Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

Remedies in Contract o Case: Robinson v Harman, as per Baron Parke, “where a party

Remedy sustains loss by reason of breach of contract, he is so far as


Definition money can do it to be placed in the same situation with respect to
- A cure, a remedy is a redress for a wrong damages as if the contract had been performed.”
- Any positive solution to a problem - Damages in the most commonly claimed remedy granted by the court in
Historical development cases of breach of contract.
- Remedies are either legal or equitable - A claim for damages arises in circumstances where there has been a failure
- Legal remedies are primarily monetary and the most common in the remedy to perform without lawful excuse, one or more of the obligations (whether
of damages condition or warranties or intermediate terms) contained in the contract.
- Equitable remedies are usually specific and available only at the discretion - It gives the right to the innocent party to claim for a remedy for every breach,
of the court. whether the nature of the breach is serious or not.
Objectives - Object of awarding damages: to compensate the innocent party’s actual
- To provide an appropriate relief loss but is not to benefit the innocent party. Hence, the function of damages
- To redress a wrong rather than to punish a defendant (civil remedy) is compensatory in nature. Never punitive.
- In remedies of contract, there are needs: o Case: Tan Sri Khoo Teck Puat & Anor v Plenitude Holdings
o to have an ability to recognize which remedy is appropriate Sdn Bhd, the Federal Court held that the general principle which
o to have an ability to determine the likelihood of success constitutes the starting point in assessment of damages for the
o to have an ability to seek/choose between alternative remedies breach of contract is to place a party who has sustained a loss by
o to have an understanding on how to calculate damages reason of breach, so far as money can do it, in the same situation
Damages as if the contract has been performed.
Definition Type of Losses
- pecuniary compensation obtainable by success in an action for a wrong - A. Pecuniary losses: losses which can be quantified in financial terms such
which is either a tort or a contract, the compensation being in the form of a as loss of profit, loss of earnings, cost of repairs/replacement and expenses
lump sum which is awarded unconditionally and is generally but not incurred.
necessarily expressed in currency. - B. Non-Pecuniary losses: losses which are not economic or financial in
Damages in contract nature. Cannot be precisely stated in financial terms such as physical pain
- where a contract has been breached, damages are available as a matter and injury to feelings, mental distress and embarrassment.
of right Pecuniary losses
- Aims: to put the plaintiff as he would have been, if the contract is performed, Basic methods of calculating loss:
rather than to punish the defendant, ie to fulfill the plaintiff’s expectation by - i) Expectation or loss of bargain basis
putting him into as good as position as he would have been in if the contract o the income which the innocent party had expected to obtained out
had been performed. of the contract but was loss due to the breach of contract.
- Principle: to compensate the claimant for his losses, rather than to measure o Case: Robinson v Harman, “where a party sustains loss by
the award by the amount of gain derived by the defendant. reason of breach of contract, he is so far as money can do it to be
o Damages are supposed to place the innocent party in the same placed in the same situation with respect to damages as if the
position that he or she would have been had the contract been contract had been performed.”
properly performed. o Case: Victoria Laundry (Windsor) Ltd v Newsman Industries
o Case: British Westinghouse Electric and Manufacturing Co. Ltd, the boiler was delivered late and the direct and obvious result
Ltd v Underground Electric Rlys Co. of London Ltd, Viscount of that was the laundry could not use it to make a profit.
Haldane LC held, the fundamental basis of an award of o May also include any claim from the innocent party for cost of
contractual damages is thus compensation for pecuniary loss alternative performance when the defaulted party fails to perform
naturally flowing from the breach. and it is necessary to find someone else to do the job. The
differences cost accrued from the breach between what the
default party quoted and what the alternative person charges can • Case: Win Sin (M) Sdn Bhd v LPPKN, the
be claimed by the innocent party (Ruxley Electronics & court awarded damages for loss of profit. The
Constructions Ltd v Forsyth) plaintiff in this case suffered loss of profits due
o Assessed in 2 ways: to the failure of the defendant to deliver vacant
§ Diminution in value: differences in value between the possession of the shop that the plaintiff intends
performance received and what he expected from the to rent for the purpose of expanding her
promise in the contract. (Illustration (a) Section 74) business. The court pointed out that the
• Case: Hadley v Baxendale, Plaintiffs operated defendant knew that the plaintiff needed the
a mill, and a component of their steam engine premise for the purpose of their business. Thus,
broke causing them to shut down the mill. the defendant was liable to account for the loss
Plaintiffs then contracted with Defendants, of profits from the date of breach of agreement
common carriers, to take the component to W. until the date the plaintiff obtains another
Joyce & Co. to have a new part created. When premise to rent.
delivery was delayed due to Defendants’ • Case: Tanjung Tiara Sdn Bhd v Southwind
neglect, causing Plaintiffs’ mill to remain closed Development Sdn Bhd, the court in their view
longer than expected, Plaintiffs sued to recover that plaintiff claim for damages was supported
damages. Held: since defendant’s delay in by the estimated and consequential
transporting the shaft had caused the plaintiff computation of 25% of the contract value and
loss of profit, thus it can be taken into such computation was not merely based on an
consideration to assess the damage suffered estimate of the loss of profit but was supported
by the plaintiff loss of profit by way of diminution by evidence.
in value. o Case: Ban Chuan Trading Co Sdn Bhd v Ng Bak Guan, in
• Case: Heller Factoring Sdn Bhd (previously claiming for loss of profits, the respondent stated that he intended
known as Matang Factoring Sdn Bhd) v to use the said premise for his business of selling clothes where
Metalco Industries (M) Sdn Bhd, the court he expected his business profits to increase by 20% because of
held that the proper measure of damages to be the location which was more favourable than the shop he was
awarded to Metalco to its status before the occupying. But there was no evidence to support the claim. Mere
seizure of the machine by Matang; that is the assertion is not evidence and the production of the assessments
difference in the price at which the machine was alone should not be allowed.
bought by Metalco and the price at which it was - ii) Reliance/Wasted expenditure
later resold by Matang plus all the abortive o arises where the claimant has expended money which is then
expenditure which Metalco had incurred in wasted in preparation for or in partial performance of the contract.
transporting and installing the machine in its o A claim for loss of capital expenditure, expenses incurred in rely
premises. on the contract and performing obligations, these expenses are
§ Cost of cure (performance measure): by taking the cost now wasted due to the breach of contract.
of putting the plaintiff into the position which he would o For a claim on reliance interest/loss or wasted expenditure, the
have been in had the contract been fully performed. innocent party may recover expenditure incurred before or after
• Case: Jones v Herxheirmer, the damages the contract provided that the expenditure was reasonably
may be assessed on the basis of what it has contemplated (must not be too remote)
cost or will cost the claimant to have the o 2 situations in which a plaintiff may wish to claim on the
contract performed by a third party in order to reliance/wasted expenditure:
ensure that the contract is fully performed.
§ when the innocent party to a breach of contract has not § Facts: Plaintiff obtained a 6 months renewable licence to
suffered any loss of profits but has incurred expenditure occupy the defendant’s garage. It was expressly
in reliance of the contract provided in the contract that any equipment installed in
§ although the plaintiff may suffer loss of profit, he has the garage becomes the property of the garage owner,
difficulty in ascertaining and proving the amount of profit defendant, at the expiration of the 6 months period.
that he would have obtained if the contract had been Despite this clause, the plaintiff spent money on
performed. improving the garage. 10 weeks before the end of 6
o Case: Anglia Television Ltd v Reed, Lord Dening stated the months period, the defendant in breach of contract,
plaintiff claims the wasted expenditure, he is not limited to the ejected the plaintiff from the garage. The plaintiff brought
expenditure incurred after the contract was concluded. He can an action to recover the cost of improvements carried out
claim also the expenditure incurred before the contract, provided on the garage. The plaintiff failed in his action.
that it was such as would reasonably be in contemplation of the Plaintiff’s election to claim for expectation loss or reliance loss/wasted expenditure
parties as likely to be wasted if the contract was broken. - The court will have to decide whether or not to grant such damages.
o Case: Ismail v Haji Taib, the court held that the order of the - In principle, the innocent party has a free choice whether to claim on an
learned appellate judge would be set aside and the learned expectation or reliance basis. The two type of damages measures are
president's order restored except that it would be varied by different but related things. Reliance losses measure to positive losses to
ordering the defendant to pay $724 by way of special damages the innocent party but expectation losses measure prospective gains and
(not $1,224.00) and nothing by way of general damages; the profits.
