As Built Pro
As Built Pro
TECHNICAL DOCUMENTS
Project Name: Package 3 - Upper Plateau Primary Road -
Project Code: QI09043311
TBN-17 & TNS-05
Location: 00 Date: February 04, 2024
Document Description: This is a As-Built Drawing Submission Procedure. It is intended for use by the
construction team of Haif-FSA JV executing the project titled Upper Plateau Roads – TBN-17 & TNS-05. It shall
only be put in use after approval from Employer’s Representative.
Enclosure:
Submitted By: Received By:
Name: Mohammed Jishad Name:
Signature: Signature:
Date: February 04, 2024 Date:
Below portion for Consultant Supervision use only
Status: A- Approved B- Approved as noted C- Revise & Resubmit R- For information only
Comments:
TECHNICAL DOCUMENTS
Project Name: Package 3 - Upper Plateau Primary Road -
Project Code: QI09043311
TBN-17 & TNS-05
Location: 00 Date: January 10, 2024
Document Description: This is a As-Built Drawing Submission Procedure. It is intended for use by the
construction team of Haif-FSA JV executing the project titled Upper Plateau Roads – TBN-17 & TNS-05. It shall
only be put in use after approval from Employer’s Representative.
Enclosure:
Submitted By: Received By:
Name: Mohammed Jishad Name:
Signature: Signature:
Date: January 10, 2024 Date:
Below portion for Consultant Supervision use only
Status: A- Approved B- Approved as noted C- Revise & Resubmit R- For information only
Comments:
AS-BUILT DRAWING
SUBMISSION PROCEDURE
Qiddiya - QPMO-410-CT-00618 -
Upper Plateau Roads - TBN-17 &
TNS-05
Rev. 01
Mohammed Jishad
03-Feb-24
Qiddiya - QPMO-410-CT-00618 - Upper
Plateau Roads - TBN-17 & TNS-05
DOCUMENT HISTORY
REV.# Change Date Description of Change Location/ Section of Change
00 Jan 04, 2024 - -
BIM submission included. Section 4.3 and 4.4
01 Feb 03, 2024
As-built stamp included Section 4.3
DOCUMENT CONTROL
Mohammed Jishad
Drafted By: Date: 01/02/2024
Quality Manager
Ali Mustafa, Khamis Yousuf
Reviewed By: Date: 03/02/2024
Project Manager
Contents
1. Purpose ................................................................................ 5
2. When to do ........................................................................... 5
3. Definition of As-built drawings .............................................. 5
4. As-Built Submission Process ............................................... 5
5. Appendices........................................................................... 7
5.1 As-Built Drawing Register .................................................. 7
5.2 As-Built Stamp ................................................................... 7
1. Purpose
The present procedure is to describe the way to establish the As-Built Drawings as records
of the constructed works for the, Package 3 - Upper Plateau Primary Road -TBN-17 & TNS-
05.
The As-Built Drawings are an essential part of the documentation to be handed over to the
Client and to the Operation & Maintenance entity. The aim of these drawings is mainly:
➢ To provide a fully detailed description of the project as it has been finally built.
➢ To be the base information for further modifications and/or extensions, and potentially
to provide information to entities that could plan/undertake construction activities
adjacent or nearby.
2. When to do
Basically, the As-Built Drawing procedure can start when works have been completed on a
given section in accordance with the construction drawings which shall be at least Code B
status.
5. Appendices
5.1 As-Built Drawing Register
5.2 As-Built Stamp
AS-BUILT DRAWINGS
Workflow
SN Drawing number As Built Drawing Title Rev Location Structure Date Submitted Status Date Received Shop Drawing number Remarks
number
TRANSPORTATION
Civil
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
1 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00001 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00265
Sheet 1
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
2 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00002 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00266
Sheet 2
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
3 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00003 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00267
Sheet 3
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
4 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00004 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00268
Sheet 4
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
5 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00005 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00269
Sheet 5
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
6 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00006 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00270
Sheet 6
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
7 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00007 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00271
Sheet 7
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
8 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00008 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00272
Sheet 8
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
9 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00009 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00273
Sheet 9
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
10 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00010 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00274
Sheet 10
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
11 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00011 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00275
Sheet 11
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
12 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00012 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00276
Sheet 12
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
13 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00013 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00277
Sheet 13
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
14 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00014 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00278
Sheet 14
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
15 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00015 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00279
Sheet 15
As Built for TNS-05 ST (0+025.00) to ST (0+570.00) Cross Sections and Quantities of Materials
16 QI09043311-HFC-DRW-ASB-CIV-02-RO2-00016 00 TNS-05 WF-063557 19/12/23 Pending QI09043311-HFC-DRW-SDW-CIV-00-Z00-00280
Sheet 16
Qiddiya - QPMO-410-CT-00618 - Upper
Plateau Roads - TBN-17 & TNS-05