RAB VS RAP

PEKERJAAN PERBAIKAN WEAKSPOT JALAN AKSES BANDARA


FASILITAS : AIRPORT LANDSIDE FACILITIES

HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


NO. URAIAN VOLUME
RAB RAP RAB RAP

1 Pek. Bongkar Aspal 27.36 m3 Rp 23,997 Rp 22,557 Rp 656,562.68 Rp 617,168.92


2 Pek. Coating Aspal 456.00 m2 Rp 17,396 Rp 15,000 Rp 7,932,678.67 Rp 6,840,000.00
3 Pek. Lapis Aspal Beton (AC-WC) 64.30 ton Rp 1,770,010 Rp 1,500,000 Rp 113,804,534.03 Rp 96,444,000.00
4 Pek. Buangan bongkaran 27.36 m3 Rp 47,662 Rp 44,802 Rp 1,304,037.56 Rp 1,225,795.31

TOTAL Rp 123,697,812.94 Rp 105,126,964.23


KEUNTUNGAN JASA 10% Rp 12,369,781.29 Rp -
JUMLAH + KEUNTUNGAN JASA 10% Rp 136,067,594.23 Rp 105,126,964.23
DIBULATKAN Rp 136,067,000.00 Rp 105,126,000.00
PPN 11% Rp 14,967,370.00 Rp 11,563,860.00
JUMLAH TOTAL Rp 151,034,370.00 Rp 116,689,860.00

Jakarta, Juli 2023 Diperiksa Oleh


Disetujui Oleh
Dibuat Oleh PT. Angkasa Pura Properti
PT. Angkasa Pura Properti

SEPNA MUHARDYANTO ARIEF BUDIMAN


RENNY SOVIAHANI
Area Manager Vice President Construction
Direktur Operasi