Download as pdf or txt
Download as pdf or txt
You are on page 1of 46

Energy - Día de la Innovación

Oliver Neukrantz

© Siemens AG 2010. All rights reserved.


Agenda

1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension

© Siemens AG 2010. All rights reserved.


Gas Turbine Development Path
 V-Frames 50/60Hz and Future Frames 50Hz

More than 700 units in commercial operation worldwide! *

SGT5-3000E (V94.2A)
2000

SGTx-4000F (Vx4.3A) SGT5-8000H


Technology

1996 2007

V84.3
1994
V64.3
1990 V94.3
1995
SGT6-2000E (V84.2) SGT-1000F (V64.3A)
V94.1 1989 1997
1980
V82.0
SGT5-2000E (V94.2)
V94.0 1981
1974
V43
VM5 V93.0
1972
VM1 1960
1956
VM80
1961

1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010
Years
* V-Technology, large Scale, As of May 2010
© Siemens AG 2010. All rights reserved.
Page 3 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Siemens Gas Turbines –
Complete Product Portfolio for 50 Hz and 60 Hz

SGT5-8000H 375

SGT5-4000F 292

SGT6-8000H 274

SGT6-5000F 208

SGT5-2000E 168

SGT6-2000E 113
SGT-800 47
SGT-700 31

SGT-600 25
SGT-500 17
SGT-400 13
SGT-300 Output in MW @ ISO conditions
8
SGT-200 Large-scale gas turbines
7
SGT-100 Industrial gas turbines
5

Extension of our product portfolio to satisfy customer demands

© Siemens AG 2010. All rights reserved.


Page 4 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-4000F / V94.3A Gas Turbine
Customer Driven Product Development

• Firing Temperature Increase


• Improved Hot Gas Parts 2008
[292 MW; 39,8 % 4) ]
• Burner Upgrade (Low-NOx  Premix-Pilot)
• Cooling Air Reduced Combustion Chamber
• Burner Upgrade (Reduced Swirl)
• Fuel Gas Preheating
Efficiency

2005
• Compressor Mass Flow Increase
2004
• Turndown 2003
• Hydraulic Clearance Optimization
• HR3 Burner 1997 3)
• Firing Temperature Increase

170 Units in Commercial Operation 1)


Total EOH > 5.636.000
Lead Unit EOH > 104.000 Ongoing Development
1996 2)
[240 MW; 37,0 %]
• Further Firing Temperature Increase

Power Output
Additional Modernization & Upgrades
• Advanced Compressor Coating • Advanced Compressor Cleaning System • Wet Compression
• EVAP Cooler • Foreign Object Detection System • Fuel Conversion
1) Source: Framebook as of June 2010 2) 17-stage compressor
3) Since 1998: 15-stage compressor 4) Expected values only, site specific values may vary

© Siemens AG 2010. All rights reserved.


Page 5 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-2000E / V94.2 Gas Turbine
Customer Driven Product Development

• Siemens innovative 3D
Blades and Vanes 1+2 2008
[173 MW; 35,8 %**]
• Compressor Mass Flow Increase
• 41MAC 2001
• Firing Temperature Increase
2006
• Turbine Section Upgrade
Efficiency

• HR3 Burner 2003


• 33MAC 1998
1996 • Wet Compression
198 Units in Commercial Operation*
Total EOH > 13.212.000 • Siemens innovative 3D
Lead Unit EOH > 260.000 Blades and Vanes 3+4

Ongoing Development
1981
[118 MW; 32,4 %]
• Hydraulic Clearance Optimization

Power Output
Additional Modernization & Upgrades
• Advanced Compressor Coating • Fuel Gas Preheating • Fuel Conversion
• EVAP Cooler

* Source: Framebook as of June 2010


** Expected values only, site specific values may vary

© Siemens AG 2010. All rights reserved.


Page 6 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Agenda

1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension

© Siemens AG 2010. All rights reserved.


Development of Outage Durations
(standard work scope, without findings)

100

90
Introduction of
IndexOutageDuration(2001=100)

Major

80
HGPI* concept eHGPI
HGPI

70

60

50

40

30
2001 2002 2003 2004 2005 2006 2007 2008 2009 Ye ar

*HGPI = Hot Gas Path Inspection,


eHGPI = extended Hot Gas Path Inspection
© Siemens AG 2010. All rights reserved.
Page 8 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Development of Maintenance Schedule
Example SGT5-2000E
25 50 75 100 k EOH

25 M AC Concept, 4 kEOH Minor Inspection Interval

based on
GT-Availability: 94,7% * EOH

Major Major Major LTE


SGT5-2000E
33 M AC Concept, 8 kEOH Minor Inspection Interval
Advanced mixing chamber New coatings
GT-Availability:design
96,8% *, optimized power output
on turbine based on EOH

blades and
HGPI (or Major) eHGPI (or Major) LTE
vanes stage 1
HR3 burner & turbine
and flame tube
Recoating of compressor vanes stage 2,
41 M AC Concept, 8 kEOH Minor Inspection Interval
modification
bladesAdvanced
stages 1 inner casing
– 6 and new blades
compressor design
vanes stages
GT-Availability: 97,3% *, optimized availability based on EOH
0 – 3 every 41,000 EOH Caulking of compressor
Major Major new vanes, new blades
* based on planned outage days only, for 100 kEOH operation period © Siemens AG 2010. All rights reserved.
Page 9 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Development of availability, example SGT5-2000E

Development of availability

3 %
Combined >
effect on GT Δ
availability:*

41MAC
%

33MAC
pastpast
(2001) today, 33MAC today, 41MAC

Availability* increase of
* based on planned outage days and standard more than 3 percentage points
workscope only
© Siemens AG 2010. All rights reserved.
Page 10 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Serviceability of Power Plants –
Example of Multi-Outage on Single Shaft Configuration
ZGK 039

Storage area
Storage area outside UMC outside UMC

Container Container Container Container Container Container Container Container

Rolling Rolling
Shutter „A“ clearance Wende- +/- 0,00m Shutter „B“
Trailer wvor-
mw
v14
v13
v12
v11
v3
v2
t2
v15
v10
v9
v8
v7
v6
v5
v4
v1
t4
t3
t1
&n Trailer
3000 x 4500 7500 7500 x 7600
richtung
W xH W xH

Con Container Container


Con tai n +4,50m
tai n er
er

Storage area
outside UMC

Outage duration dependant on plant layout – longer than longest single event.
Total area need for infrastructure, workspace and storage: 5.500 m²
© Siemens AG 2010. All rights reserved.
Page 11 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Agenda

1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension

© Siemens AG 2010. All rights reserved.


Customer’s Needs are our Market Drivers!

Efficiency Increase
Emission
Reduction

Operational Efficiency
Flexibility Increase

Customer
Customer
Needs
Needs
Availability Increase Power Increase
25
Reliability & 50 75 1 00 k EOH
Power Recovery by upg rade

Power Increase
2 5 MAC Conc ept , 4 kEOH Minor Ins pec tion Int erva l

Availability
G T-Availab ility: 94,7% *
based on
EOH
100%Increase
Ma jor Major Major LTE
SG T5-2000E
3 3 MAC Conc ept, 8 kEOH MinorI ns pe cti on Interva l

ba se d on E OH
Degrading by aging
GT -A va ilability : 96,8 % *, optimize d power out put

Power output
HGPI (or Ma jor) eHGPI ( orMajor) LTE
Reco very b y overh aul
4 1 MAC Conc ept, 8 kEOH MinorI ns pe cti on Interva l
Degra ding b y fouling
GT -Availability : 97,3 % *, opt imize dav aila bility
Maintenance
based o n EOH

Ma jor Major
Operatio n hours

Cost Reduction
© Siemens AG 2010. All rights reserved.
Page 13 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Comprehensive OEM Engineering Support

main locations Engineering Support

Analysis Evaluation

Product
Fleet
Change
Data
Base Manage
Analysis -ment
Checklists
© Siemens AG 2010. All rights reserved.
Page 14 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
The Product Development Process (PDP) @ Siemens

Customer Feedback Gate 1 Gate 2 Gate 3 Gate 4 Gate 5

Design Validation
Market Demand Product Planning
Planning
P roduct P rod.&Dev elop.
Design
Prep. Implementation
Conceptual Basic
Preparation
Commerciali-
Desi gn Implementation
Final Design, Manufacturing Installation, Product
Validation
Perfor mance
Str ategy P lanning Design Design zation P lanning P rocurem ent & As sembly Trial Operation Monitoring Validation

M00 M10 M20 M30 M40 M50 M60 M70 M80 M90 M100
time
Fleet Experience
R0 R1 R2 R3 R4 R5 R6 R7 R8 R9 R10

Single Events Minimizing risks by conducting mandatory reviews in interdisciplinary teams (e.g.
marketing, engineering, manufacturing, service …)
Reported From Sites

Engineered Solution:
Specific Solution, Fleet Solution, M&U-Product

© Siemens AG 2010. All rights re served.


Page 15 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Customer Survey - Customer Feedback

Asses Voice User Group


Analysis Improvement
of Customers Meeting
Customer Feedback
• Anonym ous • Descriptive and • Internal feedback to respons ible process owners • Presentation
web survey explorative • Initiation of improvement processes of results and
• Conducted statistics • Information of sales and feedback to customers improvem ent
by third party • Content analysis to support interaction activities

1 Month
Invitation
email 2 Month
Survey
completion 2 Month
Results User Group
Meeting
4 Month
Customer 1 Month
Feedback

UGM Documentation
(Mailing & CEP)
10 Month
© Siemens AG 2010. All rights re served.
Page 16 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-4000F / V94.3A
Example: Starting Reliability Package
Customer Feedback

Drivers for Development

SGT5-4000F

1 2 3

1 2 3

1 Analysis of over 93 units


2 Improve most frequently sources of error
3 Started implementation
© Siemens AG 2010. All rights re served.
Page 17 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-4000F / V94.3A
Starting Reliability Package
Customer Feedback

Generic Hardware Scope

 New igniter design


 Exchange of ignition cable holder
 New ignition logic with constant ignition
speed
 Online ignition monitoring
 Drying procedure after compressor
offline washing
 Automatic drainage system
 Blow-off valves with larger actuator
 Modified flame monitoring system

 Installation during major outage


recommended

© Siemens AG 2010. All rights re served.


Page 18 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-4000F: Improvement in Starting Reliability
Starting Reliability Package
Customer Feedback
Change of starting reliability after implementation of measures

Site A Outage in September 2008


Starting reliability before outage => 44%
Starting reliability after outage => 100%
(1 Start abbort due to tuning activities excluded)

Site B Outage in January 2009


Starting- reliability before outage => 33%
Starting reliability after outage => 100%

 Effectiveness of Starting Reliability Package validated.

Ready for Fleet Wide Implementation

© Siemens AG 2010. All rights re served.


Page 19 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
The Product Development Process (PDP) @ Siemens

Customer Feedback Gate 1 Gate 2 Gate 3 Gate 4 Gate 5

Market Demand Product Planning


P roduct P rod.&Dev elop.
Design
Conceptual Basic
Preparation
Commerciali-
Desi gn Implementation
Final Design, Manufacturing Installation, Product
Validation
Perfor mance
Str ategy P lanning Design Design zation P lanning P rocurem ent & As sembly Trial Operation Monitoring Validation

M00 M10 M20 M30 M40 M50 M60 M70 M80 M90 M100

Fleet Experience
R0 R1 R2 R3 R4 R5 R6 R7 R8 R9 R10

Single Events Minimizing risks by conducting mandatory reviews in interdisciplinary teams (e.g.
marketing, engineering, manufacturing, service …)
Reported From Sites

Engineered Solution:
Specific Solution, Fleet Solution, M&U-Product

© Siemens AG 2010. All rights re served.


Page 20 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Compressor
Compressor Types

SGT5-4000F 15 stage

• 15-stage compressor with


transonic front stages
• Pressure Ratio: ~17-18
Fleet Experience

• 17-stage compressor with


supercritical blades in stages
1 and 2
• Pressure Ratio: ~16

V94.3A 17 stage
© Siemens AG 2010. All rights re served.
Page 21 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Compressor Stator Rings
Design Concept Fleet Experience

Outer
Ring

Compressor
Ring Segment Vane
Compressor
vanes
• 1 Outer Ring
• Vanes Inner
Ring II
• 2 Inner Rings
Inner Ring
I

Inner Ring
II weld
Inner
Ring I

© Siemens AG 2010. All rights re served.


