STEP 1:
1. CUT /FILL EMBANKMENT TO CREATE REAR WORKING PLATFORM
3. CONSTRUCT TEMP WORKING DECK (CONCRETE PEDESTALS, STEEL COLUMNS, STEEL FLOOR JOISTS
PLYWOOD FLOOR
STRUCTURAL CONCEPT
THE BEACON RESTAURANT
STEP 2:
1. CONSTRUCT TEMP COLUMNS TO SUPPORT BOTTOM CHORD OF TRUSS ( OR CONSTRUCT
PERMANENT COLUMNS)
2. INSTALL TRUSS BOTTOM CHORDS , LIFTED IN PLACE BY CRANE LOCATED ON CONCRETE
SLAB. SPLICED AS NEEDED
3. INSTALL RESTAURANT LEVEL FLOOR BEAMS, BONDEK SLAB
STRUCTURAL CONCEPT
THE BEACON RESTAURANT
3
2
STEP 3:
1. ASSEMBLE MAIN TRUSSES, PIECE BY PIECE
2. INSTALL V - COLUMNS
3. DE-PROP TIP OF CANTILEVER USING JACK
STRUCTURAL CONCEPT