ATB-Daily Activity Report-3WL Ahead - 20240506

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

HARVEST E&I ENGINEERING SDN. BHD.

NO.2, JALAN CENDERAI 26,

KAWASAN PERINDUSTRIAN KOTA PUTERI,

81750 MASAI, JOHOR.

DAILY ACTIVITY REPORT

Plant : Att Tanjung Bin Sdn. Bhd. Indirect: 4 WEATHER


Location : Tg. Bin Direct: 21 Morning Rainy

Indirect On site : 1. Mohd Razimie 4. Fairul Total Manpower: 25 Afternoon Fine

2. Rano Evening Fine

3.Amirul Adly Hot Work PTW: 1


Date of Report : 5/7/2024 Cold Work PTW: 0

TODAY ACTIVITY
Progress % Completion Manpower Productivity

Actual Estimated Estimated


Total Accumul Accumulat No. of Work Productivity Overall
NO Job No. Location WORK DESCRIPTION Unit Today Today Accum. Manhours Manhours
Qty ated ed Manpower Hours (Today) Productivity
Manhours (Today) (Total)

1 ATB-CP-001 Substation 2 Gravel Filling 80 m 30 30 38% 38% 15 8 120 120 0.1 320.0 0.4
2
3

TOMORROW PLANNING
Date : 5/8/2024

Progress % Completion Manpower Productivity

Actual Estimated Estimated


Total Plan Accumul Plan Accumulat No. of Work Productivity Overall
NO Job No. Location WORK DESCRIPTION Unit Accum. Manhours Manhours
Qty Tmrw ated Tmrw ed Manpower Hours (Tmrw) Productivity
Manhours (Tmrw) (Total)

1 ATB-CP-001 Substation 2 Gravel Filling 80 m 30 30 38% 76% 15 8 240 120 0.1 320.0 0.8
2 ATB-CP-001 Substation 2 Copper tape rectification (Lightning Protection System) 6 point 3 4 50% 67% 5 8 20 40 0.2 80.0 0.3

16

OTHER OUTSTANDING ISSUES / PROBLEMS/ MATERIALS CRITICAL

NO Job No. Location DESCRIPTION

1 ATB-CP-001 Substation 2 Pending name plate


PHOTO ACTIVITY: 5/7/2024

Gravel filling on cable trench infront of existing building Substation 2 Gravel filling on cable trench beside genset room existing building Substation 2

Gravel filling on cable trench infront of existing building Substation 2 Gravel filling on cable trench beside genset room existing building Substation 2

Reported by :

AMIRUL ADLY
ENGINEER (E&I)
ATB-ALL JOB SUMMARY
ManhourLoading
Remarks
5/5 5/6 5/7 5/8 5/9 5/10 5/11 5/12 5/13 5/14 5/15 5/16 5/17 5/18 5/19 5/20 5/21 5/22 5/23 5/24 5/25
Total
S.no Quotation/ Job No. P.O. Number Work Location No Work Description Work load UOM Current Pending Material Required by Harvest In- Progres Planned Accu. Productivity Area of Concern
Progress Charge s % Manhours Manhours
Client PIC
M T W Th F S S M T W Th F S S M T W Th F S S
Work Direct ATB
New Tx Substation 2-Project
Substation 2 1 Gravel backfilling 80 m 38% Gravel insufficient LPK 38% 320 120 2.67
1 ATB-CP-001 770-609026 Substation 2 2 Copper tape rectification (Lightning Protection System) 6 point 1 Pending quotation Skylift rental Rano 17% 5 5 5 80 32 2.50 Halim/ Datuk
Substation 2 3 Fill device name plate installation 43 nos 0 Pending name plate Rano 0% 5 5 80 0
Substation 2 4 LPK 0% 0 0
Cable way cover job
Pending Scaffholding, Pending ATB
Jetty 1 Install new cover T-junction - berth 6 90 m 0 - Rano 0% 12 12 12 12 12 12 115 0 confirmation
Pending Scaffholding, Pending ATB
Jetty 2 Install new cover T-junction until BD 5 162 m 0 - Rano 0% 12 12 12 12 12 12 207 0 confirmation
Pending Scaffholding, Pending ATB
2 ATB-QT-010 770-609293 Jetty 3 Install new cover BD5 - BD2 45 m 0 - Rano 0% 58 0 confirmation Munawar
Pending Scaffholding, Pending ATB
Jetty 4 Install new cover BD2 - BD4 162 m 0 - Rano 0% 207 0 confirmation
Pending Scaffholding, Pending ATB
Jetty 5 Install new cover BD4 - BD1 216 m 0 - Rano 0% 276 0 confirmation
Pending Scaffholding, Pending ATB
Jetty 6 Install new cover BD1 - BD3 63 m 0 - Rano 0% 81 0 confirmation
SS 1 33kV Cable Rectification
3 ATB-QT-023 Pending P.O. Jetty 1 Install cable ladder TBA TBA TBA - Rano 0% TBA 0 Pending P.O. Halim
Jetty 2 Install Cable cleat TBA TBA TBA - Rano 0% TBA 0 Pending P.O.
Preventive Maintenance DB
Tank Farm 1 DB Rectification TBA TBA TBA - Rano 0% TBA 0 Pending P.O.
4 ATB-QT-024 Pending P.O. Jetty 2 DB Rectification TBA TBA TBA - Rano 0% TBA 0 Pending P.O. Halim
TLB 3 DB Rectification TBA TBA TBA - Rano 0% TBA 0 Pending P.O.
Admin Building 4 DB Rectification TBA TBA TBA - Rano 0% TBA 0 Pending P.O.
Work sub from Contractor
TRMS Punchlist
5 TRMS-QT-003 TRMS PO 23-121 Datuk/ Halim
Substation 3 1 Additional to install TB 40 nos 0 Rano 80% 640 361 1.77 Pending terminal block
DATARAN ELEKTRA-CABLE LAYING FOR GAS DETECTOR (JETTY)
6 DTRN-QT-001(R3) Pending PO Jetty 1 Cable Laying TBA TBA TBA TBA 0% TBA 0 Quotation for discount Munawar
Jetty 2 Gas detector installation TBA TBA TBA - TBA 0% TBA 0 To install next year
POWER-CAM-CABLE LAYING FOR POWER PACT
7 PC-QT-001 Pending PO Klagester 1 Cable trenching (manual excavation) TBA TBA TBA TBA 0% TBA 0 Quotation for discount Munawar
2 Cable Laying TBA TBA TBA - TBA 0% TBA 0 To install next year
1
2
3