Valenzuela City Technological College

Kamagong St., Fortune VI, Parada, Valenzuela City

Form 6: Session Plan


Sector : Construction Sector (Civil Works)
Qualification Title : Carpentry NC II
Unit of Competency : Fabricate, Install and Remove Wooden Formworks
Module Title : Fabricating, Installing and Removing Wooden Formworks

Learning Outcomes:
LO1. Prepare Materials, Tools and Equipment
LO2. Lay-Out and Cut Dimension of Form Sheating and Stiffeners
LO3. Assemble and Erect Form Panels and Components
LO4. Erect Wooden Scaffolds
LO5. Strip Form Panels and Dismantle Scaffold
LO6. Clean and Store Reusable Form Panels and Components
A. Introduction:
This unit covers the knowledge, skills, and attitudes to fabricate, install and remove wooden formworks.
B. Learning Activities
LO1. Prepare Materials, Tools and Equipment
Assessment Criteria
1.1 Personal protective equipment (PPE) is used in accordance with Rule 1080 of Occupational Safety and Health
Standards.
1.2 List of materials, hand tools and equipment are secured and followed according to job requirements
1.3 Materials, tools and equipment are selected, inspected and prepared consistent with job requirements.
1.4 Work area is cleaned according to safety and environmental regulations (e.g. PD 1152 Section 6, 8 & 42).
1.5 Required output is completed as specified by the immediate supervisor based on work schedule.
Learning Content Methods Presentation Practice Feedback Resources Time
1. Personal Protective Self-Study Read Information Answer Sheet Compare the Information Sheet 1hr
Equipment(PPE) and Sheet. 2.1-1 on 2.1-1 Answer to the No. 2.1-1 of
Safety and Health form design Answer Key CBLM
Standards(OHS). 2.1-1
Valenzuela City Technological College
Kamagong St., Fortune VI, Parada, Valenzuela City

LO2. Lay-Out and Cut Dimension of Form Sheating and Stiffeners


Assessment Criteria
2.1 Personal protective equipment (PPE) is used in accordance with Rule 1080 of Occupational Safety and Health Standards.
2.2 Form sheating and stiffeners are measured and marked according to job specifications.
2.3 Form sheating and stiffeners are laid out and cut according to required dimensions.
2.4 Work area is cleaned according to safety and environmental regulations.
2.5 Required output is completed as specified by the immediate supervisor based on work schedule.
1. Fabrication of Self-Study Read Information Answer Sheet Compare the Information Sheet 1hr
Formwork Panels Sheet. 2.1-2 on 2.1-2 Answer to the No. 2.1-2 of
how to fabricate Answer Key CBLM
formwork panels 2.1-2
Video View the video Answer the Oral Answer the Projector, Laptop, 1hr
Presentation presentation on Questioning Oral Speaker
how to fabricate Questioning
formwork panels Correctly
Demonstration Observe the Perform the Job Compare the Lumber, Plywood, 3hr
trainee’s Sheet 2.1-2 Job Sheet 2.1- Nails, G.I. Wire,
demonstration on 2 to the Chalk line, Pencil,
how to fabricate Performance Claw Hammer,
formwork panels Criteria Sledge Hammer,
Checklist Level Hose/Level
Bar, Steel Tape,
Nylon String,
Plumb Bob, Steal
Square,
Carpenters
Square, Lifting
Equipment, Crow
Bar, Rip Saw,
Valenzuela City Technological College
Kamagong St., Fortune VI, Parada, Valenzuela City

Adjustable
Wrench, P.P.E.
LO3. Assemble and Erect Form Panels and Components
Assessment Criteria
3.1 Personal protective equipment (PPE) is used in accordance with Rule 1080 of Occupational Safety and Health Standards.
3.2 Sheating are positioned and fixed to stiffeners.
3.3 Assembled form panels are checked for squareness, levelness, plumbness and alignment.
3.4 Primary and secondary supports are positioned and fixed to hold assembled form panels as per drawings.
3.5 Assembled form panels are checked for compliance with job requirements.
3.6 Work area is cleaned according to safety and environmental regulations.
3.7 Required output is completed as specified by the immediate supervisor based on work schedule.
1. Assembling Form Self-Study Read Information Answer Sheet Compare the Information Sheet 1hr
Panels and Stiffeners Sheet. 2.1-3 on 2.1-3 Answer to the No. 2.1-3 of
how to assemble Answer Key CBLM
form panels and 2.1-3
stiffener
Video View the video Answer the Oral Answer the Projector, Laptop, 1hr
Presentation presentation on Questioning Oral Speaker
how to assemble Questioning
form panels and Correctly
stiffener
Demonstration Observe the Perform the Job Compare the Lumber, Plywood, 3hr
trainee’s Sheet 2.1-3 Job Sheet 2.1- Nails, G.I. Wire,
demonstration on 3 to the Chalk line, Pencil,
how to assemble Performance Claw Hammer,
form panels and Criteria Sledge Hammer,
stiffener Checklist Level Hose/Level
Bar, Steel Tape,
Nylon String,
Valenzuela City Technological College
Kamagong St., Fortune VI, Parada, Valenzuela City