relationship between the parties was governed by the ordinary law o Case: Cullinane v British ‘Rema’ Manufacturing Co Ltd
of contract and was not affected by the padi committee's order o Facts: plaintiff purchased a clay pulverizing machine from the
which it is true is permissive in nature. defendant, who warranted that the machine could process clay at
o Case: Ban Chuan Trading Co Sdn Bhd v Ng Bak Guan a rate of six tonnes per hour. However, the machine only process
o Facts: the parties entered into a three-year tenancy agreement in at 2 tonnes per hour. Plaintiff claimed from the defendant capital
which the appellant failed to deliver vacant possession as the expenses incurred in installing the plant and also for loss of profits.
previous tenant refused to vacate the premise. Despite having o Held: the court of appeal held that a plaintiff could not claim both
been informed, the respondent attempted to pay the monthly rents, his capital loss, expenditure incurred as well as his loss of gross
which the appellants refused to accept, and did not take any action profits. The plaintiff is required to choose between his two claims.
to repudiate the agreement. A year later, the respondent issued a o Case: Heller Factoring Sdn Bhd (previously known as Matang
notice to terminate the agreement and claimed from the appellant Factoring Sdn Bhd) v Metalco Industries (M) Sdn Bhd
loss of profits and money expended for the purchase of furniture o Facts: The appellants agreed to sell a machine built according to
and mannequins in preparation of continuing his business at the certain specifications to the respondents for RM65,000 subject to
new premise. the lessee’s right (Pembinaan Siap Sdn Bhd) to redeem it within
o Held: However, the Court of Appeal found that the respondent was 14 days. The respondents then obtained the machine and
only entitled to the money expended and not the loss of profits. installed it at its premises for which a concrete foundation had
o Exception to the General Rule of Reliance Interest: when reliance been built. However, the next month, the appellants came to the
loss cannot be claimed respondents’ premises and removed the machine as they had
§ The plaintiff cannot choose to recover wasted sold the machine to a third party for RM85,000. The respondents
expenditure to protect his reliance loss, or when he has contended that the appellants had breached the contract as the
made a bad bargain. machine was theirs subject to the lessee’s right to redeem it, which
§ Bad bargain is when the defendant can show that the the lessee did not exercise. The appellants contended that the
loss is one which the innocent party would have suffered purchase by the respondents was subject to no higher prices
even if the defendant had not breached the contract being offered. As the respondents refused to increase their price,
§ Case: C & P Haulage v Middleton the machine was sold to the third party. The respondents brought
a claim for RM20,000 being the loss of profit and an additional of £70,178. The contract expressly provided that the maximum
sum of RM30,000 as expenses incurred in installing the machine. depth of the pool should be 7 ft 6 in. After the work had been
o Held: The Court of Appeal in finding in favour of the respondents: completed, the defendant discovered that the maximum depth
The machine was not a standard item machine that was easily was only 6 ft 9 in. The plaintiffs claimed the balance of the price,
obtainable from the market, but was one that was built according and the defendant counterclaimed for breach of contract.
to particular specifications. o In regards to the defendant’s claim for loss of amenity, the court
o Case: CCC Films (London) Ltd v Impact Quadrant Films, held: The general rule is that in claims for breach of contract, the
decided that a plaintiff claiming for breach of contract had an aggrieved party cannot recover damages for his injured feelings,
unfettered choice whether to claim for loss of profits or wasted subject to the exception when the object of the contract is to afford
expenditure. pleasure. Where the contract was one “for the provision of a
o Case: Blue Sea Pools Swimming Centre (Klang) Sdn Bhd v pleasurable amenity”, the court found that the defendant’s
Loo Ah Chew & Sons Sdn Bhd, the court allowed the plaintiff’s pleasure was not so great as it would have been if the swimming
claim for wasted expenditure incurred in renovation works, but pool had been 7 ft 6 in deep, and thus, the defendant was awarded
excluded the claim for losses of profit as “the plaintiff is not entitled damages for loss of amenity.
to make a claim for both”. - 2) physical inconvenience and discomfort
- iii) Restitution o The common law permits the recovery of damages for pecuniary
Non-Pecuniary Losses loss and for physical discomfort and inconvenience but not for
Introduction injured feelings that may accompany a breach of contract.
- Lord Steyn in Farley v Skinner, “awards in this case should be restrained o Case: Hobbs and wife v The London and South Western
and modest. It is important that logical and beneficial developments in this Railway Company, the court awarded damages for the physical
corner of the law should not contribute to the creation of society bent on inconvenience suffered by the plaintiff and his family who were set
litigation.” down by the defendant railway company at the wrong station late
- The difficulties of verifying genuine claims have caused the courts not to at night. They had to walk five miles home in the drizzling rain, in
grant damages for non-pecuniary loss: the absence of available transport or accommodation. The court
o 1) because of the floodgates argument emphasized that the award is strictly confined to real, physical
o 2) the difficulty in assessing and accurately quantifying the inconvenience, and there can be no award of damages for mere
damages to be awarded. inconvenience, annoyance or loss of temper.
- But non-pecuniary losses may be recoverable when they are within the o Case: Farley v Skinner
contemplation of the parties. o Facts: the plaintiff employed the defendant, a land surveyor, to
Definition inspect a property in the countryside located 15 miles from an
- Damages that do not have a discernible, quantifiable monetary value. international airport seeking advice as to whether the property
Categories of Non-Pecuniary Losses would be seriously affected by aircraft noise. The defendant
- 1) pain, suffering, loss of amenities and expectation of life breached the contract when he reported that it was unlikely that
o often recoverable, ie purchaser of goods may be injured from the house would be greatly affected. The plaintiff bought the
using or consuming the said goods by reason of breach of property and incurred expenses in refurbishing it, but after moving
warranty. in, he was disturbed by the aircraft noise.
o Case: Summers v Salford Corp, the plaintiff who was a tenant o Held: Had the plaintiff known of the noise disruptions, he probably
was cleaning the window when it broke, causing injuries to her would not have bought the property. Where the surveyor’s
hand. She sued the landlord for breach of the covenant of fitness obligation to inspect whether the property was affected by the
for habitation and was successful in her claim. noise formed a vital part of the contract, this deprived the plaintiff
o Case: Ruxley Electronics and Construction Ltd v Forsyth from making an educated choice in the purchase of the property
o Facts: The defendant contracted with the plaintiffs to build a for which he was granted damages.
swimming pool in his garden and a building to enclose it for a price
o Case: Watss v Marrow, any distress, anxiety, displeasure, distress and disappointment for the defendant’s
tension and aggravation caused by the breach is irrecoverable. failure to prepare sufficient food for the plaintiff’s
o Case: Subramaniam Paramisavam & Ors v Malaysian Airlines wedding reception. As a result of the
System defendant’s breach, the plaintiff suffered much
o Facts: The plaintiffs’ baggage was re-weighted when they reached embarrassment before his guests at the
KLIA. It was found to be 60kg in excess of the permitted weight. reception.
They were asked to pay excess baggage charge at the airport.
They spent two hours in the airport due to this problem. They sued § ii) contract is entered into with the aim to prevent future
the defendant for damages for mental distress, agony, humiliation, distress
loss of reputation and injured feelings. • Case: Heywood v Wellers, where the contract
o Held: The court found that the damages sought, which were not was entered into to retain the defendant-
within the contemplation of the parties, were irrecoverable. solicitor to initiate legal proceedings against a
However, the court awarded damages of RM300 for discomfort man who had been molesting the plaintiff and
and inconvenience. to prevent any further distress, the breach by
- 3) injury to feelings/mental distress the defendant prolonged the plaintiff’s distress,
o generally, the courts are reluctant to grant non-pecuniary losses and she was thus, awarded damages for
for injured feelings. anxiety and mental distress.