Page 22 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Compressor Stator Rings
Vane Hook Crack Findings Fleet Experience
Possible Issue:
 Single vane hook cracking at some front stages.
 In very rare cases airfoil breakouts with downstream
compressor findings.
(Repair measures performed during regular outages
using boroscopic compressor inspection as mitigation
measures.)
Root Cause:
 Increased local surface stresses in the
hook due to constrained deflection with
contributing factors as surface finish /
undefined contact surfaces. 3D Model
 In single stages superposition with
dynamic loading.
Suction Side
© Siemens AG 2010. All rights re served.
Page 23 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Compressor Stator Rings
Vane Hook Improvements Fleet Experience

Solution

1. Smooth transition
hook / airfoil

2. Plain (parallel)
hook surfaces

3. Increased hook
width

Old design New design


© Siemens AG 2010. All rights re served.
Page 24 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Compressor
V94.3A / 17 stage Additional Enhancement
for Stage 2 & 4 Fleet Experience

Frequency Tests (Modal Analysis) at Berlin Factory performed for new design.

Sche matic Vie w of Modal Analysis

Stage 4 with new design

Verification of FEA analysis with regard to frequency margin by


modal analysis (natural frequency measurement).
© Siemens AG 2010. All rights re served.
Page 25 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
The Product Development Process (PDP) @ Siemens

Customer Feedback Gate 1 Gate 2 Gate 3 Gate 4 Gate 5

Market Demand Product Planning


P roduct P rod.&Dev elop.
Design
Conceptual Basic
Preparation
Commerciali-
Desi gn Implementation
Final Design, Manufacturing Installation, Product
Validation
Perfor mance
Str ategy P lanning Design Design zation P lanning P rocurem ent & As sembly Trial Operation Monitoring Validation

M00 M10 M20 M30 M40 M50 M60 M70 M80 M90 M100

Fleet Experience
R0 R1 R2 R3 R4 R5 R6 R7 R8 R9 R10

Single Events Minimizing risks by conducting mandatory reviews in interdisciplinary teams (e.g.
marketing, engineering, manufacturing, service …)
Reported From Sites

Engineered Solution:
Specific Solution, Fleet Solution, M&U-Product

© Siemens AG 2010. All rights re served.


Page 26 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Market Demand: More Operational Flexibility

Increase of green energy production requires

Market Demand

2000: 18 GW 2010: 160 GW 2020: … GW

Operational Flexibility
Source: Global Wind Energy Council, 2010

Improved
Start-up Curve Current
Smart Grids ST+GT
Start-up

Plant Load
loading
Curve
GT+ST
Improvement
parallel
Start-up

GT Hold-time

GT Start-up
Time
© Siemens AG 2010. All rights re served.
Page 27 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
More Operational Flexibility - Example
Wet Compression - How it Works Market Demand
Air Intake

Comb.
Compressor Turbine
Chamber

Cooling Air

Evap. Inter Steam power


cooling cooling effect augmentation
effect effect

Efficiency improvement
© Siemens AG 2010. All rights reserved.
Page 28 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Siemens Gas Turbine Modernization
Wet Compression Market Demand

Main Facts

 Controlled water injection in front of


the compressor
 Optimized positioning of spray rack and
droplet distribution in the inlet duct
 Optimized droplet size for best
vaporization effect
 Minim ized erosion and corrosion
 OEM* experience to handle large quantities of
demineralized injected water
 GT-Customized: axial thrust compensation, Spider Nozzle
surge protection and controlled combustion
dynam ics
* OEM … Original Equipment Manufacturerx

© Siemens AG 2010. All rights reserved.


Page 29 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Siemens Gas Turbine Modernization
Wet Compression Market Demand

Benefit
Power output improvement*

- up to 30 M W on gas turbine SGT5-4000F


- up to 18 M W on gas turbine SGT5-2000E
** Subject to specific technical plant evaluation,
expected values with test tolerance @ ISO
conditions.

References
More than 40 Wet Compression syste ms**
installed on the frame types SGT5-2000E,
SGT6-2000E, SGT6-3000E and W501FC+.

First Wet Compression systems sucessfully


implemented on the fram e type SGT5-4000F.
** As of May 2010

© Siemens AG 2010. All rights reserved.


