CS G04 (45M + 298 + 45 DAYS EOT, DD: 25 JUL 21) B-001464_GWT_TM_G00_WS_9001

RBL DETAIL TIME PROGRAM_CS_ONE PAGE (FULL)

Activity ID Activity Name Activity BL1 At Completion Start Finish Total 2018 2019 2020 2021 2022 2023 24
Count Duration Duration Float M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
- - - -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
CS G04 (45M + 298 + 45 DAYS
D EOT, DD: 25 JUL 21) 2096 1924 1969 01-Sep-18 A 21-Jan-24 -45

CONTRACTUAL DATES
DATE & OVERSIGHT 31 1924 1969 01-Sep-18 A 21-Jan-24 -45

PLANNED SUBSECTION
SUBSECTIO MILESTONES 53 1438 1472 04-Sep-19 A 15-Sep-23 83

ENGINEERING 1 1234 1234 03-Sep-18 A 18-Jan-22 688

PROCUREMENT 963 1626 1626 27-Nov-18 A 11-May-23 177

MECHANICAL, ELECTRICA
ELECTRICAL/INSTRUMENTATION ETC. 918 1626 1626 27-Nov-18 A 11-May-23 177

MECHANICAL 684 1626 1626 27-Nov-18 A 11-May-23 177

ELECTRICAL/INSTRUMENTATION ETC.
ELECTRICAL/INSTRUMEN 234 1302 1302 01-Oct-19 A 25-Apr-23 60

RAW WATER PIPELINE 45 1183 1125 01-Jun-19 A 29-Jun-22 118

PO 79 - C020 RAW WATER PIPELINE 36 1183 1125 01-Jun-19 A 29-Jun-22 118

C020 BATCH 01 9 254 254 01-Jun-19 A 09-Feb-20 A

C020 BATCH 02 9 549 549 01-Jun-19 A 30-Nov-20 A

C020 BATCH 03 9 1003 1125 01-Jun-19 A 29-Jun-22 118

C020 BATCH 04 9 1183 1125 01-Jun-19 A 29-Jun-22 118

PO 80 - M063 RWP VALVES PORTABLE ACTUATOR 9 534 534 15-Mar-20 A 31-Aug-21 122

GEOTECHNICAL INVESTIGATION
INVE & TOPO SURVEY 3 456 456 01-Sep-18 A 30-Nov-19 A

BUILD (CONSTRUCTIO
(CONSTRUCTION) 684 1536 1570 30-May-19 A 15-Sep-23 83

DSM/GROUND IMPROVEMENT
IMPROVEM 20 488 488 03-Aug-19 A 02-Dec-20 A

GROUND IMPROVEMENT AT INTAKE 5 228 228 03-Aug-19 A 17-Mar-20 A

GROUND IMPROVEMENT AT WTP 15 460 460 31-Aug-19 A 02-Dec-20 A

INTAKE- RAW RIVER WATER


WAT 219 1519 1540 30-May-19 A 16-Aug-23 113

B PM i 100000
PREPARATION/EARLY WO
WORKS 23 745 1152 27-Jun-19 A 21-Aug-22 383

MAIN CIVIL WORKS 195 1323 1344 12-Dec-19 A 16-Aug-23 113

WTP - WATER TREATMENT


TREATMEN PLANT 279 1518 1552 17-Jun-19 A 15-Sep-23 83

B PM P 100030
PREPARATION/EARLY WO
WORKS 19 375 375 17-Jun-19 A 25-Jun-20 A

MAIN CIVIL WORKS 259 1517 1551 18-Jun-19 A 15-Sep-23 83

RWP - RAW WATER PIPEL


PIPELINE 166 879 875 01-Mar-21 A 23-Jul-23 137

ERECTION (ELECTROMECHANICAL)
(ELECTRO 329 584 482 30-Mar-22 24-Jul-23 60

INSTALLATION OF STOPLOGS
STOPL 7 136 176 30-Mar-22 21-Sep-22 -27

ELECTROMECHANICAL A
AT INTAKE & WTP 322 384 384 06-Jul-22 24-Jul-23 60

INTAKE- RAW RIVER WATER


WAT 74 166 109 05-Oct-22 21-Jan-23 60

WTP - WATER TREATMENT


TREATMEN PLANT 236 200 214 05-Oct-22 06-May-23 29

INSTRUMENTATION/COMMON INSTALLATION
INSTRUMENTATION/COM 10 384 384 06-Jul-22 24-Jul-23 60

WORKSHOP TOOLS & SA


SAFETY EQUIPMENTS 2 154 154 07-Feb-23 10-Jul-23 60

TESTS ON COMPLETIO
COMPLETION & COMMISSIONING 32 364 371 16-Jan-23 21-Jan-24 -45

PRE-COMMISSIONING 6 178 185 16-Jan-23 19-Jul-23 -45

INTAKE 3 74 74 16-Jan-23 30-Mar-23 -8

WATER TREATMENT PLANT


PLA 3 74 74 07-May-23 19-Jul-23 -45

COMMISSIONING 26 273 318 10-Mar-23 21-Jan-24 -45

INTAKE 8 89 89 10-Mar-23 06-Jun-23 80

PIPELINE 1 33 33 21-May-23 22-Jun-23 75

WATER TREATMENT PLANT


PLA 14 189 234 18-Mar-23 06-Nov-23 -45

STAGE 2/ TESTS ON COMPLETION


COM FOR TRIAL OPERATION 3 76 76 07-Nov-23 21-Jan-24 -45

RE-BASELINE REMAINING % Actual Progress Date Revision Checked Approved


Page 1 of 1
25-Jul-21 G04 ABDUL MATIN PK
ACTUAL CRITICAL REM. P6 R 19.12.0 ©Oracle Corporation