Plumb Bob, Steal


Square,
Carpenters
Square, Lifting
Equipment, Crow
Bar, Rip Saw,
Adjustable
Wrench, P.P.E.
LO4. Erect Wooden Scaffolds
Assessment Criteria
4.1 Personal protective equipment (PPE) is used in accordance with Rule 1080 of Occupational Safety and Health Standards.
4.2 Soleplates/ timber planks are prepared, placed and spaced accordingly considering ground surface conditions based on design
requirements.
4.3 Wooden scaffold components are erected, plumbed and leveled based on design requirements.
4.4 Wooden scaffolds systems are checked based on design requirements.
4.5 Lifeline for fall protection devices (harness) are installed in accordance with job specification and OSHS requirements.
4.6 Work area is cleanedaccording to safety and environmental regulations.
1. Procedures to Erect Self-Study Read Information Answer Sheet Compare the Information Sheet 1hr
Scaffold Sheet. 2.1-4 on 2.1-4 Answer to the No. 2.1-4 of
how to erect Answer Key CBLM
scaffold 2.1-4
Video View the video Answer the Oral Answer the Projector, Laptop, 1hr
Presentation presentation on Questioning Oral Speaker
how to erect Questioning
scaffold Correctly
Demonstration Observe the Perform the Job Compare the Lumber, Plywood, 3hr
trainee’s Sheet 2.1-4 Job Sheet 2.1- Nails, G.I. Wire,
demonstration on 4 to the Chalk line, Pencil,
how to erect Performance Claw Hammer,
Valenzuela City Technological College
Kamagong St., Fortune VI, Parada, Valenzuela City

scaffold Criteria Sledge Hammer,


Checklist Level Hose/Level
Bar, Steel Tape,
Nylon String,
Plumb Bob, Steal
Square,
Carpenters
Square, Lifting
Equipment, Crow
Bar, Rip Saw,
Adjustable
Wrench, P.P.E.
LO5. Strip Form Panels and Dismantle Scaffold
Assessment Criteria
5.1 Personal protective equipment (PPE) is used in accordance with Rule 1080 of Occupational Safety and Health
Standards.
5.2 Tools, equipment and staging area are prepared.
5.3 Bracing, supports and form panels are removed as scheduled accordingly.
5.4 Shores and scaffolds are removed according to schedule.
5.5 Panels and other components are sorted, clean and stored for the next reuse.
5.6 Work area is cleanedaccording to safety and environmental regulations (e.g. PD 1152 Section 6, 8 & 42).
1. Removing Formworks Self-Study Read Information Answer Sheet Compare the Information Sheet 1hr
Sheet. 2.1-5 on 2.1-5 Answer to the No. 2.1-5 of
how to remove Answer Key CBLM
formworks 2.1-5
Video View the video Answer the Oral Answer the Projector, Laptop, 1hr
Presentation presentation on Questioning Oral Speaker
how to remove Questioning
formworks Correctly
Valenzuela City Technological College
Kamagong St., Fortune VI, Parada, Valenzuela City

Demonstration Observe the Perform the Job Compare the Lumber, Plywood, 3hr
trainee’s Sheet 2.1-5 Job Sheet 2.1- Nails, G.I. Wire,
demonstration on 5 to the Chalk line, Pencil,
how to remove Performance Claw Hammer,
formworks Criteria Sledge Hammer,
Checklist Level Hose/Level
Bar, Steel Tape,
Nylon String,
Plumb Bob, Steal
Square,
Carpenters
Square, Lifting
Equipment, Crow
Bar, Rip Saw,
Adjustable
Wrench, P.P.E.
2. How to Dismantle Self-Study Read Information Answer Sheet Compare the Information Sheet 1hr
Scaffold Sheet. 2.1-5 on 2.1-5 Answer to the No. 2.1-5 of
how to dismantle Answer Key CBLM
scaffold 2.1-5
Video View the video Answer the Oral Answer the Projector, Laptop, 1hr
Presentation presentation on Questioning Oral Speaker
how to dismantle Questioning
scaffold Correctly
Demonstration Observe the Perform the Job Compare the Lumber, Plywood, 3hr
trainee’s Sheet 2.1-5 Job Sheet 2.1- Nails, G.I. Wire,
demonstration on 5 to the Chalk line, Pencil,
how to dismantle Performance Claw Hammer,
scaffold Criteria Sledge Hammer,
Valenzuela City Technological College
Kamagong St., Fortune VI, Parada, Valenzuela City

Checklist Level Hose/Level


Bar, Steel Tape,
Nylon String,
Plumb Bob, Steal
Square,
Carpenters
Square, Lifting
Equipment, Crow
Bar, Rip Saw,
Adjustable
Wrench, P.P.E.
LO6. Clean and Store Reusable Form Panels and Components
Assessment Criteria
6.1 Personal protective equipment (PPE) is used in accordance with Rule 1080 of Occupational Safety and Health Standards.
6.2 Materials such as scaffolding and formworks are recovered and stockpiled according to company rules and procedures.
6.3 Work area is cleanedaccording to safety and environmental regulations (e.g. PD 1152 Section 6, 8 & 42).
6.4 Tools, equipment and other materials are cleaned after use.
6.5 Required output is completed as specified by the immediate supervisor based on work schedule.
Self-Study Read Information Answer Sheet Compare the Information Sheet 1hr
Sheet. 2.1-6 on 2.1-6 Answer to the No. 2.1-6 of
1. Maintain and Store how to maintain Answer Key CBLM
Formworks Component and store 2.1-6
formworks
component
C. Assessment Plan
Demonstration/Observation with Oral Questioning.
D. Learning Facilitator’s Self-Reflection of the Session
The learners were active and very cooperative during activities. The delivery of the contents went well and was accomplished on time
according to the planned session. Based on the result of the assessment of the learners, they can now:
Valenzuela City Technological College
Kamagong St., Fortune VI, Parada, Valenzuela City

 Prepare materials, tools and equipment


 Lay-out and cut dimension of form sheating and stiffeners
 Assemble and erect form panels and components
 Erect wooden scaffolds
 Strip form panels and dismantle scaffold
 Clean and store reusable form panels and components