E&I Cost - Zone-1 & 2
E&I Cost - Zone-1 & 2
No Tender Cost-SPS-1
1 Electrical 6600000
2 Lighting 48000
3 PLC/Instrument 1400000
Total 8,048,000
Total 4,595,000
Total 3,495,000
Total 2,995,000
Total 19,133,000
Remarks
Remarks
Remarks
Remarks
Sl.No Tender Cost-SPS-1 Remarks
1 Electrical 6500000
2 Lighting 48000
3 PLC/Instrument 1400000
Total 7,948,000
Total 15,102,000
Total 2,821,000
Total 2,821,000
Total 2,796,000
Total 2,446,000
Total 37,530,000
Motor Drive List
Total
Sl.No. Description WORKING STAND BY Quantity Phase KW Working KW Standby kW DistanceNo of runs Power Cable cost/Mtrs Total Control cable cost/Mtrs Total
0 0 TOTAL KW 0 0
1 Total Working KW = 0
2 Total Input KVA = 0.00
3 Total working Current = 0.00 Amps (Input KVA total/(V3 X .415))
4 Required Rating of MCC Incomer. = 0.00 Amps ((Total working Current+(Total working Current X
20)/100)
5 Rating of MCC Incomer Selected. = 400 Amps
APFCR
Calculate the required kVAr compensation for 46 kW to 0 0 0
improve the PF from 0.8 to 0.99.
kVAr = kW x multiplying factor from below table = 0 0.608 0 45 KVAR
Transformer 0.00
0.00 250 KVA
UPTO 5 KW 33 8
FROM 5 TO 10 KW 5 2
FROM 20 TO 40 KW 3 1
41 11
PCC-1
Sl.No Description Unit Quantity Unit Price Total Price
1 MCC Main Incomer - 250A Nos 3 100000 300000 400A MCCB UPTO 5 KW 33 8
2 MCC Main Incomer - 2500A Nos 0 0 0 FROM 5 TO 10 KW 5 2
3 MCC Main Incomer - 2000A Nos 0 0 0 FROM 20 TO 40 KW 3 1
4 MCC Main Incomer - 1600A Nos 0 0 0 41 11
5 MCC Main Incomer - 1000A Nos 0 0 0
6 MCC Main Incomer - 800A Nos 0 0 0
7 MCC Main Incomer - 630A Nos 0 0 0
8 MCC Power Feeder - 630A Nos 0 0 0
9 MCC Power Feeder - 400A Nos 0 0 0
10 MCC Power Feeder - 250A Nos 0 0
11 MCC Power Feeder - 32A Nos 4 10000 40000
12 MCC Power Feeder - 63A Nos 2 15000 30000
13 MCC Control Transformer - Single Nos 0 0 0
14 MCC Control Transformer - Redundant Nos 1 10000 10000
15 MCC Compartmental DOL Starter upto 5KW Nos 41 18500 758500
16 MCC Compartmental DOL Starter upto 5 to 10KW Nos 7 21500 150500
17 MCC Compartmental DOL Starter upto 10 to 20KW Nos 0 26500 0
18 MCC Compartmental DOL Starter upto 20 to 40KW Nos 3 30500 91500
19 MCC Compartmental DOL Starter upto 40 to 60KW Nos 0 95000 0
20 MCC Compartmental DOL Starter upto 60 to 90KW Nos 0 0
21 MCC Compartmental DOL Starter upto 90 to 120KW Nos 0 0
22 MCC Compartmental DOL Starter upto 5KW Nos 0 0
23 MCC Compartmental DOL Starter upto 5KW Nos 0 0
24 Space Heater Nos
25 Ammeter with Selector Switch Nos 3 15000 45000
Total 1425500
Drawout 0
OEM Vendor 0
Total 1425500
600000
Instruments taken from technical offer HOOKUP
S.No Instrument Type Basic Price Quantity Total Quantity Total
3
SWITCHES
8 Pressure Switch 8500 0 2500 0
0
TRANSMITTERS/ ANALYSERS
11 Differential Pressure Transmitter Transmitter 36000 0 8500 0
23 Instruments Racks 0
1,074,380
13 9 5 0
3 2 1 0
Spare (20%) 16 11 6 0
S.No Specification Qty Cost / unit COST
1 JB's ( with 40 terminal blocks) for DI 12 10000 120000
2 JB's ( with 40 terminal blocks) for DO 4 10000 40000
