Professional Documents
Culture Documents
06 Calculations
06 Calculations
Table of content.
The dry film thickness (DFT) of an applied coating can be determined if the percent
volume solids (% VS) and the wet film thickness (WFT) are known. This information
can be obtained from the manufacturer’s Technical Data Sheets. The equation for
calculating the dry film thickness is:
Example 1:
A coating is to be applied at wet film thickness of 250 microns, and the percent
volume solid is 50 percent. The equation becomes:
The wet film thickness can be determined if the percent volume solids (%VS) and the
dry film thickness (DFT) are known. This information can also be obtained from the
manufacturers Technical Data Sheets. The equation for calculating the WFT is:
Example 2:
A coating is to be applied at a dry film thickness of 100 microns. The percent volume
solid is 65 %.
The coating must be applied in a WFT of 154 microns since 35% of the paint is
solvents that will evaporate.
If the coating is thinned 20 % to adjust the viscosity for application the solid by
volume will change, it decreases. The new volume percent solids can be calculated or
found in a table (See tables in section 16.2).
Example 3:
If one litre of a coating with 65 percent volume solid is thinned 20%, the total volume
of the coating will increase to 1.2 litres. The new percentage by volume of solid is:
The new WFT, to get a DFT of 100 microns after adding 20%, is:
The coating must be applied in a WFT of 185 microns, since 46 % of the paint in the
tin is solvents that evaporates.
Example 4:
Another way of calculating the new WFT after thinning is given by the formula:
New WFT : DFT x (100 + % added thinner) = 100 microns x 120 = 185
microns
% VS 65 % VS
See also the Table in section 16.3: “Solids content after thinning”.
The theoretical spreading rate (m2/litre) is the area covered by one litre of paint for a
given dry film thickness. Thus, the spreading rate can be determined if the percent
volume solid and the desired dry film thickness are known. The equation for
calculation is:
The theoretical consumption of a coating can be determined if the area (m 2), the
or
The constant 10 is a correction factor for the different units included in the formula
and derives from the following:
First, let us calculate the paint consumption in m 3. Here we have to include the
correlation factor for transforming from metres to microns. We know that 1 m =
1.000.000 microns, and get the following equation:
However, we would like to order the paint in litres and not in m 3. Then, we have to
convert by introducing that 1 m3 = 1000 litre, and we get the equation:
Paint consumption in litre = area (m2) x DFT (microns) x 100 % x 1000 l/m3
% V.S. x 1 000 000 microns/m
Example 5:
The outside of a tank is to be painted. The total area is 500 m 2. The following paint
system is to be applied by airless spray:
The above example assumes that there is no loss of paint during the job and that every
drop of paint is applied to the surface. In a real situation some of the paint will be lost:
The coating may miss target due to strong wind, very complex geometry of the
structure or by poor application technique.
Overspray due to complex geometry of the structure or by poor application
technique.
Some material will be left in the pump, the tins or in the container.
Dead volume: See section 16.1.8.
Such paint losses are usually in the range of 25 – 40 %, but may accumulate to as
high as 50 percent of the total theoretical volume. Loss of paint must always be
included when the total paint consumption is calculated. Further, it is important to
calculate the volume of paint to order in the correct manner. If the theoretical amount
of paint needed is 100 litres and the loss is 40 %, only 60 % of the actually paint is left
on the surface after painting. The loss factor is 0.6. The equation for calculation is:
Example 6:
The same figures as for Example 5 are used, but now a loss of 40% (loss factor of
0.6) is included. The correct amount of paint to order will be:
Blast-cleaning will increase the surface roughness and thereby increase the surface
area. The roughness will depend on the abrasive used. However, the consequence is
that more paint is needed to cover the increased area. “The dead volume” is the
amount of paint needed to fill in for the roughness (profile) on the blast-cleaned steel.
(From the bottom to the top of the valley). The amount of paint (l/m2) needed to fill in
the roughness is indicated below:
The equation for calculating the paint consumption, including loss and dead volume
is:
Total paint consumption (litre): Area (m2) x dead Volume (l/m2) x 100
% VS x loss factor
NB! The “dead volume” is only a factor which effect the paint consumption for the
primer or the first coat of a paint system.
Example 7:
Here example 6 is taken one step further. The loss is 40%. The surface of 500 m 2 is
blast-cleaned to Sa 2 ½ with a roughness of 60 microns. A roughness of 60 microns
gives a dead volume of 0,04 l / m2 (see table above).
As Epoxy mastic is used as a first coat we have to include the dead volume:
The total need of Epoxy mastic is: 39 litres + 196 litres = 235 litres
As the dead volume will have no influence on the topcoat the volume of the
Polyurethane is the same as in example 6:
Table 16.2.1.
Loss in % and corresponding loss factor
Table 16.2.2.
Dead volume as function of surface roughness.
Table 16.2.3.
Volume solids (%VS) after thinning.
Formula used: