THE BEACON RESTAURANT

EXSTING GROUND PERMANENT SLAB TEMP PLATFORM TO


TOPO LINE OF CONCRETE INSTALL THE STEELWORK
STRUCTURE PART STRUCTURE

1
3
2

STEP 1:
1. CUT /FILL EMBANKMENT TO CREATE REAR WORKING PLATFORM

2. CONSTRUCT RESTAURANT LEVEL CONCRETE SLAB

3. CONSTRUCT TEMP WORKING DECK (CONCRETE PEDESTALS, STEEL COLUMNS, STEEL FLOOR JOISTS
PLYWOOD FLOOR

STRUCTURAL CONCEPT
THE BEACON RESTAURANT

2 HYDRAULIC TEMP PLATFORM


JACKING SYSTEM FOR TRUSS
INSTALLATION

STEP 2:
1. CONSTRUCT TEMP COLUMNS TO SUPPORT BOTTOM CHORD OF TRUSS ( OR CONSTRUCT
PERMANENT COLUMNS)
2. INSTALL TRUSS BOTTOM CHORDS , LIFTED IN PLACE BY CRANE LOCATED ON CONCRETE
SLAB. SPLICED AS NEEDED
3. INSTALL RESTAURANT LEVEL FLOOR BEAMS, BONDEK SLAB

STRUCTURAL CONCEPT
THE BEACON RESTAURANT

3
2

STEP 3:
1. ASSEMBLE MAIN TRUSSES, PIECE BY PIECE
2. INSTALL V - COLUMNS
3. DE-PROP TIP OF CANTILEVER USING JACK

STRUCTURAL CONCEPT