Professional Documents
Culture Documents
Attachment 01 (Inquiries Response Sheet)
Attachment 01 (Inquiries Response Sheet)
A- PLANT LAYOUT
1- Identification of the area allocated for the project: there are The preferred location is near the old 4 units, however; electrical department preferred to install the 5th
three options in SOW. Check at site if one of them if unit in DS-08 due to load requirement.
preferred by Client and /or preferred by Contractor
according to the situation. Collect pictures and drawings
(General plan) if available
2- Verification of accessibility to site and availability of Verified accessibility and sufficient spaces are available at site. Please refer to below photos.
sufficient space for manoeuvring and lifting
3- Verification of soil conditions and presence of previous Geotechnical & soil conditions were requested but was not available. WOOD representative informed
geotechnical survey, if any. We assume the area should be these tests to be carried out by the nominated contractor.
similar to previous projects excluding need of piling and / or
drain activities
4- Working area is very narrow. Check necessity of temporary Consolidation work can be carried out near the construction area, and it seems to be enough for the
consolidation works to be done in order to perform scope of the project.
excavation
5- Verification of existing soil resistivity data Soil resistivity report were requested but not available. WOOD representative informed this test to be
carried out by nominated contractor.
6- Verification if any underground existing facilities may be As informed by the WOOD representative there is no underground existing facilities; however, the
expected. In this case it is necessary to evaluate impact of WOOD representative informed nominated contractor needs to verify if any underground facilities are
demolition and / or rerouting if feasible existing.
7- Verification if any demolition works has to be considered to Verified no demolishing work is required.
make the area free and accessible
8- Verification of suitable storage area and availability of water Verified storage area is available and water and electricity are available for construction.
and electricity for construction
9- Verification of existing earthing grid and relevant Verified earthing system used for the fourth units is TN-S (PE separated from neutral) – triangle type.
documentation
10- Verification if new installation shall be in safe area or Verified the area is classified.
classified
11- Verification if Client expects construction of new access Verified and informed by the WOOD representative no new access roads & parking areas are required.
roads and parking areas
Page 1 of 5
S/N Description AL-MAHAM response
12- Verification of possible area for construction for Contractor Verified and informed by WOOD representative area is available.
camp
B- PROCUREMENT
1- SOW at pag. 22 indicates:
1) The new 5th Solar GTG shall be single fuel type (Fuel Gas)
unlike the existing GTGs, with all the technical specifications
generally matching with that of existing GTGs.
2) The new FG Compression skid and Treatment skid shall be ALMAHAM team requested the datasheet for the existing FGS, but was not available. WOOD
similar to the existing Fuel Gas (FG) Compression skid and representative informed that the required datasheet can be requested from Dubai office.
treatment skids, and include all equipment to ensure FG is
supplied with necessary degrees of superheat (i.e. above
both hydrocarbon and water dew points) and pressure to
meet the GTG battery limit specifications.
Therefore please collect information existing compression
skid and treatment skid in order to allow proper alignment
with existing specification.
As per SOW it is expected these 2 items to be procured by
SOLAR
2- SOW at pag. 39 indicates:
CONTRACTOR shall expand existing 11kV switchgear (IQD7- ALMAHAM team requested the datasheet for the existing 11 KV switchgear, but was not available.
SWG823014) by adding a generator incomer panel for the WOOD representative informed that the required datasheet can be requested from Dubai office.
GTG under this project’s scope. All related engineering,
fabrication and supervisory works during installation and
commissioning shall be executed by the switchgear OEM.
All component required for 11kV switchgear extension must
be supplied by the Original Equipment Manufacturer (OEM)
Vendor: Electro tech LLC, USA.
Collect available information at site. It is necessary to
contact the OEM asap in order to get relevant quotation.
Page 2 of 5
S/N Description AL-MAHAM response
Page 3 of 5
S/N Description AL-MAHAM response
4- Earthing system: check tie ins and collect data about existing Similar to points # 02 & 03 mentioned above.
5- Cathodic Protection: Similar to points # 02,03, and 04 mentioned above.
CONTRACTOR shall carry out detailed engineering,
procurement, installation, and commissioning/pre-startup of
Impressed Current Cathodic Protection (ICCP) for foundation
piles in line with COMPANY cathodic protection
specifications. Temporary sacrificial cathodic protection shall
be provided during construction phase. CONTRACTOR shall
take into consideration and mitigate any interference with
adjacent buried structures.
check tie ins and collect data about existing
6- Other TIE INS:
All indicated in SOW. Check discrepancies if any
Page 5 of 5