DMRC DC-05 Contractual Note Afcons

1) Which of the following is not a key benefit of contract risk management?

(a) Maximum benefit to contractor


(b) Understanding of contractual liabilities
(c) Identification of process improvements
(d) Enhanced corporate governance

2) What is the full form of DLP in terms of Contract?

a) Defects Loss Prevention


b) Defects Liability Period
c) Digital Larning Program
d) Direct Legal Propup

3) An agreement becomes a contract if:

a) It is by free consent of the parties.


b) Parties are competent.
c) It is enforceable by law.
d) None of the above.

4) Contract DC-05 is in line with which form of FIDIC Contract:

a) Red Book
b) Yellow Book.
c) Silver Book.
d) Grey Book.