Innovacin en Servicios en Generacin de Energa Modernizacin - Oliver Neukrantz
Innovacin en Servicios en Generacin de Energa Modernizacin - Oliver Neukrantz
Oliver Neukrantz
1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension
SGT5-3000E (V94.2A)
2000
1996 2007
V84.3
1994
V64.3
1990 V94.3
1995
SGT6-2000E (V84.2) SGT-1000F (V64.3A)
V94.1 1989 1997
1980
V82.0
SGT5-2000E (V94.2)
V94.0 1981
1974
V43
VM5 V93.0
1972
VM1 1960
1956
VM80
1961
1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010
Years
* V-Technology, large Scale, As of May 2010
© Siemens AG 2010. All rights reserved.
Page 3 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Siemens Gas Turbines –
Complete Product Portfolio for 50 Hz and 60 Hz
SGT5-8000H 375
SGT5-4000F 292
SGT6-8000H 274
SGT6-5000F 208
SGT5-2000E 168
SGT6-2000E 113
SGT-800 47
SGT-700 31
SGT-600 25
SGT-500 17
SGT-400 13
SGT-300 Output in MW @ ISO conditions
8
SGT-200 Large-scale gas turbines
7
SGT-100 Industrial gas turbines
5
2005
• Compressor Mass Flow Increase
2004
• Turndown 2003
• Hydraulic Clearance Optimization
• HR3 Burner 1997 3)
• Firing Temperature Increase
Power Output
Additional Modernization & Upgrades
• Advanced Compressor Coating • Advanced Compressor Cleaning System • Wet Compression
• EVAP Cooler • Foreign Object Detection System • Fuel Conversion
1) Source: Framebook as of June 2010 2) 17-stage compressor
3) Since 1998: 15-stage compressor 4) Expected values only, site specific values may vary
• Siemens innovative 3D
Blades and Vanes 1+2 2008
[173 MW; 35,8 %**]
• Compressor Mass Flow Increase
• 41MAC 2001
• Firing Temperature Increase
2006
• Turbine Section Upgrade
Efficiency
Ongoing Development
1981
[118 MW; 32,4 %]
• Hydraulic Clearance Optimization
Power Output
Additional Modernization & Upgrades
• Advanced Compressor Coating • Fuel Gas Preheating • Fuel Conversion
• EVAP Cooler
1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension
100
90
Introduction of
IndexOutageDuration(2001=100)
Major
80
HGPI* concept eHGPI
HGPI
70
60
50
40
30
2001 2002 2003 2004 2005 2006 2007 2008 2009 Ye ar
based on
GT-Availability: 94,7% * EOH
blades and
HGPI (or Major) eHGPI (or Major) LTE
vanes stage 1
HR3 burner & turbine
and flame tube
Recoating of compressor vanes stage 2,
41 M AC Concept, 8 kEOH Minor Inspection Interval
modification
bladesAdvanced
stages 1 inner casing
– 6 and new blades
compressor design
vanes stages
GT-Availability: 97,3% *, optimized availability based on EOH
0 – 3 every 41,000 EOH Caulking of compressor
Major Major new vanes, new blades
* based on planned outage days only, for 100 kEOH operation period © Siemens AG 2010. All rights reserved.
Page 9 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Development of availability, example SGT5-2000E
Development of availability
3 %
Combined >
effect on GT Δ
availability:*
41MAC
%
33MAC
pastpast
(2001) today, 33MAC today, 41MAC
Availability* increase of
* based on planned outage days and standard more than 3 percentage points
workscope only
© Siemens AG 2010. All rights reserved.
Page 10 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Serviceability of Power Plants –
Example of Multi-Outage on Single Shaft Configuration
ZGK 039
Storage area
Storage area outside UMC outside UMC
Rolling Rolling
Shutter „A“ clearance Wende- +/- 0,00m Shutter „B“
Trailer wvor-
mw
v14
v13
v12
v11
v3
v2
t2
v15
v10
v9
v8
v7
v6
v5
v4
v1
t4
t3
t1
&n Trailer
3000 x 4500 7500 7500 x 7600
richtung
W xH W xH
Storage area
outside UMC
Outage duration dependant on plant layout – longer than longest single event.
Total area need for infrastructure, workspace and storage: 5.500 m²
© Siemens AG 2010. All rights reserved.