§ Case: Addis v Gramophone Co Ltd, despite the § iii) where the plaintiff’s distress is a direct consequences
wrongful dismissal from the plaintiff’s position as the of physical loss cause by the breach of contract
defendant’s manager and the “harsh and humiliating” • Case: Perry v Sidney Phillips & Sons,
manner in which he was treated, there could be no award damages was granted where it can be foreseen
of damages for his injured feelings or for the loss that he that mental distress will result as a direct
may sustain from the dismissal making it more difficult consequence of physical inconvenience
for him to obtain employment. caused by the defendant’s breach.
o However, courts are not more willing and ready to allow such • Case: Bliss v South East Thames Regional
awards but only in very clear EXCEPTIONAL cases: Health Authority, the court reiterated the
§ i) contract is one to provide enjoyment general rule laid down by the House of Lords in
• Case: Jarvis v Swans Tours Ltd, the plaintiff Addis that where damages fall be assessed for
was compensated by damages for his breach of contract rather than in tort, it is not
disappointment, distress, annoyance and permissible to award general damages for
frustration at not getting as good of a holiday as frustration, mental distress, injured feelings or
had been promised. The plaintiff in his contract annoyance occasioned by the breach. The
with the defendants did not merely contract for court recognized that Jarvis and Heywood are
the travel facilities, board and lodging, but also exceptions to the general rule.
to enjoy himself. • Case: Hayes & Anor v James & Charles
• Case: Abdul Karim v T & R United (S’pore) Dodd (a firm)
Pte Ltd, the defendant did not meet up the • Facts: the plaintiffs bought a yard and a
contractual obligations in respect of a tour workshop on the faith of their defendant-
package offered to the plaintiff. The plaintiff was solicitor’s advice. The advice was found to be
granted damages for mental distress, subsequently untrue and the yard and
disappointment and discomfort. workshop served no purpose to the couple. The
• Case: James Yu v Raffles Hotel Ltd, the court plaintiffs brought an action against the
awarded the plaintiff damages for mental
defendant for breach of its contractual duty of • Case: Malik v Bank of Credit and Commerce
care. International SA (in liquidation), long serving
• Held: However, the court disallowed damages employees of the defendant bank were
for the plaintiffs’ anguish and vexation and dismissed upon its liquidation due to its corrupt
stressed that damages cannot be allowed for and dishonest manner of operation. The
anguish and vexation arising out of a breach of plaintiffs claimed damages, alleging that their
a purely commercial contract. inability to obtain alternative employment was
due to the shame attached to being former
§ iv) loss of reputation employees of the defendant bank. Held: The
• the courts in determining this form of non- plaintiffs’ contracts of employment contained an
pecuniary loss will regard it as the manner implied term imposing an obligation of mutual
society regards the innocent party, not to the trust and confidence between the parties. Thus,
innocent party’s injured feelings. the defendants were under an obligation to act
• According to Burrows in Remedies for Torts and honestly in its business dealings. Where the
Breach of Contract, has categorized 4 groups plaintiffs had suffered injury to reputation as a
of cases in which damages for loss of reputation result of the defendants’ breach of the implied
have been awarded: term, damages for loss of reputation was
o 1) the defendant’s breach comprises a recoverable.
refusal to allow an actor’s appearance • Case: CCA Holdings Ltd v Palm Resort Bhd,
or it is a breach to publish an author’s the plaintiffs were managers of the defendants’
book. club under a technical assistance and
o 2) the breach comprises the managerial agreement. The defendants
mismanagement of advertising where terminated the agreement on the ground that
a defendant fails to include an the club had not generated profits as required
advertisement in a newspaper, in the agreement. The plaintiffs alleged that as
thereby resulting in loss of business to a consequence of the termination, they suffered
the plaintiff. The loss of business can loss of reputation and goodwill which will impact
be viewed as analogous to an them as managers of prestigious clubs
instance where there has been a lost internationally. However, in considering
opportunity to enhance one’s whether the damages for loss of credibility and
reputation. reputation could be awarded, the court held that
o 3) a bank in breach of contract, the facts of the case did not fall within the
refuses to honour the plaintiff-trader’s exceptional situations where damages for loss
cheque or fails to supervise the of reputation may be granted.
plaintiff’s business as agreed so that Limitation to awards of damages
the plaintiff goes bankrupt - Compensatory damages are subject to limitation imposed by the rules
o 4) the defendant in breach of contract preventing claims for losses which are deemed to be too remote from the
supplies to the plaintiff goods which breach. This is considering the fact that the contract breaker cannot be
are not of quality sought by the pinned with liability for every single loss suffered by the innocent party.
plaintiff’s customers. Pecuniary - Courts have taken into consideration the limitations when rewarding
damages are recoverable for the loss awards of damages for breach of contract requirements of remoteness and
of goodwill. mitigation, since the contract breaker cannot be held liable for losses,
through flowing from his breach of contract, that are too remote.
- The function of remoteness principle: to control the extent of recovery of o The loss suffered by the plaintiff must be at the time of the contract
kinds and of quantum of loss. reasonably foreseeable as liable to result from the breach of
- The general common law formulation is in broad terms of “foreseeability” contract. In determining what was reasonable by the parties, the
or “contemplation of loss”. court must take into account the knowledge possessed by the
Rule in Hadley v Baxendale parties.
- Facts: Plaintiffs operated a mill, which they were forced to shut down when o Knowledge possessed is of two kinds:
the crank shaft of their steam engine broke. They contacted the § Imputed knowledge: Any reasonable individual can be
manufacturer of the engine, W. Joyce & Co. (Joyce), and Joyce agreed to assumed to know the ordinary course of things and to be
make a new shaft from the pattern of the old one. Therefore, a servant of aware of the loss that is liable to result from a breach of
Plaintiffs went to the office of Defendants, common carriers, to have the contract in the ordinary course. The law will impute or
crank shaft taken to Joyce. Plaintiffs’ servant told Defendants’ clerk that the ascribe to every individual, knowledge of the loss that is
mill was shut down and the shaft must be sent immediately. The clerk liable to result naturally or in the ordinary course of things
informed Plaintiffs’ servant that if the shaft were given to them by twelve from a breach of contract. (first limb in Hadley v
o’clock any day, it would be delivered by the next day. Plaintiffs took the Baxendale)
shaft to Defendants the next day before noon. Due to Defendants’ neglect, § Actual knowledge: Where parties actually have
the delivery to Joyce was delayed, and Plaintiffs did not receive the new knowledge of special circumstances outside the ordinary
shaft for several days after they should have received it. course of things of such kind that a breach in those
- Held: the court held that the loss of profit was too remote and defendant special circumstances would be liable to cause more loss.
not liable. (second limb in Hadley v Baxendale)
- Alderson B laid down the test of remoteness in 2 rules: o Case: Koufos v C Czarnikow Ltd
o “Where two parties have made a contract which one of them has o Facts: The charterer chartered a ship from the shipowner to carry
breached, the damages which the other party ought to receive in sugar from Constanza to Basrah. The charterer had intended to
respect of such breach of contract, should be: sell the sugar as soon as the ship reached Basrah. Their intention
§ Such as may fairly and reasonably be considered either was not communicated to the shipowner and the shipowner did
arising naturally, that is according to the usual course of not know about it. However, it was shown that the shipowner knew
things from such breach of contract itself; or that there was a market for sugar in Basrah. In breach of contract
§ Such as may reasonably be supposed to have been in for charter, the ship deviated and reached Basrah 9 days late.
the contemplation of both parties, at the time they made During these 9 days late, the market price for sugar at Basrah fell
the contract, as the probable result of the breach of it and the charterer suffered loss.
- Case: Victoria Laundry (Windsor) Ltd v Newman Industries Ltd o Held: the charterers were entitled to recover the difference in price
- Facts: the plaintiffs bought a new boiler for their laundry and dry cleaning caused by the delay.
business from the defendant, but received it 5 months after the contracted o Case: H Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd, the
date of delivery. The defendant knew that the plaintiff required the boiler for Court of Appeal held that the defendants could have contemplated
their business. The plaintiff claimed for loss of profits during the period of 5 a serious possibility that the pigs might become ill due to the defect
months, and the loss of profit from a highly lucrative dyeing contract with in the hopper.
the Ministry of Supply. Position in Malaysia
- Held: The plaintiff was entitled to the loss of profits arising from the - Section 74(1) of the Contracts Act 1950: When a contract has been
defendant’s delay in delivering the boiler, but was not entitled to the broken, the party who suffers by the breach is entitled to receive, from the
exceptional loss of profit it could have earned from the dyeing contract with party who has broken the contract, compensation for any loss or damage
the Ministry of Supply as it was not reasonably foreseeable that the plaintiff caused to him thereby, which naturally arose in the usual course of things
would suffer such loss. from the breach, or which the parties knew, when they made the contract,
- Lord Asquith reformulated the rule in Hadley v Baxendale with a specific to be likely to result from the breach of it.