Page 30 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-4000F / V94.3A Gas Turbine
Market Driver and Benefits

o … neutral
Market Driver Power Efficiency Emission Reliability & Operational Maintenance
Product Increase Increase Reduction Availability Flexibility Cost Reduction
ACC
(Advanced Compressor Coating)
+ + o + o o
ACCSpro (Siemens‘ Advanced

Legend: + … positive
Compressor Cleaning System – + + o + o o
pro)
CMF+
(Compressor Mass Flow ++ o o o o o
Increase)

EVAP Cooler ++ o o o + o
FODS (Foreign Object Detection
System) o o o ++ o o
Fuel Conversion
(according to SIGAMA) o o o o + o
HCO (Hydraulic Clearance
Optimization) + + o o o o

LTE (Lifetime Extension) o o o + o +

TD (Turndown) o + o o ++ o

WetC (Wet Compression) +++ o o o +++ o


© Siemens AG 2010. All rights reserved.
Page 31 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-2000E / V94.2 Gas Turbine
Market Driver and Benefits (1)

Market Driver Power Efficiency Emission Reliability & Operational Maintenance


Product Increase Increase Reduction Availability Flexibility Cost Reduction

33MAC o o o ++ + ++

41MAC o o o ++ + ++
ACC
(Advanced Compressor + + o + o o
Coating)
CMF+
(Compressor Mass ++ o o o o o
Flow Increase)

EVAP Cooler ++ o o o + o
FTI
(Firing Temperature ++ + o o o +
Increase)

Fuel Conversion o o o o + o

HR3-Burner o o ++ + o o
Legend: + … positive
o … neutral

© Siemens AG 2010. All rights reserved.


Page 32 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
SGT5-2000E / V94.2 Gas Turbine
Market Driver and Benefits (2)

Market Driver Power Efficiency Emission Reliability & Operational Maintenance


Product Increase Increase Reduction Availability Flexibility Cost Reduction

IGV Modification o o o + o o
LTE
(Lifetime Extension)
o o o + o +
OTC Control
Optimization
o o o o + +

Si3D Stages 1+2 ++ +++ o o + +

Si3D Stages 3+4 ++ ++ o o + +


WetC
(Wet Compression) +++ o o o +++ o

Legend: + … positive
o … neutral

© Siemens AG 2010. All rights reserved.


Page 33 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Agenda

1. Frame Portfolio
2. Maintenance Concepts - Update
3. Engineering, R&D and Modernization
4. Life Time Extension

© Siemens AG 2010. All rights reserved.


LTE - additional machine life time

The life of a component is limited!

therefore it is not a question if it fails, but when it fails.

therefore LTE helps to prevent catastrophic failures.

LTE stands for high availability, reliability and


therefore
safety.

LTE can enable the extended life of a

AL:N ECCN: N
component at optimum performance levels

© Siemens AG 2010. All rights reserved.


Page 35 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Lifetime Extension

with out
Average overall component risk prior to Lifetime Extension
Average overall component risk with Lifetime Extension End of Design Life
100,000 EOH /
Average overall component risk without Lifetime Extension
3,000 starts
LTE
Potential for increased
Major Inspection * risk of operation
beyond 100,000 EOH /
3,000 starts without
Risk

Lifetime Extension

Lifetime Extension program designed


to help reduce risk of operation
Minor Inspection
* Major Inspections might be executed as a
Equivalent Operating Hours / Starts Hot Gas Inspections, depending on site
specific s or findings

© Siemens AG 2010. All rights reserved.


Page 36 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Aging Factors - Aging Effects:
Some common aging mechanisms evaluated at the 100,000 EOH inspection

Compressor Compr. stator II, Burner complete: Combustion Chamber Disk spring stack,
blades & vanes: Diffusor, Radiation •Creep Outer shell Screws, Tile holder:
•Creep liner: •Wet Corrosion •Oxidation, Corrosion •Creep
•Wet corrosion •Creep •Low cycle fatigue •Creeping, Material removal •(Low cycle fatigue)
•Low cycle fatigue •Low cycle fatigue •High cycle fatigue •Low cycle fatigue
•High cycle fatigue •Material removal •High cycle fatigue Housing: • Creep
•Low cycle fatigue

Tie rod nut, cooling air, Tie Rod, middle hollow shaft, Turbine stator: Turbine B&V:
front/rear hollow shaft, Compr./Turbine disks: •Creep •Oxidation, Corrosion
intermediate shaft: •Creep •Low cycle fatigue •Creeping, Material removal
•Low cycle fatigue •Low cycle fatigue
•Creep
•Low cycle fatigue •High cycle fatigue •High cycle fatigue

© Siemens AG 2010. All rights reserved.


