Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Inspection Checklist

Pipeline Fitup
Document # : HFY-Checklist-5-1-2
Report # PRID #: Project Name: Contractor :
RFI # :
Inspection Time Start: Finish: Inspection Date:
Dwg # / Line # : Area/Location :
Spec Reference : HFY-GEN-PPL-SPC-0016

Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (Write N/A if Not Applicable)
(Record the Data)

Verify the approval of all the Documents (e.g. IFC, Drawing, Procedures,
1 Qualifications of Welding/NDE Personnels etc.)
¨ Acc
¨ Rej
2 Verify all the Pipes are Materials are inspected and approved .
¨ Acc
Before Fit-up: ¨ Rej
Verify the pipes/Fittings/Flanges are cleaned at least 25mm at both side of the
Weld joint .
3 Pipes are internally cleaned.
Beveling done on the Pipes are as per approved WPS.
¨ Acc ¨ Rej
After Fit-up :
Ensire Joint Preparation is made as per the WPS and ASME 31.4 or 31.8 (As
applicable)
Ensure the Joint Number is marked.
Internal misalignment at the prepared joint shal not exceed 10% of the wall
thickness and not more than 1.6mm whichever is smaller.
4 If the misallignment exceed morethan 1.6mm (Due to dimensional variation) ¨ Acc
trimmed 1:4 ratio. ¨ Rej
Distance between 2 Circumferential Joints atleast 2 times of Pipe diameter or
200 mm (Whichever is greater).

Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or
applicable, other activities can be added to the checklist.

Contrator PMC

Name
Date

Signature

760105401.xlsx 1 OF 1

You might also like