focus on reasonable foreseeability: - Section 74(2) of the Contracts Act 1950
- Case: Bee Chuan Rubber Factory Sdn Bhd v Loo Sam Moi o Case: Bank Bumiputra Malaysia Bhd, Kuala Terengganu v
- Facts: the appellants entered into a contract to sell a piece of land and to Mae Perkayuan Sdn Bhd
build a house thereon for the respondent. In breach of contract, the o Facts: The respondent proposed to develop a few pieces of land
appellants delayed in the completion of the contract. in Dungun, and agricultural lands in Alor Gajah into housing
- Held: The court awarded damages to the respondent at $100 for every estates. The appellant agreed to grant an overdraft facility of
month from the time delivery was due on 21st September 1970 until 3rd RM4.5 million to the respondent for both projects. The appellant
April 1975 when delivery was finally given. The Federal Court affirmed the knew that the repayment for facility for the Alor Gajah project
trial judge’s decision. Damages are recoverable for a breach of contract for would be recovered from the Dungun project’s profit revenue.
delay in the completion of an ordinary dwelling house required for personal Before the term of the overdraft facility ended, the appellant
occupation. Such damages which include the reasonable cost of living withdrew the overdraft facility and demanded payment of the
elsewhere and storing furniture came within the first limb of the rule in money due together with interest. Where the appellant had
Hadley v Baxendale. breached the bridging loan agreement, the respondent claimed for
Remoteness and measure of damages in specific cases damages for both projects.
- a) sale and purchase of land o The Supreme Court held: the claim for loss of profit in regards to
o Case: Tan Sri Khoo Teck Puat v Plenitude Holdings Sdn Bhd the Dungun project was allowed as the appellant had known that
o Facts: The appellant had agreed to sell to the respondent certain if the overdraft facility was frozen, the project would be affected.
land for the purpose of development. The respondent failed to pay The court stated that the loss of profits was the natural and
the balance purchase price within the stipulated period and the probable result of the breach of agreement (first limb of Sec. 74(1)),
appellant terminated the agreement. The respondent initiated and the appellant knew of the loss the respondent would suffer if
action for damages, which included a loss of profits, for delay in they committed the breach (second limb of Sec. 74(1)). However,
delivering title as a result of wrongful termination by the appellant. the court did not allow the claim for loss of profit for the Alor Gajah
o Held: However, in assessing the damages, the Federal Court held project which was dependent upon the application of profits
that any price increase in the land should be deducted from the expected from the Dungun project, and was thus, too remote.
loss of profits, or else it would put the respondent in a better - d) building contracts
position than it would have been if the contract had been o Case: Joo Leong Timber Merchant v Dr Jaswant Singh a/l
performed. Where the value of the land had increased by nearly Jagat Singh, it was held that in Malaysia there is no legal authority
RM70 million, the court found that the respondent had in fact which states that the failure to mitigate must be pleaded.
suffered no loss by reason of the breach of the agreement and Mitigation of loss
had not proved its claim for loss of profits. The court awarded the - The common law imposes upon the victim of a breach of contract a duty to
respondent nominal damages of RM10. mitigate or minimize the losses flowing from the breach. Meaning, the
- b) goods sold and delivered innocent party cannot recover any part of the damages that he could have
o Case: Bee Wah Plastic Factory Sdn Bhd v Francis Soh Kai avoided by taking all reasonable steps possible in the circumstances.
Shuen (b/s Shatin Marketing & General Agencies) - Section 74(3) of the Contracts Act 1950
o Facts: the appellants agreed to make and supply plastic gum - Explanation to Section 74 of the Contracts Act 1950: In estimating the
bottles by using the mould provided by the respondent. The loss or damage arising from a breach of contract, the means which existed
appellants had failed to make the bottles and the Magistrate’s of remedying the inconvenience caused by the non- performance of the
Court awarded damages amounting to RM20,972 to the contract must be taken into account.
respondent. The appellants appealed - Case: British Westinghouse Electric Co Ltd v Underground Electric
o Held: the HC held that the loss of profit claimed by the respondent Railway, the plaintiff has a duty to take all reasonable steps to mitigate the
was a direct loss caused by the failure of the appellants in loss consequent on the breach, and is barred from claiming any part of the
supplying the bottles, there was insufficient evidence to prove loss damage which is due to his neglect to take such steps.
of profits claimed. The HC only allowed nominal damages. - Case: Kebatasan Timber Extraction Co v Chong Fah Shing
- c) overdraft facility
- Facts: The appellants contracted to supply timber to the respondent, which obtain other suitable employment. He is not entitled to remain idle
was to be delivered at the site where the respondent had erected a saw- at the defendant’s expense simply because no precisely similar
mill. Three lots of timber were delivered. The second lot, instead of being employment can be found, but he can accept employment which,
delivered to the mill, was dumped more than 500 feet away from the mill. having regard to his standing, experience and personal history he
The respondent purchased new timber elsewhere in substitution of the can reasonably be expected to accept even at a lower salary.
second lot and claimed for the cost of doing so. - Burden of proof that the plaintiff has failed to mitigate is on the
- Held: The respondent had a duty to take reasonable steps to mitigate its DEFENDANT.
loss. Instead of expending money to purchase new timber, all that was o Case: Raja Lope & Anor v Malayan Flour Mills Bhd, the High
required of the respondent was to arrange to move the logs to the saw-mill. Court held that a defendant who wishes to rely on the defence that
- Case: Malaysian Rubber Development Corp Bhd v Glove Seal Sdn Bhd a claimant has failed to mitigate his loss must plead the issue of
- Facts: The plaintiffs were to supply to the defendants two million rubber mitigation.
gloves per month from November 1988 to October 1989. The defendant Rules of Mitigation
breached the agreement in failing to issue an irrevocable letter of credit in - 1) Avoidable losses: a plaintiff will not recover damages for losses it should
favour of the plaintiffs. The plaintiffs claimed damages of approximately have avoided
RM6.2 million being loss of profits, interest, marketing costs and losses o Case: Tansa Enterprise Sdn Bhd v Temenang Engineering
incurred. Sdn Bhd, where the defendant breached the contract to supply
- The Supreme Court held: In cases involving sale of goods, the innocent common bricks, which was available in the open market at the
party should act immediately upon the breach, and buy or sell in the market, material time, the plaintiff should have mitigated his loss by
if there is an available market. In the absence of an available market, the entering into a substitute contract for the bricks.
innocent party is to act reasonably to mitigate his loss. - 2) Avoided losses: if a plaintiff avoids a loss, damages are not recoverable
- Case: Berjaya Times Square Sdn Bhd v Twingems Sdn Bhd & Anor for that loss
and another action o Case: British Westinghouse Electric Co Ltd v Underground
- Facts: both entered into a 3 year fixed term tenancy agreement to rent Electric Railway, the appellants sold faulty and inefficient
space in the square for a food and beverage outlet. However, after only 77 turbines to the respondents, which the respondents still accepted
days, Twingems closed its business. The plaintiff did not agree but and used. After several years, the respondents replaced the
Twingems returned the keys to the plaintiff. turbines, which proved to be much more efficient than the ones
- Held: allowing the claim of the plaintiff for losses as the losses suffered by which should have been supplied by the appellants. The court
the plaintiff were actual losses (Pursuant to Cl. 10(2), where the plaintiff held that where the respondents were not obligated to replace the
was entitled to claim for the monthly rentals and service charges). The turbines, the efficiency of the replaced turbines reduced the
plaintiff had no obligation to mitigate its losses. respondents’ working expenses such that all loss was
- The test of whether a plaintiff has mitigated his loss has thus been extinguished.
formulated: - 3) Money spent in mitigation: money spent in mitigation or attempting to
o “whether a prudent man would have acted in the same way if the mitigate losses is recoverable.
original wrongful act arisen through his own default. o Case: Hoffberger v Ascot International Bloodstock Bureau
th
- In Halsbury’s Law of England 4 edn. Vol 12 para 1195 explains the Ltd, where the defendants breached the contract to buy a horse,
following situations represent examples of mitigation: the plaintiff kept the horse for an entire year in hopes of selling it
o A) in a sale of good situation, the plaintiff is under a duty to mitigate at a higher price. However, after a year, the horse was sold at a
his loss by going to the market and buying and selling, if there is much lower price, and thus the court awarded damages to the
an available market plaintiff in having kept the horse for a year.
o B) to accept an offer by the defendant to supply goods on different
terms
o C) in actions for breach of contract of employment, a plaintiff who
has been wrongfully dismissed must take reasonable steps to
Types of Damages period, as the plaintiffs failed to prove the depreciation, the HC awarded
1. General Damages nominal damages of RM100.
- Damages that flow naturally from the commission of a wrong and which 4. Exemplary Damages
need not specifically pleaded or proven. - As the purpose of damages in contract is to put the plaintiff in the position
- Damages that the law presumes to have resulted from the defendant’s he would have been in if the contract had been performed, the defendant’s
breach of contract. conduct is irrelevant.
