Note On Material Management
Note On Material Management
(Extracted from: Hedley G. and Garrett C. (1983) Practical Site Management: 2nd Edition. Longman,
Essex page: 119 -138).
THE TENDER
Chapter 1 described how the tender was built up using the resource elements
of:
Labour
Plant
Materials
Sub-contractors
It is clear that, if you can identify the cost of materials contained in relevant
items of the Bill of Quantities, then you can evaluate the sums allowed in the
bill, and hence the tender, for each type of material required for the works.
1/8
The information available in a tender can be very comprehensive and it will
enable you to place materials orders in a manner which conforms to the price
and quantity allowance contained within the tender.
Estimators will have done their best to ensure that materials availability will
suit the programme. Any major anomaly will have been covered. In theory at
least the supply will fit the programme. Considering the construction
programme and the tender together yields information to make sure you:
Order the correct quantity
To the correct quality
At an acceptable price
And have it available at the required time.
Materials information from the tender is handed over to the buyer and the
construction team and the first action required is to prepare a materials
planning schedule. The schedule is a list of materials required and when they
are required, to meet the construction programme. A typical schedule may be
detailed as shown in Fig. 18.
2/8
MATERIALS REQUISITIONS
Requisitions are a development of the schedules. Whereas the schedules list all
materials the requisition is intended to cover single materials only. The
requisition will become the basis of the order to be placed.
The format of the requisition is generally similar to that of the schedule. It will,
however, include the specification and any other information necessary to tell
any supplier fully and exactly what is required.
Requisitions and schedules will be to your organization format. Figure 19
shows a typical example. Materials requisitions should be prepared as soon as
possible after the schedules are prepared. It is again much better to do them
pre-contract. This will help you to concentrate on other matters, and also let
the buyer assist you at the earliest possible time.
Major orders
The buyer should have full information from the tender of the materials pricing
and specification. If all the materials quotes are available, the buyer can start
the purchasing process as soon as requisitions are received from the site
manager. The buyer may decide to obtain further quotations or to try and get
lower prices. In the end orders are placed on a 'best value' basis for all
materials. Figure 20 shows a typical order form. Obviously your orders must be
for the correct quantity, quality, delivery and price.
Minor orders
Rarely can the buyer place all orders. Variations occur; some items are omitted
by error. Many orders, especially on building elements, are for small individual
items. It would be extremely expensive to order each one separately.
3/8
DELIVERY TO SITE
The supplier
Ticket number
Product description
Quantity delivered
Date of delivery
Materials arriving should be checked for quality and quantity. Any unsuitable
items should be returned to the supplier at once and a note made of such
events.
STORAGE ON SITE
4/8
All materials arriving on site should be checked to ensure they are acceptable
in terms of quality and that the quantity is correct. Materials should also be
checked out of the store when they are issued for use.
All checks should be confirmed in writing and signed by the persons issuing or
accepting the material.
MINIMIZING WASTE
The materials supply has to suit the programme and items need to be ordered,
sometimes in piecemeal fashion, to satisfy this need. All team members need to
be aware of the material delivery situation so that off-loading and storage can
be arranged. Clearly a site manager has to carry out a task which varies
according to the job and the organizational requirements being worked to.
Possible actions include the following.
5/8
You need to ensure that the materials you want are available and to confirm
this with the supplier. Suppliers can have difficulty in meeting fast rates of
delivery. Be prepared to use a back-up source if necessary. Quarried stone,
ready-mixed concrete and bricks are examples of this. You must ensure that
delivery rates are compatible with the programme requirement, otherwise you
will have delays and resources will stand idle awaiting deliveries.
Do not call materials up for delivery too early. They will clutter up the site.
Many items are available on 24 h delivery. Utilize this factor. Goods arriving on
site are accepted by signing a receipt for them. Signature implies acceptance
and probable payment to the supplier and it is therefore important that you
ensure that any goods you sign for are fully satisfactory.
A storeman can record materials onto site, then into the job. On jobs such as
roads or wherever high volumes of materials are used, this is essential.
Lead times for delivery of different materials vary. Ensure you know what they
are for the products which you are using. They also vary according to whether
the industry is in boom times or in recession. You need to be aware of any
changing factors. Keep stocks replenished as necessary.
6/8
Many contractors negotiate supplies on a national basis for items which they
use in bulk. Concrete or glazed stoneware pipes, reinforcement, concrete and
bricks are examples. You need to be aware of such agreements.
Protect materials in place from damage (doors, windows, quoins, etc.). Whilst
this may seem expensive, it is cheaper than buying new items. Ensure correct
handling arrangements are in place for all materials. Expensive materials, used
in small quantities, can be used very wastefully. An example would be an epoxy
resin or a special grout. Train your people to use the items correctly and supply
the material in small packs if possible.
I have seen this in practice where lintels have proved inadequate for their
loadings and stone sole plates supporting the ends of lintels have been too
small. This gave excessive bearing pressures on the supporting masonry.
Be aware that certain paints or plastics become stiff or brittle in cold weather
and cannot be used effectively. Everyone makes mistakes and none of us has
total knowledge. When a problem like this is encountered the sooner it is
sorted out the better.
7/8
Corrective work
Once defective materials are incorporated into the work, the cost of any
remedial action rises dramatically. As this cost is abortive, no one is
happy about paying for it. I have also found that the cost of remedial
action is generally higher than anticipated. It is essential that careful
records are kept of any remedial works required.
In addition to recording the rectification actions taken, record the chain
of events which led to the items being built in. People do forget detail and
you may well need the records later.
Let the supplier, who you hope is going to pay, see the corrective actions
as you take them.
In making your records, note any delays or costs which are occasioned
elsewhere as a result of the problem,
Finally, remember that the supplier will only wish to supply new items
and this will represent a minor part of the overall cost.
This generally means higher than expected wastage and tends to occur with
the use of domestic sub-contractors. I have experienced this particularly when
placing hardcore over site with failure to use a ground membrane—the sub-
contractors were simply pressing new supplies into the ground.
Personal relationships
We will deal with relationships in more depth later. When you do have meetings
with people, do it on the basis of developing a long term relationship. I always
went for goodwill and trust. It worked!