3 JB's ( with 40 terminal blocks) for AI 3 10000 30000
4 JB's 0 10000 0
190000
8 POWER CABLE 0
9 CONTROL CABLE 0
10 INSTRUMENTATION CABLES
1 24C X 1.5 Sq.mm Armoured CU FRLS PVC Insulated 1600 320 512000
2 12 Pair X 1 Sq.mm Armoured CU FRLS PVC Insulated 300 320 96000
3 1 Pair X 1 Sq.mm Armoured CU FRLS PVC Insulated 2750 52 143000
4 3C X 1.5 Sq.mm Armoured CU FRLS PVC Insulated 750 90 67500
818500
1 600 mm width with 50mm Sides & 5mm Th. 50 900 45000
2 450 mm width with 50mm Sides & 5mm Th. 50 750 37500
3 300 mm width with 50mm Sides & 5mm Th. 75 650 48750
4 150mm width with 50mm Sides & 5mm Th. 150 375 56250
5 100mm width with 50mm Sides & 5mm Th. 150 250 37500
6 50mm width with 50mm Sides & 5mm Th. 150 180 27000
150mm width with 50mm Sides & 5mm Th. 100 300 30000
282000
51 6 16 2 14 10 1
TOTAL PG PS LI LT LS FIT FI
DPT PT DPS TT Tur CIT PH ORP TSS SDIA Silica
2
2
2 1
6 4 1 1
0 0 12 0 1 4 1 1 0 0 0
DPT PT DPS TT Tur CIT PH ORP TSS SDIA Silica
AV
7
7
7
25
AV
S.NO Model Quantity
1 MLDB 1
2 ELDB 1
3 SLDB 2
4 DCDB 2
5 PDB 2
1 Lighting Transformer 0
1 3x2.5SQmm cu 500
2 4CX16 Sq.mm -AL 200
3 Incomer Cable 3C 185Sq mm Al 50
4 JUNCTION BOXES 50
5 ACCESSORIES 1
cost/unit Total
175000 175000
20000 20000
20000 40000
20000 40000
20000 40000
450000 0
15000 15000
6500 13000
110 22000
160 8000
650000 0
2000 20000
2500 75000
2000 40000
1500 30000
4500 22500
2500 12500
11000 55000
4500 22500
750 150000
95 47500
120 24000
600 30000
250 12500
50000 50000
0
964500
S.No From To Size QTY
3 Transformer -1 6.6 kV switch board -1 HT- 3C x 240 sq mm
4 Transformer -2 6.6 kV switch board -2 HT- 3C x 240 sq mm
13 Feeder differential protection for HV Cable at Power supply receiving end located at
Total
50000 HT Accessories
4 30 120 950 114000 1200 9600
1 50 50 180 9000 1200 2400
1 20 20 180 3600 1200 2400
1 50 50 180 9000 1200 2400
1 50 50 180 9000 1200 2400
2 75 150 150 22500 800 3200
1 50 50 150 7500 800 800
1 50 50 150 7500 800 800
1 50 50 150 7500 800 800
800 0
1 1500000
3929600 126800
4056400
1 25 25 58000 1450000
1 25 25 58000 1450000
50000
2950000
S.NO Model Quantity cost/unit
1 8 SWG SOLID G.I. WIRE 100 20
2 10MM (3/10") DIA GI WIRE ROPE 100 120
3 25 x 6 G.I. FLAT 100 140
4 40 x 5 G.I. FLAT 200 180
5 50 x 6 G.I. FLAT 300 220
6 SRO 12/14 mm dia MS rod 500 675
7 Lightning Cu Spick 3 2000
8 Earth Pit 15 10000
9 PLC Eirth Pit 2 6000
10 ACCESSORIES 1 50000
Total TAX Total
2000 2000
12000 12000
14000 14000
36000 36000
66000 66000
337500 337500
6000 6000
150000 150000
12000 12000 Keep in Existing room
50000 50000
TOTAL 685500
SL.NO DESCRIPTION PRICE ACCESS COST
QUANTITY
SAFTY EQUIPMENTS
Shock hazard charts 5000 1
first aid boxes 5000 1
caution board 5000 1
discharge Rods 5000 1
DCP 10000 1
CO2 fire extinguishers 5500 8
insulating mats
sand buckets 5000 1
6.6 kV grade hand gloves 2000 2
TOTAL COST
3600000
2985000
3300000
9885000
1850000
385000
3000
2000
112500
10000
2500
4500
5000
5000
5000
5000
5000
10000
44000
0
5000
4000