Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (Write N/A if Not Applicable)
(Record the Data)
1 Verify the materials with the Material Requisition/ Specification. ¨ Acc ¨ Rej
Check the Identification No./ Tag No. as mentioned on the Delivery Note/Purchase
3 Order. ¨ Acc ¨ Rej
4 Check the physical condition of the materials (e.g. Surface,Size etc.) ¨ Acc ¨ Rej
Verify the Protection/ Preservation Measures taken or not by the Manufacturer or the
5 Supplier. ¨ Acc ¨ Rej
1 Verify the materials with the Material Riquisition/ Specification. ¨ Acc ¨ Rej
3 Check the Batch No. as mentioned on the Delivery Note. ¨ Acc ¨ Rej
Verify the Protection/ Preservation Measures taken or not by the Manufacturer or the
5 Supplier. ¨ Acc ¨ Rej
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract
requirements (Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where
relevant or applicable, other activities can be added to the checklist.