FLOW COMPUTER OMNI 6000

ID Task Task Name Duration Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8
Mode W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32
1 FLOW COMPUTER OMNI 6000 210 days

2 KONTRAK / PURCHASE ORDER (PO) 1 day

3 ENGINEERING 6 days

4 Verifikasi dokumen 6 days

5 PROCUREMENT 198 days

6 Material 198 days

7 Omni Flow Computer 198 days

8 TESTING 2 days

9 Factory Acceptance di Workshop Kontraktor 2 days

10 PENGIRIMAN MATERIAL DI PERTAMINA NUSANTARA REGAS 1 day

11 Onhore Receiving Facility (ORF) Muara Karang 1 day

12 PEKERJAAN AKHIR 1 day

13 Serah Terima 1 day

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Jadwan Pengadaan Omni Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress