2 Storey Residential Plan

Location: LOT 10, BLOCK 6, VITA TOSCANA SUBD., BACOOR CITY, CAVITE Period Highlight: 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)

PLAN ACTUAL ACTUAL PERCENT


ACTIVITY PLAN START PERIODS
DURATION START DURATION COMPLETE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
I. Pre Construction
100%
Design and Planning 31/08/2023 5 days 30/09/2023 5 days

1.1. Specifications Bids 100%


and Contract 01/09/2024 6 days 01/10/2024 6 days

1.2. Obtain Permits 01/12/2024 7 days 02/10/2024 12 days 70%

1.3. Permit Approved 02/09/2024 8 days 03/10/2024 5 days 10%


2. Survey, Layout, 85%
Excavation 03/09/2024 9 days 04/10/2024 13 days

2.1. Survey of the Lot 04/09/2024 10 days 05/10/2024 13 days 65%

2.2. Excavation 05/09/2024 11 days 06/10/2024 14 days 50%

2.3. Site Preparation 06/09/2024 12 days 07/10/2024 12 days 60%


2.4. Layout the Location
75%
of Column-Footing 07/09/2024 days 08/10/2024 13 days
2.5. Material 100%
Procurement 08/09/2024 14 days 09/10/2024 14 days

3. Foundation Works 09/09/2024 15 days 10/10/2024 15 days 60%


3.1. Formwork
0%
Installation 10/09/2024 16 days 11/10/2024 16 days
3.2. Fabrication of 50%
Rebars 11/09/2024 17 days 01/10/2025 17 days
3.3. Concrete Pouring
in Footing and 0%
Footing Tie Beam 12/09/2024 18 days 02/10/2025 13 days
3.4. Curing and 1%
Drying 01/09/2025 19 days 03/10/2025 17 days

3.5. Backfilling Work 02/09/2025 20 days 04/10/2025 20 days 80%

3.6. Plinth Work 03/09/2025 21 days 05/10/2025 15 days 0%

3.7. Waterproofing 04/09/2025 22 days 06/10/2025 11 days 0%

3.8. Inspection and 0%


Quality Control 05/09/2025 23 days 07/10/2025 25 days

3.9. Structural Work 0%


Columns 06/09/2025 24 days 08/10/2025 16 days
3.10. Ground Floor
44%
Slab 07/09/2025 25 days 09/10/2025 23 days

0%
3.11. First Floor Work 08/09/2025 26 days 10/10/2025 23 days
4. Stair Work
Staircase Layout and 12%
Marking 21/09/2024 27 days 11/10/2025 9 days
4.1. Cutting and
Shaping Stair 5%
Components 22/09/2024 31 days 12/10/2025 28 days

4.2. Fabrication of 0%
Rebars 23/09/2024 29 days 13/10/2025 19 days
4.3. Concrete
50%
Pouring 24/09/2024 30 days 14/10/2025 30 days
4.4. Installation of 0%
Stair Stringers 25/09/2024 31 days 15/10/2025 31 days
4.3. Installation of 50%
tread and risers 26/09/2024 32 days 16/10/2025 25 days
4.4. Installation of
Handrails and 0%
Balluster 27/09/2024 33 days 17/10/2025 13 days

4.5. Stair Finishing 28/09/2024 34 days 18/10/2025 34 days 50%


PLAN ACTUAL ACTUAL PERCENT
ACTIVITY PLAN START PERIODS
DURATION START DURATION COMPLETE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

5. Truss Work 29/09/2024 35 days 19/10/2025 21 days 0%


5.1. Truss Design
50%
and Engineering 30/09/2024 36 days 20/10/2025 26 days
5.2. Material
Procurement for 0%
Trusses 01/10/2024 37 days 21/10/2025 27 days
5.3. Truss
Component
Cutting and 50%
Shaping 02/10/2024 38 days 22/10/2025 30 days
5.4. Truss
0%
Assembly 03/10/2024 39 days 23/10/2025 29 days
5.5. Truss
Inspection 50%
04/10/2024 40 days 24/10/2025 10 days
5.6. Truss 0%
Installation 05/10/2024 41 days 25/10/2025 28 days

Page 2 of 2