SEE NOTE-8 WORK SCOPE LIMIT WORK SCOPE LIMIT SEE NOTE-8 1. ALL DIMENSIONS ARE IN MILLIMETERS EXCEPT THE ELEVATIONS
(UNIT 490) (UNIT 490)
ARE IN METERS.
12000
2. EXCAVATION, BACKFILLING WORKS AND MATERIALS SHALL BE DONE
2000 8000 2000 IN STRICT COMPLIANCE WITH AMIES-A-114.
(SHOULDER) (SHOULDER) 3. SUBGRADE & FILL MATERIAL SHALL BE COMPACTED TO 85% RELATIVE
= = DENSITY FOR COHESION LESS SOILS OR 95% OF THE MAXIMUM DENSITY AS
DETERMINED BY ASTM D1557 FOR COHESIVE MATERIALS.
4. TACK COAT SHALL BE APPLIED TO THE SURFACE BETWEEN LAYERS OF
ROAD
1 6000
BITUMINOUS PAVEMENT, VERTICAL EDGES OF PAVEMENT, CURBS AND
OTHER SURFACES IN CONTACT WITH BITUMINOUS PAVEMENT.
-
= = 5. MODULUS OF RESILIENCE FOR BASE COURSE CLASS A=30KSI (CBR=100)
2% SLOPE 2% SLOPE
5% 5% AND CLASS B-25KSI (CBR=50), ASPER AMIES-Q-006.
ROAD
6. EMBANKMENT SLOPE SHALL BE 1V:3H AS PER GEOTECHNICAL
INVESTIGATION REPORT UNLESS OTHERWISE NOTED.
7. THE MARL CAPPING (THK 150) FOR ROADS UNDER UNIT 490 SHALL BE
1 PROVIDED ON EMBANKMENT TO AVOID ANY EROSION.
R.G.L 8. THIS DRAWING WORK SCOPE IS LIMITED TO ROADS ONLY. FOR WORK SCOPE
-
GENERAL FILL MATERIAL EXISTING RELATED TO DRAINAGE SWALES AND ASSOCIATED ITEMS, REFER TO
SUBGRADE 2% SLOPE 2% SLOPE RESPECTIVE WBS PACKAGE DELIVERABLES.
R.G.L
SEE NOTE-8 WORK SCOPE LIMIT WORK SCOPE LIMIT SEE NOTE-8
(UNIT 490) (UNIT 490) GENERAL FILL MATERIAL EXISTING
12000 SUBGRADE
ROAD
2
-
2% SLOPE 2% SLOPE
5% 5%
R.G.L
SEE NOTE-8 WORK SCOPE LIMIT SEE NOTE-8
EXISTING GENERAL (UNIT 490)
LINE OF EXISTING PAD 4600
FILL MATERIAL
(WORK SCOPE
UNDER UNIT 700) (WORK SCOPE
UNDER UNIT 700) = =
ROAD
SCALE N.T.S
1
SEE NOTE-8 WORK SCOPE LIMIT WORK SCOPE LIMIT SEE NOTE-8 -
(UNIT 490) (UNIT 490)
10000/4600 2% SLOPE 2% SLOPE
(SEE ROAD LAYOUT)
EDGE OF ASPHALT
EDGE OF ASPHALT
ASPHALT ASPHALT
1 IFC 12-OCT-2023 ISSUE FOR CONSTRUCTION Y.B. LEE D.K. KIM Y.B.IM
BINDER COARSE (CLASS-A) BINDER COARSE (CLASS-A)
TACK COAT RC-70 TACK COAT RC-70 0 IFR 07-SEP-2023 ISSUE FOR REVIEW Y.B. LEE D.K. KIM Y.B.IM
UNIT 490
50
ROAD LEVEL
70
EXISTING
3 AMIRAL
TEMP. ROAD CONCTRUCTED
250
UNDER UNIT 700
1
BASE COARSE
EXISTING
PROJECT
150
R.G.L
This document is the property of AMIRAL and shall not be disclosed to third parties or reproduced without permission of the owner.
This document has been generated by an Electronic Document Management System. When printed it is considered as a for information
EXISTING only copy. The controlled copy is the screen version and it is the holder's responsibility that he/she holds the latest valid version.
COMPACTED AGGREGATE BASE COARSE AGGREGATE BASE COARSE GENERAL FILL MATERIAL
(TYPE-A) EXISTING (TYPE-A)
SUB-BASE AS PER AMIES-A-114
COMPACTED STANDARD DETAILS FOR ROAD
EXISTING SUBGRADE (SEE NOTE-3) SUB-BASE EXISTING SUBGRADE/
EMBANKMENT
Doc Type: STD Discipline: CIV Phase: DE Class: 2 System / Subsystem: NA Equipment Type: NA
1 DETAIL 2 DETAIL TYPICAL EMBANKMENT DETAIL Contractor
Document -
Site
-
- SCALE N.T.S - SCALE N.T.S SCALE N.T.S Number : Reference:
Company Rev: Scale: Format: Sheet:
Document SA-AMI-000-HDAI-370104
ID : 1 N.T.S A1 001