If it is
decided to pave next layer immediately, it is
allowed to pave crack relief layer
immediately. If duration gap is given then it
is advisable to pave next layer – Crack relief
layer after 7 days, to exclude any possibility

Completion
Task 10 of disturbance in formation of structural
skeleton.
If it is required, light weight vehicles
movement can be started after 12 hours
curing time after final compaction.
Ready non-cured structure shall be handed
over to client or its representatives for
further construction of structure Layer.
Testing:
For every 1000 cubic meter RoadstaB layer,
3 testing samples shall be transported for
UCS mould compaction from the ready mix.
Mould preparation for assessment.

These samples shall be taken air tight bags, UTM machine – 1 No.

and taken to field laboratory for UCS mould UCS Mould (minimum of 50 mm dia) – 1 No.
compaction. Mould compaction shall be
Task-11 done in UTM machine at 200 kg / sq cm Base plate and load plate for compaction.

load. These moulds (minimum 50 mm Weighing Scale grams – 1 No.


diameter) shall be pre-defined, and prepared
for compaction to exclude any delay in Weighing Scale milligrams – 1 No.

formation of moulds. These moulds shall be


provided by client or independent
laboratory. This testing shall be arranged
and paid by client.

6
Methodology
RoadstaB Layer Construction

These prepared moulds shall be compacted


and left for curing for 7 days in air tight
containers in room temperature, after
completion of 7 days curing, these moulds

Curing
TasK-12 shall be taken out and left open in shade at
room temperature for another 21 days.
These cured moulds are ready for counter
testing and shall be handed over to
authority engineer for assessment

5. SAFETY AND ENVIRONMENTAL ACTIVITIES:

a) Caution Boards shall be placed at the beginning and end of working site and also at risky
locations.
b) Barricading tape will be placed at risky locations, turning etc.
c) Signal man will be placed at heavy traffic locations at the time of Execution.
d) Reflective sign boards will be placed during night near risky locations.
e) Regular sprinkling of water shall be done to minimize dust emission.
f) All necessary measures shall be taken to maintain all plants and silencing equipment’s in good
conditions so as to maintain air and noise emission during the operation.
g) All necessary measures shall be taken to control the disposal of all forms of waste generated by
the construction operations and in all associated activities.
h) All necessary measures and precautions shall be taken to avoid any nuisance or disturbance
arising from the execution of the work.

6. ANY OTHER POINTS THE CONTRACTOR LIKE TO MENTION:

a) The manpower & machinery proposed is indicative only. The requisite qty. of resources may
vary based upon site condition.
b) Any modification in execution of activity shall be done with prior information with consultant.