- Damages that do not need to be pleaded as the law presumes that such - In UK, exemplary damages are no longer available for a breach of contract.
damages result from the infringement of a legal right or duty. - Case: Addis v Gramaphone Co Ltd, the position that exemplary damages
- General damages are those losses, usually but not exclusively non should not be awarded in a breach of contract.
pecuniary, which are not capable of precise quantification in monetary - In Malaysia, exemplary damages have been awarded and used to punish
terms. a defendant in exceptional situations.
- Examples: - Case: Rookes v Barnard, the House of Lords established three categories
o Anticipated future loss when exemplary damages may be awarded:
o Damages for pain & suffering, loss of amenity o There has been oppressive, arbitrary or unconstitutional conduct
o Difference between contract price and market price by government servants
o Reasonable expenses incurred o The defendant’s conduct had been calculated by him to make a
2. Special Damages profit for himself which may exceed the compensation payable to
- Losses which can be calculated in financial terms the plaintiff
- Lord Macnaghten in Stroms Bruks Aktie Bolag v Hutchison, special o A statute has expressly authorised it
damages are exceptional in their character, and there they must be claimed - Case: Dennis v Sennyah, general damages RM1,500 and special
specifically and proved strictly. damages RM620.10 was awarded.
- Damages that must be specifically pleaded. The court would require the - Case: Dato’ Abdullah Hishan v Sharma Kumari Shukla
precise amount of pecuniary loss and relevant evidence must be adduced. - Facts: The plaintiff loaned the defendant money for her to purchase certain
- Damages which accrued in the particular situation caused by the breach shares and the defendant offered to convert to Islam to marry him. The
and which would not customarily flow from all situations of that type. defendant breached the agreement and the plaintiff sought exemplary
3. Nominal Damages damages, arguing that the defendant had misled the plaintiff into believing
- Usually of a small sum that she would convert to Islam to marry him.
- Whenever there is a breach of contract by the defendant but the plaintiff - Held: This case fell within the second category set out in Rookes v Barnard
suffers no actual loss or fails to sufficiently prove such loss, the plaintiff is as it amounted to behaviour calculated to bring about a profit. The
generally entitled to nominal damages. defendant’s promise to marry had encouraged the plaintiff to give the loan.
- Case: Owners of the Steamship “Mediana” v The Owners, Master, and The defendant’s profit extended to her desire and aspiration to be called
Crew of the Lightship “Comet”, nominal damages affirm that there has ‘Datin’, as well as her travel expenses and expensive gifts. Thus, the
been an infraction of a legal right, and although it does not give the plaintiff plaintiff was awarded RM500,000 in exemplary damages.
rights to any real damages, it gives the plaintiff the right to a verdict or 5. Aggravated Damages
judgment where his right has been infringed. - In certain circumstances the court may award more than the normal
- Case: Tan Sri Khoo Teck Puat v Plenitude Holdings Sdn Bhd, where measure of damages by taking into account the defendant’s motive and
the court found that the respondent had in fact suffered no loss by reason conduct (Huljich v Hall)
of the breach of the agreement and had not proved its claim for loss of - Often claimed together with exemplary damages
profits, the court awarded the respondent nominal damages of RM10. - Injury to the plaintiff which has been aggravated by malice or manner of
- Granted when the plaintiff suffers loss but it is unable to prove his loss. doing that injury, the insolence or arrogance by which it is accompanied, is
- Case: Industrial & Agricultural Distribution Sdn Bhd v Golden Sands not justification for an award of exemplary damages.
Constructions Sdn Bhd, the plaintiffs claimed that the excavators had
depreciated in value owing to the defendants used of them over 2 months
- Case: Dato’ Abdullah Hishan v Sharma Kumari Shukla, aside from the - Case: Wearne Brothers (M) Ltd v Jackson
exemplary damages, the court also awarded the plaintiff aggravated - Facts: An appeal against the award of damages for breach of contract in
damages of RM500,000. respect of a hire purchase agreement relating to a motor car. The main
6. Liquidated Damages and Penalties ground of appeal was that the learned president of the sessions court failed
- Liquidated damages: the fixed and contractually agreed sum which are to consider whether the relevant clause in the hire purchase agreement
many payables by the defaulting party upon a breach of contract. The was a penalty clause or was a genuine pre- estimate of the damage as on
definition of 'Liquidated Damages' in The Black's Law Dictionary, an the date of the agreement. The learned president merely applied the
amount contractually stipulated as a reasonable estimation of actual common law principle for the assessment of damages for breach of contract.
damages to be recovered by one party if the other party breaches. The judge in his decision has mentioned that where the distinction between
- Penalty: according to the US Legal, is the stipulated damages a party to a liquidated damages and penalty has ceased because in either case, the
contract should pay in case of breach. It is the sum of money the party court must determine reasonable compensation.
agrees to pay or forfeit by way of punishment in case of breach of the - Held: A party cannot claim whether the clause in the agreement was a
contract. Penalty can also be said to be sums which are grossly penalty clause or not was irrelevant in view of section 75, which provides
disproportionate to the actually loss that will be suffered by the innocent that in every case the court must determine what is the reasonable
party in the event of a breach. compensation. The effect of the section is that the plaintiff cannot claim
- Common Law Common Law terms liquidated damages as a “penalty” as it simpliciter the sum fixed in the contract whether as penalty or liquidated
is actually meant to terrorize the other party into performing his obligation damages and the plaintiff must prove the loss suffered by him.
under the contract. - Case: Selva Kumar A/L Murugiah v Thiagarajah A/L Retnasamy
- Case: Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd, - Facts: Both the appellant and respondent in this case are medical
the court will decide if they are liquidated damages or a penalty. If a practitioners. The appellant entered into an agreement in writing with the
provision in a contract constitutes a penalty, then that provision is respondent whereby the respondent sold his clinic to the appellant for a
unenforceable by the parties. total purchase price of RM120,000. Pursuant to the agreement, the
- Case: Esanda Finance Corp Ltd v Plessnig & Anor, an agreed sum is a appellant paid to the respondent RM12,000 on signing the agreement, and
penalty if it is extravagant, exorbitant or unconscionable in relation to the thereafter paid a further sum of RM48,000. The balance of RM60,000 was
loss likely to be suffered. to be paid by 15 monthly instalments of RM4,000 each. However, at the
- Malaysian position based on Section 75 of the Contracts Act 1950 stage when the appellant had paid up to a total sum of RM96,000 towards
- Section 75 of the CA 1950: when a contract has been broken, if a sum is the total purchase price, he refused to go on paying the remaining six
named in the contract as the amount to be paid in case of such breach, or monthly instalments. The respondent sought to forfeit the paid amount by
if the contract contains any other stipulation by way of penalty, the party relying on a clause in the agreement which in effect, provided that if the
complaining of the breach is entitled, whether or not actual damage or loss appellant defaulted, all moneys paid to date of such breach would be
is proved to have been caused thereby, or to receive from the party who forfeited absolutely to the respondent as agreed liquidated damages, and
has broken the contract reasonable compensation not exceeding the the agreement would be terminated.
amount so named or, as the case may be, the penalty stipulated for. - Held: where the respondent failed to prove actual loss suffered, he was
- In short, Section 75 allows reasonable compensation to be awarded by the only entitled to forfeit the deposit of RM12,000. The remaining sum of
court irrespectively of whether actual loss or damage is proven. Thus, proof RM84,000 was ordered to be refunded to the appellant.
of actual loss is not the sole conclusive determinant of reasonable o The plaintiffs need to prove their loss and they managed to prove
compensation although evidence of that may be a useful starting point. In as their actual damage, the sum of Rs500 which they recovered.