Page 11 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Agenda
1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension
Efficiency Increase
Emission
Reduction
Operational Efficiency
Flexibility Increase
Customer
Customer
Needs
Needs
Availability Increase Power Increase
25
Reliability & 50 75 1 00 k EOH
Power Recovery by upg rade
Power Increase
2 5 MAC Conc ept , 4 kEOH Minor Ins pec tion Int erva l
Availability
G T-Availab ility: 94,7% *
based on
EOH
100%Increase
Ma jor Major Major LTE
SG T5-2000E
3 3 MAC Conc ept, 8 kEOH MinorI ns pe cti on Interva l
ba se d on E OH
Degrading by aging
GT -A va ilability : 96,8 % *, optimize d power out put
Power output
HGPI (or Ma jor) eHGPI ( orMajor) LTE
Reco very b y overh aul
4 1 MAC Conc ept, 8 kEOH MinorI ns pe cti on Interva l
Degra ding b y fouling
GT -Availability : 97,3 % *, opt imize dav aila bility
Maintenance
based o n EOH
Ma jor Major
Operatio n hours
Cost Reduction
© Siemens AG 2010. All rights reserved.
Page 13 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Comprehensive OEM Engineering Support
Analysis Evaluation
Product
Fleet
Change
Data
Base Manage
Analysis -ment
Checklists
© Siemens AG 2010. All rights reserved.
Page 14 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
The Product Development Process (PDP) @ Siemens
Design Validation
Market Demand Product Planning
Planning
P roduct P rod.&Dev elop.
Design
Prep. Implementation
Conceptual Basic
Preparation
Commerciali-
Desi gn Implementation
Final Design, Manufacturing Installation, Product
Validation
Perfor mance
Str ategy P lanning Design Design zation P lanning P rocurem ent & As sembly Trial Operation Monitoring Validation
M00 M10 M20 M30 M40 M50 M60 M70 M80 M90 M100
time
Fleet Experience
R0 R1 R2 R3 R4 R5 R6 R7 R8 R9 R10
Single Events Minimizing risks by conducting mandatory reviews in interdisciplinary teams (e.g.
marketing, engineering, manufacturing, service …)
Reported From Sites
Engineered Solution:
Specific Solution, Fleet Solution, M&U-Product
1 Month
Invitation
email 2 Month
Survey
completion 2 Month
Results User Group
Meeting
4 Month
Customer 1 Month
Feedback
UGM Documentation
(Mailing & CEP)
10 Month
© Siemens AG 2010. All rights re served.
Page 16 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-4000F / V94.3A
Example: Starting Reliability Package
Customer Feedback
SGT5-4000F
1 2 3
1 2 3
M00 M10 M20 M30 M40 M50 M60 M70 M80 M90 M100
Fleet Experience
R0 R1 R2 R3 R4 R5 R6 R7 R8 R9 R10
Single Events Minimizing risks by conducting mandatory reviews in interdisciplinary teams (e.g.
marketing, engineering, manufacturing, service …)
Reported From Sites
Engineered Solution:
Specific Solution, Fleet Solution, M&U-Product
SGT5-4000F 15 stage
V94.3A 17 stage
© Siemens AG 2010. All rights re served.
Page 21 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Compressor Stator Rings
Design Concept Fleet Experience
Outer
Ring
Compressor
Ring Segment Vane
Compressor
vanes
• 1 Outer Ring
• Vanes Inner
Ring II
• 2 Inner Rings
Inner Ring
I
Inner Ring
II weld
Inner
Ring I
Solution
1. Smooth transition
hook / airfoil
2. Plain (parallel)
hook surfaces
3. Increased hook
width
Frequency Tests (Modal Analysis) at Berlin Factory performed for new design.
M00 M10 M20 M30 M40 M50 M60 M70 M80 M90 M100
Fleet Experience
R0 R1 R2 R3 R4 R5 R6 R7 R8 R9 R10
Single Events Minimizing risks by conducting mandatory reviews in interdisciplinary teams (e.g.
marketing, engineering, manufacturing, service …)
Reported From Sites
Engineered Solution:
Specific Solution, Fleet Solution, M&U-Product
Market Demand
Operational Flexibility
Source: Global Wind Energy Council, 2010
Improved
Start-up Curve Current
Smart Grids ST+GT
Start-up
Plant Load
loading
Curve
GT+ST
Improvement
parallel
Start-up
GT Hold-time
GT Start-up
Time
© Siemens AG 2010. All rights re served.
Page 27 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
More Operational Flexibility - Example
Wet Compression - How it Works Market Demand
Air Intake
Comb.
Compressor Turbine
Chamber
Cooling Air
Efficiency improvement
© Siemens AG 2010. All rights reserved.
