Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

S.

NO DESCRIPTION QUANTITY UNIT RATE AMOUNT


1 CIVIL WORK
1.1 Brickwork
Bricklaying side walls that are
3.5' feet high and 4.5' inches
thick with a cement mortar ratio
of 1:4 210 sq.ft 300 63000
In the kitchen area, the walls are
constructed with brickwork that is
9 inches thick and 6.5 feet high
using a cement mortar ratio of 1:
5 5 Cubic meter 15,000 75000
1.2 plastering
Plastering walls with a 1:5
cement mortar ratio and 12 mm
thickness will result in wall
finishes that can support tile
installation. 437 sq.ft 130 56810
1.3 Tiles
The kitchen counter and side
walls are tiled to a height of three
feet using a two millimeter
spacer, and grouting is
completed. 438 sq.ft 200 87600
2 INTERIOR WORKS
2.1 Panelling 600 sq.ft 200 120000
The order counter and self-
pickup counter are made from
BWP waterproof plywood, high
shine Virgo laminates, glass, or
granite above the counter, with
drawers and lock provisions
underneath.Floating shelves are
2.2 included 48 Sq.ft 2400 115200
Wall cladding made using WPC
2.3 products according to design 80 400 32000
Glass partitions are constructed
utilizing 12mm toughened glass
2.4 and stainless steel fittings. 100 750 75000
2.5 Glass partition ( door entrance) 100 1000 100000
2.6 ACP sheet 36 1500 54000
2.7 Digital sign boards 24 1800 43200
TOTAL AMOUNT 821810
Miscellaneous project expenses ( 5% ) 41090.5
GST (18%) 147925.8
OVERALL AMOUNT 10,10,825
Professional engineer consulting charges 15% 1,51,623