Malaysia, there no distinction of liquidated damages and penalty where Thus, it is obvious that any submission as to whether a certain
there is a breach of contract, an innocent party cannot recover simpliciter clause in a contract is a penalty or liquidated damages is an
the sum fixed in a damages clause regardless of whether it is stipulated as exercise in futility. In effect, section 75 deems a liquidated
a penalty or liquidated damage damages clause to be penal and therefore invalid. Accordingly,
any sum expressed as liquidated damages cannot, be
automatically recovered by the injured party.
o The second issue is on the requirement to prove loss in order to - Case: Cubic Electronics Sdn Bhd (in liquidation) v Mars
determine compensation. The court held that the words in Telecommunications Sdn Bhd
question, 'whether or not actual damage was proved to have been - Facts: The appellant owned a piece of land with plant and machinery in
caused thereby', are limited or restricted to those cases where the Mukim Bukit Katil, Melaka. The land was charged to OCBC Bank (M) Bhd
court would find it difficult to assess damages for the actual (‘OCBC’), as a secured creditor of the appellant. OCBC presented a petition
damage or loss, as distinct from or opposed to all other cases, to wind up the appellant and was granted by Shah Alam High Court on 25
when a plaintiff in each of them will have to prove the damages or July 2011. Following the appellant’s winding-up, the liquidators decided to
the reasonable compensation for the actual damage or loss in the sell the properties by open tender and issued an information memorandum
usual ways. Hence, a plaintiff who is claiming for actual damages containing the terms, conditions and requirements of the tender exercise.
in an action for breach of contract must still prove the actual Before the exercise could be carried out, the respondent offered to buy the
damages or the reasonable compensation in accordance with the properties for RM90 million and submitted a cheque for RM1 million as
settled principles in Hadley v Baxendale. Any failure to prove such earnest deposit, on 3rd October 2011. The liquidators accepted the offer
damages will result in the refusal of the court to award such and the earnest deposit (even though under the terms of the information
damages. memorandum the respondent should have paid RM2.6 million as earnest
o The third issue, on the assessment of damages where the value deposit) and did not proceed with the tender exercise. The liquidators
is not known. For cases where the court finds it difficult to assess notified the respondent that under the terms of the information
damages for the actual damage as there is no known measure of memorandum if the respondent failed to sign a sale and purchase
damages employable, and yet the evidence clearly shows some agreement (‘SPA’) for the purchase of the properties within 30 days from
real loss inherently which is not too remote; the court ought to 7th October 2011, they had the right to cancel the sale and forfeit the RM1
award substantial damages as opposed to nominal damages million ‘as agreed liquidated damages and not by way of penalty’. Before
which are reasonable and fair according to the court's good sense the 30-day deadline approached, the respondent asked for an extension of
and fair play. In any event, the damages awarded must not exceed time of one month to pay the balance of the 10% deposit under the SPA
the sum so named in the contractual provision. until 23rd November 2011. The liquidators agreed to grant the extension
o Where the parties failed to bring evidence or to prove damage. In (subject to the same forfeiture warning as before) upon the respondent
any case where there is any actual loss or damage from the paying an additional RM500,000 towards the earnest deposit. The
evidence or nature of the claim and damage for such actual loss appellant had in November 2011 received and declined a proposal by
is not too remote and could be assessed, the parties must bring in UTeM Holdings to purchase the properties for RM135 million on the basis
further evidence or to prove damages for such actual loss or that it had already finalized the SPA with the respondent. On 22nd
damage. The failure to do so will result in the refusal of the court November 2011, the respondent requested for a second extension of time
to award such damages. which was again granted on the respondent’s payment of a further
o The claim for deposit. Apart from the real loss (which has not been RM500,000 towards the earnest deposit. On 21st December 2011, the
proved), the vendor ought to be entitled, in any event, to forfeit any respondent asked for a third extension of time, the liquidators made it clear
reasonable amount of earnest money or deposit. The sum of that it would be the final extension subject to the respondent paying an
deposit in this case was RM12,000, which was paid on signing the additional RM1 million towards the earnest deposit and a further RM40,000
agreement by the purchaser to the vendor. as interest calculated at 8% per annum on the unpaid balance deposit of
o The court viewed that the sum of RM12,000, considering the RM6m payable upon the signing of the SPA. The liquidators reminded the
circumstances of this case, is not too large to prevent it from being respondent that if it defaulted in paying the additional RM1 million earnest
fully forfeitable. The court would not interfere with it, and thus deposit and RM40,000 in interest and also failed to execute the SPA and
would allow the vendor to forfeit it or keep it. pay the balance RM6 million deposit by the final extended deadline, all
earnest deposit sums paid would be forfeited as agreed liquidated
damages pursuant to the terms of the information memorandum. On 25th
January 2012, the respondent sent a cheque for RM6 million to the
appellant together with a request for another extension of time to sign the
SPA. On 30th January 2012, the appellant refused the request, terminated § Regardless of whether the damage was quantifiable or
the sale, returned the respondent’s cheque and informed the respondent not, it was incumbent upon the court to adopt a common-
that it was forfeiting the total sum of RM3.04 million that the respondent had sense approach by taking into account the legitimate
paid as earnest deposit and interest. The properties were subsequently interest which an innocent party might have and the
sold to a third party (‘Neraca Niaga Sdn Bhd’) by way of an open tender. proportionality of a damages clause in determining
- Held: reasonable compensation. In a straightforward case,
o The decision of the High Court was that the court dismissed the reasonable compensation could be deduced by
respondent’s claim holding that the liquidators were entitled to comparing the amount that was payable on breach with
terminate the sale agreement and forfeit the deposits and interest the loss that might be sustained if indeed the breach had
payment on the respondent’s failure to execute the SPA. The occurred. Thus, to derive reasonable compensation,
court held that the appellant did not have to prove any loss or there must not be a significant difference between the
damage in order to forfeit the deposits as they were true earnest level of damages spelt out in the contract and the level
deposits paid towards purchase of the properties and were not of loss or damage which was likely to be suffered by the
penalties and therefore section 75 of the Contracts Act 1950 had innocent party.
no application. § On the correspondence between the parties disclosed
o The decision of Court of Appeal overturned the High Court’s that the additional sums totalling RM2.04 million were
decision and ruled that the parties had only agreed to the first paid by the respondent in return for the appellant
payment of RM1 million as the earnest deposit and only that sum extending the time for the respondent to execute the SPA
was forfeitable; that since no SPA was signed the respondent was and that upon execution of the SPA the said payments
not liable to pay a deposit of RM9 million to buy the properties. would go towards part payment of the total earnest
The Court of Appeal held that the appellant failed to prove that it deposit of RM9 million for the purchase of the properties.
had suffered any loss and the forfeited monies were not a genuine The additional payments, thus, bore the characteristics
pre-estimate of loss or reasonable compensation as required of a deposit which was subject to the same test of
under section 75 of the Contracts Act 1950. reasonableness under the law applicable to damages
o The Federal Court held by allowing the appeal by the appellant, clause under section 75 of the Contracts Act 1950.
setting aside the decision of the Court of Appeal and reinstating § That the parties were well aware that if the respondent
the decision of the High Court but for different reasons. defaulted in executing the SPA, the earnest deposit
§ That there was no necessity for proof of actual loss or payments it had made would be forfeited as agreed
damage in every case where an innocent party sought to liquidated damages. On each occasion when an
enforce a damages clause in a contract. Section 75 of extension of time was granted, the appellant repeatedly
the Contracts Act 1950 allowed reasonable warned that failure to execute the SPA would result in
compensation to be awarded by the court irrespective of forfeiture of the amounts paid as ‘agreed liquidated
whether actual loss or damage was proven. The court damages and not by way of penalty’. Accordingly, the
stated that in the case of Selva Kumar Murugiah v respondent’s conduct was strong evidence of its
Thiagarajah Retnasamy and Johor Coastal agreement that the additional payments of RM2 million
Development Sdn Bhd v Constrajaya Sdn Bhd, should would form part of the earnest deposit guaranteeing its
not be interpreted (as what the subsequent decisions execution of the SPA and which would eventually be
since then have done) as imposing a legal straightjacket counted towards payment of the total earnest deposit of
in which proof of actual loss is the sole conclusive RM9 million.
determinant of reasonable compensation. Reasonable § Where the parties had agreed to the payment of the
compensation is not confined to actual loss, although RM40,000 as interest charged for the respondent’s delay
evidence of that may be a useful starting point. in paying the balance of the earnest deposit of RM6
million. The parties agreed that the sum was non-
refundable regardless of whether or not the sale went Deposit
through and regardless of any breach. - Paid as security for the performance of a contract. Should a breach occur
- Case: Kerajaan Malaysia v KCSB Konsortium Sdn Bhd and is caused by the payer, then the payee can forfeit the deposit
- Facts: where there was an Army Camp in Skudai that remained automatically without having to prove any actual loss cause by the breach.