Page 37 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Siemens Experience with Life Time Extension (LTE) across fleets

Siemens SGT5-4000F / SGT5-2000E Operating Regime

SGT5-40 00F
3500 SGT5-20 00E
LTE

3000

2500
Number Of Starts

2000

1500

1000

500

0
-10.000 10.000 30.000 50.000 70.000 90.000 110.000 130.000 150.000

Equivalent Ope rating Hours

© Siemens AG 2010. All rights reserved.


Page 38 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
The challenge about comprehensive LTE
Planning – technical aspects

-36 -24 -12 0 12 24


(months before LTE) LTE (months after LTE)

66 74 82 90 100 108 Compressor


116 124
side 133

MO HGPI
MO
1.LTE
LTE Pre-review Replace ment of
• Evaluation Questionnaire limited Components
• Final Outage meeting
• Operation history analyzing MO + LTE
• LTE recomme ndation by unit
• Destructive Inspections

AL:N ECCN: N
specific investigation
• NDT Inspections
• Repairs
• Replace ments
• Evaluation
© Siemens AG 2010. All rights reserved.
Page 39 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
LTE Experience
Example: Rotor of mature frames

Rotor

© Siemens AG 2010. All rights reserved.


Page 40 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Volumetric Re-qualification of Rotor

UT Indication

Ultra Sonic (UT) Inspection of Forged Rotor Components

Highly sensitive Ultrasonic Test inspection method for rotor components


developed and qualified to detect critical internal flaws
Volumetric re-qualification of rotor components in critical areas
© Siemens AG 2010. All rights reserved.
Page 41 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
LTE Experience
Example: Rotor of mature frames

Results of LTE - NDE Disc Inspection

Inspected GTs
without
indications
79%

Inspected GTs
with indications
21%

Indications = cracks, forging defects, etc. that required further evaluation

© Siemens AG 2010. All rights reserved.


Page 42 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
LTE summary
Status:
 LTE program derived from R&D program over last
decade and unit experience;
 Experience of +60 LTE`s across frames is adding to
knowledge base & engineering evaluation;
 base LTE experience with mature frames since 2003,
with advanced (A-)frames since 2009;
 Findings confirm evaluation for testing and replacement
of components, especially with units operating under
more severe conditions (fuel, ambient conditions etc.)
Outlook:
 Constant update of component LTE
LTE by SIEMENS will optimize the service life,
reliability and availability of components!

© Siemens AG 2010. All rights reserved.


Page 43 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Summary

Siemens Energy provides you the


power to improve the performance of
your gas turbine and your
competitiveness!
 Full range of options
o Power and efficiency increase
o Operational flexibility
o Maintenance cost reduction
o Emission reduction
o Reliability & availability increase
 Gas turbine performance enhancements for
all benefits available.
 Product validation and operational
experience help ensure high reliability.

© Siemens AG 2010. All rights reserved.


Page 44 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Thank You
for Your Attention!
© Siemens AG 2010. All rights reserved.
Page 45 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N
Disclaimer

This docum ent contains forward-looking statements and information – that is, statements related to
future, not past, events. These statements may be identified either orally or in writing by words as
“expects”, “anticipates”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “will” or words of similar
meaning. Such statements are based on our current expectations and certain assumptions, and are,
therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond
Siemens’ control, affect its operations, performance, business strategy and results and could cause
the actual results, performance or achievements of Siemens worldwide to be materially different from
any future results, performance or ac hievements that m ay be expressed or implied by such forward-
looking statements. For us, particular uncertainties aris e, among others, from changes in general
economic and business conditions, changes in currenc y exchange rates and interest rates,
introduction of c ompeting products or technologies by other companies, lac k of acceptance of new
products or services by custom ers targeted by Siemens worldwide, changes in business strategy and
various other factors. More detailed information about certain of these factors is contained in
Siemens’ filings with the SEC, which are available on the Siemens website, www.siemens.com and
on the SEC’s website, www.sec.gov. Should one or more of these risks or uncertainties m aterialize,
or should underlying assumptions prove incorrect, actual results may vary materially from those
described in the relevant forward-looking statement as anticipated, believed, estimated, expected,
intended, planned or projected. Siem ens does not intend or assume any obligation to update or revise
these forward-looking statements in light of developments which differ from those anticipated.

Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or their
respective owners.

© Siemens AG 2010. All rights reserved.


Page 46 July 2010 Energy - Día de la Innovación Neukrantz AL =N ECCN =N