6.

Computer Room Air Conditioners

Pre-functional checklist for CRAC units


Equipment Tag: Manufacturer:
Location: Serial number:
Area Served: Date:
Item Ensure Yes No Remarks
1 Transit bolts, brackets etc. are removed.
2 Pipe vacuum and nitrogen test are approved.
3 The fan motor rotates freely.
4 All components are in good condition and no damage or leaks
is visible
5 There is no visual damage to the external casing of the unit or
damage to the internal parts
6 Safety guards and panels fitted and secure.
7 Ensure that the walls, floor, and ceiling of the room where the
cooling unit is located are sealed with a vapor barrier.
8 All electrical components are undamaged
9 Suitable fuses and overloads are fitted.
10 Air system access covers are secure
11 Room humidity is below 60% relative humidity and room
construction is complete.
12 Condenser drain pipe is connected to main line.
13 Incoming voltages match the phase and voltage rating on the
nameplate.
14 Filters are in place, properly cleaned and accessible.
15 All electrical aspect was commissioned and approved.
16 All electrical connections are correct, and that the unit is
isolated.
17 All terminals connection is securely tightened.
18 Electrical cables are properly terminated and sized.
19 Circuit breakers are correct and securely attached to the DIN
rail.
20 The primary and secondary power feeds are properly
connected.
21 Fans rotate in the correct direction as marked.
22 Unit identification tags and labelling works are complete.
Remarks: