BMG Work Status

Chainage Length
Sl. No. Work Status Applicable TCS
From To (m)
1 0+000 2+070 2070 TCS IV
2 2+070 2+250 180 TCS II
3 2+250 2+750 500 TCS IV
4 2+750 3+640 890 TCS IV
No Work
5 3+640 4+000 360 TCS I
6 4+000 4+180 180 TCS IV
7 4+180 4+800 620 TCS I
8 4+800 5+180 380 TCS IV
9 5+700 6+200 500 TCS IV
10 6+200 6+800 600 No Work TCS I
11 6+800 8+456 1656 TCS V
12 8+456 10+700 2244 Forest Area TCS V
13 11+750 11+980 230 No Work TCS I
14 18+400 18+850 450 TCS IV
15 18+850 20+500 1650 No Work TCS II
16 20+500 21+000 500 TCS IV
17 21+440 21+740 300 Hindrance due to PHED Pipe line TCS IV
18 28+000 28+580 580 No Work TCS II
19 30+200 30+500 300 No Work TCS I
20 34+900 36+420 1520 No Work TCS IV
21 39+460 39+560 100 TCS IV
No Work
22 39+560 40+100 540 TCS II
23 40+100 41+000 900 NH-79 NH-79
24 41+000 41+600 600 TCS VII
25 41+600 41+900 300 No Work TCS I
26 41+900 42+100 200 TCS VII
27 47+560 47+860 300 No Work TCS VII
28 49+230 49+780 550 Toll Plaza & MNB TCS VIII
29 53+960 54+400 440 No Work TCS VIII
30 62+200 62+700 500 TCS I
No Work
31 62+700 63+220 520 TCS VIII
Total 20660
Status
Type of TCS Village Name Remarks
Re-Construction
Rigid Pavement Lasadiya
Re-Construction
Re-Construction
Rigid Pavement Andheri Deori
Re-Construction
Rigid Pavement Andheri Deori
Re-Construction
Re-Construction
Rigid Pavement Pakhariyawas
Overlay
Overlay
Rigid Pavement Khimpura
Re-Construction Masuda
Rigid Pavement Masuda
Re-Construction Masuda
Re-Construction
Rigid Pavement Begliyawas
Rigid Pavement Jhinpiya
Re-Construction
Re-Construction
Rigid Pavement Bandanwada
NH-79 Bandanwada
Re-Construction Bandanwada
Rigid Pavement Bandanwada
Re-Construction Bandanwada
Re-Construction Kitap
Widening + Strengthing
Widening + Strengthing Tantoti
Rigid Pavement Jawla
Widening + Strengthing Jawla