Professional Documents
Culture Documents
Report On Preliminary Survey of Existing Rundu WTW Site To Sikondo Mupini Pipeline Route - Rundu WTP Project
Report On Preliminary Survey of Existing Rundu WTW Site To Sikondo Mupini Pipeline Route - Rundu WTP Project
Report On Preliminary Survey of Existing Rundu WTW Site To Sikondo Mupini Pipeline Route - Rundu WTP Project
1. Objectives
To know the location and distribution of the pipe line on the ground.
To take note of any obstruction that may delay or interfere with the construction of the
pipeline.
To make a preliminary survey of the pipe line route.
3. Methodology
This was the preliminary survey of the proposed clear water Main Gravity pipe from Existing
Rundu WTW Site to Sikondo Mupini Pipeline route. All chainages along the pipeline were
located in a sequence of one after another and all features of interest or features within the
premises of the Pipeline were physically surveyed and noted. All drawing were done in Auto
cad 3D Civil.
4. Observations
a) There is a section of construction drawing missing i.e.W12.18–W12.30 between
W12.17 and W12.31
1
Figure 1:
The distance between the existing boundary wall and the proposed water pipeline is
0.009mm
Figure 2:
Between point W12.60 – W12.61 the pipeline cut through an encroached boundary
wall and Stoop labelled as existing house on the figure above.
At W12.61 the existing house surpassed the pipeline with 0.56cm onto the street
2
Figure 3:
Boundary wall encroachment
Figure 4: This picture was taken on site showing the toilet and encroached building shown in
figure 3
3
Figure 5: Structure of building through Vambo location where the pipeline passed
Figure 7: This picture was taken on site for the features surveyed above
4
Figure 8: Boundary wall close to the pipeline premises
Boundary wall close to the pipeline premises
There is a distance of 0.692cm between the wall and pipeline centre
Figure 9:
Manhole crossing road
Gum tree in the middle of the pipeline
5
Figure 10: This picture was taken from Google satellite showing surveyed features in
figure 9 above
6
Figure 12: Section where the Pipeline passed between culverts
7
Figure 14: Intersection of the road to Sikondo
Two gum trees at the intersection
Figure 15: Screenshot was taken from Google earth for surveyed features above
Pipeline crossing bitumen road
8
Figure 16: Surveyed gum trees and boundary wall along the pipeline
Distance between gum trees and pipeline indicated
Boundary wall surveyed
Pipeline located
9
Figure 17: Screenshot from Google earth for surveyed features above
5. Conclusion
For all the chainages provided with the design of the pipeline, preliminary demarcation was
done and all features interfering with the premises of the pipeline were surveyed and noted.
The challenges and obstructions within the pipeline alignment due to the permanent structures
and natural trees shall be reviewed and resolved with the Engineer.
10