RENCANA WAKTU PELAKSANAAN

PEKERJAAN : RUMAH TIPE HATO PLUS


LOKASI : SHOJI LAND SIDOARJO
TAHUN : 2024
MEI JUNI JULI AGUSTUS SEPTEMBER
No. Uraian Pekerjaan PRESENTASE BOBOT %
W1 W2 W3 W4 W5 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19

I PEKERJAAN PERSIAPAN 0.817 0.817


II PEKERJAAN GALIAN DAN PONDASI 4.581 0.527 3.20 0.854
III. PEKERJAAN STRUKTUR LANTAI 1 10.242 4.20 2.437 1.20 1.203 1.203
IV PEKERJAAN STRUKTUR LANTAI 2 11.685 2.547 2.547 2.547 1.72 2.325
V PEKERJAAN PASANGAN BATA LT 1 & LT 2 10.793 1.70 2.809 1.982 1.982 2.320
VI PEKERJAAN PLESTERAN & ACIAN 14.042 3.5 3.5 7.042
VII PEKERJAAN KUSEN DAN PARTISI 3.203 1.601 1.601
VIII PEKERJAAN DAUN PINTU 8.853 4.427 4.427
IX PEKERJAAN RANGKA ATAP + PENUTUP ATAP 3.952 2 1.952
X PEKERJAAN KERAMIK LT 1 & LT 2 9.135 3.400 2.868 2.868
XI PEKERJAAN PLAFOND 3.101 1.550 1.550
XII PEKERJAAN PENGECATAN 5.578 2.789 2.789
XIII PEKERJAAN SANITASI 3.190 2.5 0.690
XIV PEKERJAAN INSTALASI LISTRIK 2.305 1.152 1.152
XV PEKERJAAN INSTALASI AIR BERSIH & KOTOR 1.630 1.027 0.603
XIV PEKERJAAN FAÇADE, CARPORT, BOX KWH DAN LAIN-LAIN 6.891 3.000 1.500 1.500 0.891
TOTAL 100.00
PROGRESS RENCANA 1.344 3.2 5.054 5.164 4.009 3.749 3.749 4.529 3.702 6.400 5.500 5.452 7.042 4.550 6.450 7.157 8.411 6.028 6.927 1.581
TOTAL KOMULATIF PROGRES RENCANA 1.344 4.544 9.598 14.762 18.771 22.520 26.269 30.798 34.501 40.901 46.401 51.853 58.896 63.446 69.897 77.053 85.464 91.492 98.419 100.000
PROGRES AKTUAL 1.344 3.20 6.081
TOTAL KOMULATIF PROGRESS AKTUAL 1.344 4.54 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63 10.63
NB :
Start pekerjaan 06 mei 2024
Due date pekerjaan 05 oktober 2024