uncompleted after 13 over years. In consideration of the defendant - Rationale: a deposit is a guarantee for the performance of the contract, if
completing the project, the plaintiff at the outset of the contract transferred the contract is not performed, this guarantee can be called upon.
the two pieces of the exchanged lands to the defendant. As required under Definition
the contract, the defendant duly furnished a land bond of RM256m and a - An initial payment made under a contract to show that the payer is earnest
performance bond of RM12.8m. The defendant had some serious financial intensely serious in carrying out the contract.
problems. This was where the defendant failed to renew both of the - Lord Hailsham LC in Linggi Plantations Ltd v Jagatheesan, a deposit is
performance bonds that should be renewed. With no security in the bonds not merely a part payment but it is also an earnest money to bind the
equivalent to the value of the exchanged lands already transferred to the bargain entered into creates by fear of its forfeit a motive in the payer to
defendant for which the plaintiff could not get back, there was only the sure perform the rest of the contract.
loss if the project could not be completed at all. On 17 August 2004, the Purpose
parties agreed that the works at the project was revalued and the land bond - If the purchase is carried out, it goes towards the purchase price but the
was reduced based on the balance work to be completed. However, later primary purpose for the deposit is to act as guarantee that the purchaser
the defendant disclosed that they lacked the financial resource to means business.
recommence work that they had stopped. - Case: Howe v Smith, CoA, plaintiff is not entitled for a specific performance
- Held: HC that allowing the plaintiff’s claim where it could not be disputed and on the issue of deposit, it was a guarantee for the performance of the
failure to renew the performance bond and the land bond was both a breach contract since the plaintiff defaulting in performing his contractual
of the contract. The plaintiff was entitled to RM269,502,986.14 for which obligations he had no right to a return of the deposit.
allowed judgment to be entered against the defendant and the plaintiff must - Case: Guna Sittampalan & Anor v Aik Hua Properties Sdn Bhd, where
still show and prove what is the loss it has suffered. money is deposited with either contracting party on the formation of a
- Case: Macvilla Sdn Bhd v Mervyn Peter Guan Yin Hui & Anor contract, it will, prima facie, be interpreted as a security for performance,
- Facts: the appellant is a housing developer and the respondent is the buyer and hence, forfeited if the depositor in breach of the contract fails to perform
of one unit of condominium in the project developed by the appellant, his side of the bargain.
known as “Vision Residence”. They entered into a sale and purchase - Case: Sun Properties Sdn Bhd v Happy Shopping Plaza Sdn Bhd
agreement and the respondent claimed for liquidated ascertained damages - Facts: There was a sale and purchase agreement for shares of RM10
for the late delivery of the vacant possession of the Property and common million and RM1 million was paid as a deposit.
facilities for RM32,011.79. This is where stipulated in the agreement that - Held: 10% of the purchase price was a normal sum for a deposit. Thus, the
“in the event that the housing delays in handing over the vacant possession sum of RM1 million was a true deposit which, upon the purchaser’s failure
according to the deadline, the purchaser is entitled to not less than 10% of to pay the first instalment on the due date, entitled the vendor to forfeit it.
the purchase price”. - Case: Linggi Plantations Ltd v Jagatheesan, a deposit or earnest money
- Held: The Tribunal of Homebuyers Claims allowed the claim of the is part of the purchase price when the transaction goes forward, it is
respondent and gave an award in favour of the respondent. The developer forfeited when the transaction falls through by reason of the fault or failure
appealed to the High Court and appeal to the Court of Appeal. The Court of the vendee.
of Appeal held in favour of the respondent and stated that the 10% claimed - Deposit is not a benefit received under the contract within the meaning of
was reasonable. The principles relied in this case by the Court of Appeal Section 65 of the Contracts Act 1950, but a security that the purchaser
are, Section 75 of the Contract Act 1950 is related to a claim by an innocent would fulfill his contract. Section 75 had no application to the forfeiture of a
party against the defaulting party. that if there is a stipulated sum as agreed deposit.
damages, there is a presumption that it is a penalty. If the defaulting party Issue of unpaid deposit
agrees to the clause there is no issue and if the defaulting party objects to - Case: Morello Sdn Bhd v Jagues (International) Sdn Bhd, when a
the clause, the plaintiff has an obligation to prove loss and damage. deposit is forfeited, it represents damages for a vendor for the loss of his
bargain. Thus, a vendor is entitled to sue for recovery of an unpaid deposit Part-payment
upon termination of the contract for a breach committed. The fact that there - An installment towards the contract price, unlike deposits, part payments
is no provision in the contract on forfeiture of the deposit does not prohibit cannot be forfeited automatically upon a breach of contract.
the vendor from obtaining an unpaid deposit. - The innocent party will have to return these payments or installments to the
General Rule party in breach but the former is entitled to sue the latter for any losses
- A true deposit can be forfeited by the innocent party upon there being a suffered as a result of the breach of contract.
breach of the contract. However, there are certain instances where the - Case: Mayson v Clouet
court may in its discretion grant equitable relief against the forfeiture of a - Facts: a contract for the sale of land was entered into between a vendor
deposit. and purchaser, which provided that a deposit should be paid immediately.
- Case: Stockloser v Johnson, Dening LJ laid down two conditions before Two instalments of cash were to be paid at certain dates. The contract
equity can intervene to prevent forfeiture of money paid under a contract: provided that, in the event of a breach, the deposit is to be forfeited. The
o The forfeiture clause must be a penalty, must be of a penal nature purchaser paid the deposit and the two instalments, but defaulted in paying
in that sum forfeited must be out of proportion to the damage the balance of the price. The vendor rescinded the contract and the
o It must be unconscionable for the defendant to retain the money. purchaser sued to recover the instalments.
Equitable relief against forfeiture of deposit - Held: Despite the purchaser’s default in complying with his contractual
- Case: K Umar Kandha Rajah v EL Magness, in a sale and purchase obligations, he was entitled to recover the instalments paid to the vendor.
agreement for land, the vendor failed to surrender title to the land and later The contract had clearly distinguished between the deposit and the
terminated the contract and forfeited the deposit of RM5000. The Federal instalments, and only provided for the forfeiture of the deposit.
Court granted the purchaser relief against forfeiture as it would be unjust
for the vendor to forfeit the deposit in light of the vendor’s failure to
surrender title to the land within the agreed time.
- Case: Chen Chow Lek v Tan Yew Lai
- Facts: Respondent agreed to sell the appellant a terrace house. There was
a provision in the agreement that if the purchaser failed to pay the
installments and interest, the vendor would be entitled to forfeit all
payments already made by the purchaser and also recover possession of
the said house. The appellant had paid all the installments except for a
balance of $100 at the time of the trial. Based on the appellant’s failure to
pay this balance, the respondent terminated the contract and forfeited all
payments made. The appellant claimed for relief against the forfeiture.
- Held: granted the said relief and stated that the forfeiture clause was meant
to guarantee payment of the installments and interest for the price of the
house. The court referred to Stockloser v Johnson and held that based on
the sum paid, the appellant is entitled to the relief because if it was not
granted, the forfeiture would amount to a penalty since the appellant had
almost paid the full purchase price of the house.
Specific Performance informed the plaintiff that he would sell the land and give
- Works at the discretion of the court to the plaintiff the latter’s due proceeds from the sale.
