17. FOR FIXING MANHOLE,LADDER , DRAINAGE SPOUT, EXPANSION JOINT , SUB DRAIN CONNECTION , UTILITY
CROSSING ETC PLEASE FOLLOW DETAIL AS GIVEN IN MISC. DETAIL DRAWING NO. 2013/J-633/DRAINAGE/MISC/01 SH.1 TO 4
18. FOR GENERAL CROSS SECTIONS PLEASE FOLLOW DRAING NO. 2013 / J-633 / DRAINAGE /MD-1/CS/CH 3650-3850/ SH 1 TO 3
19. CLEAR COVER TO MAIN R/F.:- a. TOP SLAB=60MM
b. VERTICAL WALL=60MM.
c. BOTTOM SLAB=60MM.
20. DRAWING SHALL NOT BE SCALED AND WRITTEN DIMENSION AND LEVELS SHALL BE FOLLOWED ONLY.
21. SAND FILLING BELOW THE FOUNDATION SHALL BE DULY COMPACTED LAYER BY LAYER NOT
EXCEEDING 250MM IN ONE LAYER.
22. NO BACK FILLING BEHIND THE WALL SHALL BE CARRIED OUT ON BOTH SIDES TO THE BOX DRAIN TO
AVOID UNBALANCED FORCE ACTING ON THE STRUCTURE .
23. DEVELOPMENT LENGTH / ANCHORAGE LENGTH SHALL BE (Ld) = 40Xd ; d = DIA OF BAR.
24. BEFORE CUTTING OF REINFORCEMENT, BBS ARE CHECKED AT SITE.
25. NO EXCAVATION IN THE FUTURE SHALL BE CARRIED OUT ON ONE SIDE OF THE BOX DRAIN TO AVOID STABILITY PROBLEM.
26. AT THE TOP CORNER EDGE OF BOX DRAIN ANCHORAGE VALVE AND POSITIONS SHALL BE KEPT.
27. THE STRUCTURAL PART AS INCLUDED HERE SHALL BE INTEGRATED WITH THE G.A. DRAWING FOR THE RESPECTIVE
CHAINAGE i.e THERE SHOULD NOT BE ANY DEVIATION AND DIFFERENCE BETWEEN G.A DRAWINGS AND STRUCTURAL DRAWING.
7200
400 3000 400 3000 400
FORMATION LEVEL
3 1.0%SLOPE 1.0%SLOPE 3 AS PER GA. SECTION
80
HAUNCH 2 150 2
150x150
150
450
300
200
(TYPE G)
150(typ)
Ld(typ)