Page 28 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Siemens Gas Turbine Modernization
Wet Compression Market Demand
Main Facts
Benefit
Power output improvement*
References
More than 40 Wet Compression syste ms**
installed on the frame types SGT5-2000E,
SGT6-2000E, SGT6-3000E and W501FC+.
o … neutral
Market Driver Power Efficiency Emission Reliability & Operational Maintenance
Product Increase Increase Reduction Availability Flexibility Cost Reduction
ACC
(Advanced Compressor Coating)
+ + o + o o
ACCSpro (Siemens‘ Advanced
Legend: + … positive
Compressor Cleaning System – + + o + o o
pro)
CMF+
(Compressor Mass Flow ++ o o o o o
Increase)
EVAP Cooler ++ o o o + o
FODS (Foreign Object Detection
System) o o o ++ o o
Fuel Conversion
(according to SIGAMA) o o o o + o
HCO (Hydraulic Clearance
Optimization) + + o o o o
TD (Turndown) o + o o ++ o
33MAC o o o ++ + ++
41MAC o o o ++ + ++
ACC
(Advanced Compressor + + o + o o
Coating)
CMF+
(Compressor Mass ++ o o o o o
Flow Increase)
EVAP Cooler ++ o o o + o
FTI
(Firing Temperature ++ + o o o +
Increase)
Fuel Conversion o o o o + o
HR3-Burner o o ++ + o o
Legend: + … positive
o … neutral
IGV Modification o o o + o o
LTE
(Lifetime Extension)
o o o + o +
OTC Control
Optimization
o o o o + +
Legend: + … positive
o … neutral
1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension
AL:N ECCN: N
component at optimum performance levels
with out
Average overall component risk prior to Lifetime Extension
Average overall component risk with Lifetime Extension End of Design Life
100,000 EOH /
Average overall component risk without Lifetime Extension
3,000 starts
LTE
Potential for increased
Major Inspection * risk of operation
beyond 100,000 EOH /
3,000 starts without
Risk
Lifetime Extension
Compressor Compr. stator II, Burner complete: Combustion Chamber Disk spring stack,
blades & vanes: Diffusor, Radiation •Creep Outer shell Screws, Tile holder:
•Creep liner: •Wet Corrosion •Oxidation, Corrosion •Creep
•Wet corrosion •Creep •Low cycle fatigue •Creeping, Material removal •(Low cycle fatigue)
•Low cycle fatigue •Low cycle fatigue •High cycle fatigue •Low cycle fatigue
•High cycle fatigue •Material removal •High cycle fatigue Housing: • Creep
•Low cycle fatigue
Tie rod nut, cooling air, Tie Rod, middle hollow shaft, Turbine stator: Turbine B&V:
front/rear hollow shaft, Compr./Turbine disks: •Creep •Oxidation, Corrosion
intermediate shaft: •Creep •Low cycle fatigue •Creeping, Material removal
•Low cycle fatigue •Low cycle fatigue
•Creep
•Low cycle fatigue •High cycle fatigue •High cycle fatigue
SGT5-40 00F
3500 SGT5-20 00E
LTE
3000
2500
Number Of Starts
2000
1500
1000
500
0
-10.000 10.000 30.000 50.000 70.000 90.000 110.000 130.000 150.000
MO HGPI
MO
1.LTE
LTE Pre-review Replace ment of
• Evaluation Questionnaire limited Components
• Final Outage meeting
• Operation history analyzing MO + LTE
• LTE recomme ndation by unit
• Destructive Inspections
AL:N ECCN: N
specific investigation
• NDT Inspections
• Repairs
• Replace ments
• Evaluation
© Siemens AG 2010. All rights reserved.
Page 39 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
LTE Experience
Example: Rotor of mature frames
Rotor
UT Indication
Inspected GTs
without
indications
79%
Inspected GTs
with indications
21%
This docum ent contains forward-looking statements and information – that is, statements related to
future, not past, events. These statements may be identified either orally or in writing by words as
“expects”, “anticipates”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “will” or words of similar
meaning. Such statements are based on our current expectations and certain assumptions, and are,
therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond
Siemens’ control, affect its operations, performance, business strategy and results and could cause
the actual results, performance or achievements of Siemens worldwide to be materially different from
any future results, performance or ac hievements that m ay be expressed or implied by such forward-
looking statements. For us, particular uncertainties aris e, among others, from changes in general
economic and business conditions, changes in currenc y exchange rates and interest rates,
introduction of c ompeting products or technologies by other companies, lac k of acceptance of new
products or services by custom ers targeted by Siemens worldwide, changes in business strategy and
various other factors. More detailed information about certain of these factors is contained in
Siemens’ filings with the SEC, which are available on the Siemens website, www.siemens.com and
on the SEC’s website, www.sec.gov. Should one or more of these risks or uncertainties m aterialize,
or should underlying assumptions prove incorrect, actual results may vary materially from those
described in the relevant forward-looking statement as anticipated, believed, estimated, expected,
intended, planned or projected. Siem ens does not intend or assume any obligation to update or revise
these forward-looking statements in light of developments which differ from those anticipated.
Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or their
respective owners.