- Equitable remedy § Held: However, after several years the sale had not yet
- Will not rescind the contract to taken place. It was found by the High Court that, as
- Specific Performance can be said as an decree by the court that requires the defendant was to be regarded the plaintiff’s trustee in
the party against whom it is directed to do what he promised to do under a respect of the share due to the fact that the defendant
contract. had recognized the plaintiff’s entitlement to a share in the
Nature land although he is the sole proprietor of the land. By
- Case: Zainab bte Mohamed v Syarikat Permodalan Johor Sdn Bhd, informing the plaintiff since 1981 that he was going to sell
Abdul Malik Ishak J, specific performance is an equitable relief given by the the said land, and from the proceeds of sale the plaintiff
court to enforce against a defendant the duty of doing what he agreed by should receive his entitlement, the defendant under
contract to do. It can be seen that the remedy of specific performance is in section 11(1)(a) of the SRA be compelled to carry out the
sharp contrast with the remedy of damages for breach of contract - where act that he agreed to do that is to sell the land.
the court orders pecuniary compensation for failure to carry out the terms o b) When there exists no standard for ascertaining the actual
of the contract. damage caused by the non-performance of the act agreed to be
Effect: done;
- to put parties into the position they would have been in had the contract § Provides that a contract may be specifically enforced
been performed and it is the equitable equivalent of damages in respect of where there exists no standard for ascertaining the
claimant’s expectation loss. actual damage caused by its non-performance. In other
Judicial principles words, specific performance will be granted if there is no
- 1. Specific performance of a contract will only be granted where a valid and standard to ascertain the damage.
enforceable contract exists § Case: Gan Realty Sdn Bhd v Nicholas & Ors
- 2. Contract must be valid in form, has been made between competent § Facts: This was an application to dissolve the ex parte
parties and in unobjectionable in its nature and circumstances injunction granted to the plaintiffs restraining the
- 3. Parties must have agreed, expressly or impliedly to all the essential defendants from parting with their shares in the Oriental
- 4. Ready and willing to perform his part. Bank of Malaya Berhad, the 6th defendant. On 4th May,
Cases in which specific performance enforceable 1968 they negotiated with the plaintiffs concerning the
- Section 11 of the SRA 1950: sale of their respective shares in the bank. The terms and
o a) When the act agreed to be done is in the performance, wholly conditions of the agreement are confirmed in a letter
or partly, of a trust; dated 5th May, 1968 written by the plaintiffs' former
§ Specific performance may be granted for those solicitors to the defendants' former solicitors. The
beneficiaries in the event when a person is appointed as plaintiffs claim for specific performance of the agreement
a trustee and misapplied the trust and a permanent injunction.
§ Case: KK Kumaran v TS Sambanthanmurthi § Held: It was held that an agreement for sale and
§ Facts: Plaintiff bought a share in a plot of land whose title purchase of share could be specifically enforced
was registered in the name of the defendant. The plaintiff because the shares were not available in the open
claims that sometime in 1975, the defendant approached market. This means that there is no standard for
him to buy a share in the said land, which he did. He paid ascertaining the actual loss which would be caused by
to the defendant's solicitors a total sum of RM15,000 and the non-performance of the agreement. Here the
received in return receipts confirming this purchase. He inconvenience caused to the plaintiffs would be
claims that the defendant gave him the impression that irreparable and could not be remedied by damages.
the land would be subdivided. The defendant had Hence, specific performance was granted by the court
o c) When the act agreed to be done is such that pecuniary transfer the house to the plaintiff, and it also awarded damages for
compensation for its non-performance would not afford adequate incomplete work and defects under Section 18(3).
relief; or Contract which is not specifically enforced
§ Specific performance will be granted if monetary - Section 20(1) of the SRA:
compensation is inadequate. a) a contract for the non-performance of which compensation in money
§ In other words, where the act agreed to be done is such is an adequate relief
that pecuniary compensation for its non-performance o Case: Rainbow Estates Ltd v Tokenhold Ltd, it was held
would afford inadequate relief that specific performance should be available when damages
§ Case: Lim Sin Oo v Cheah Tjeng Sion, the court are not an adequate remedy or, in the more modern
granted the plaintiff specific performance as pursuant to formulation, when specific performance is the appropriate
an agreement to sell his landed property to the defendant, remedy. But the question of whether damages will be an
the plaintiff had terminated three existing tenancies in the adequate remedy for a breach of contract is often put in terms
building and paid compensation to the tenants, and also of whether the injured party would be able to purchase a
terminated his business carried out on the premises. substitute performance if given the remedy of damages.
§ Read together with Section 11(2) of the SRA b) a contracts which runs into such minutes or numerous details or which
§ Case: Zaibun Sa bte Syed Ahmad v Loh Koon May & is so dependent on the personal qualifications or volition of the parties
Anor or otherwise from its nature is such, that the court cannot enforce
§ Facts: The respondent applied for specific specific performance of its material terms
§ performance to direct the appellant to transfer the land to o Case: Dayang Nurfaizah Bte Awang Dowty v Bintang Seni
him as agreed under the contract. There was also an oral Sdn Bhd, a management agreement between the plaintiff, a
agreement that the vendor should pay RM5000 to the professional recording artist with the defendant, her personal
purchaser if he breaches the agreement. manager, was a contract to render personal services which
§ Held: Liquidation of damages is not a bar to specific cannot be specifically performed.
performance. The oral agreement did not prevent the o Specific performance is generally not granted for construction
granting of specific performance. contracts as they contain numerous details and require
o d) When it is probable that pecuniary compensation cannot be got continuous supervision.
for the non-performance of the act agreed to be done. § However, in Oon Hock Lai v Lee Kok Leong, the
Contracts which the subject has partially ceased to exist defendant agreed to sell a piece of land and to
- Section 12 of the SRA construct a building thereon for the plaintiff, which
Power to Award Compensation in Certain Cases was to be completed in seven months. The plaintiff
- Section 18 of the SRA claimed for specific performance against the
- Case: Lee Hoy v Chen Chi, where the sale and purchase agreement was defendant when the defendant abandoned the
for 9 acres of land, but the IDT only stated 5.28 acres, the purchaser applied construction after completing part of the building.
to rescind the contract based on misrepresentation. The High Court The High Court allowed specific performance of the
dismissed the application on the ground that there was no agreement as the plaintiff had sufficiently defined
misrepresentation, but awarded compensation under Section 18(3). the construction works required by exhibiting
- The Federal Court, in disagreeing with the High Court, held: Compensation comprehensive building plans for the construction of
under Section 18(3) can only be awarded where there is a claim for specific the building.
performance. c) a contract the terms of which the court cannot find with reasonable
- Case: Quah Ban Poh v Dragon Garden Pte Ltd, the High Court granted certainty
the plaintiff’s application for specific performance of a sale and purchase o Case: Soo Lip Hong v Tee Kim Huan
agreement of a house by ordering the defendant to surrender the IDT and o Facts: Parties signed an option for the sale of a shop house
at a specified purchase price. However, the vendor failed to
sign the sale and purchase agreement and to collect the § Case: Ooi Siew Eng & Ors v Link Ventures Sdn Bhd
balance of the purchase price from the purchaser. (In Liquidation) & Another Appeal, the decision of the
o Held: that as no sale and purchase agreement had been High Court, denied the specific performance, however in
signed, there was no concluded contract. Specific Appeal, specific performance should be granted as it will
performance cannot be granted as many essential terms had not give appellants any unfair advantage on Link
yet to be agreed upon between the parties and thus remained Ventures. This also will not cause hardship on the
largely a matter of conjecture. respondent as there is nothing that they can't foresee.
d) a contract which is in nature revocable o Section 21(2)(b) of the SRA: where the performance of a
e) a contract made by trustees either in excess of their powers or in contract would involve some hardship on the defendant which he
breach of their trust did not foresee, whereas its non-performance would involve no
f) a contract made by or on behalf of a corporation or public company such hardship on the plaintiff.
which is in excess of its powers. § Case: Sekemes Sdn Bhd v Lian Seng Co Sdn Bhd,
g) a contract the performance of which involves the performance of a court granted specific performance to plaintiff and denied
continuous duty extending over a longer period than three years from contention of defendant where they claimed that it would
its date cause hardship to complete the purchase of plot of land
o Case: Marble Terrazo Industries Sdn Bhd v Anggaran as they are not able to pay. The court held that hardship
Enterprise Sdn Bhd & Ors was self-inflicted because development project that
o The plaintiffs claimed that the defendants had verbally agreed required significant funds without ensuring that it had
to allow the plaintiffs to extract rocks material from certain sufficient financial resources.
land for a period of 20 years. Pending the outcome of the suit, - Court discretion to decree specific performance
the plaintiffs sought a temporary injunction to restrain the o Section 21(3) of the SRA: A case in which the court may properly
defendants from allowing other parties to mine the land. exercise a discretion to decree specific performance is where the
o The High Court held that no such injunction could not be plaintiff has done substantial acts or suffered losses in
granted by virtue of section 54(f) of the SRA due to the consequence of a contract capable of specific performance.
contract being not specifically enforceable under section o Case: Ganam d/o Rajamany v Somoo s/o Sinnah, where the
20(1)(g). defendant and plaintiff entered into a contract. The defendant had
h) a contract which a material part of the subject matter supposed by both paid RM 26,000.00 to the plaintiff but only paid less than one third
parties to exist, has before it has been made, ceased to exist of the amount of the contract. It was decided by the court that the
Discretion of the Court defendant was unable to bring the case as under section 21(3).
- Section 21 of the SRA: the jurisdiction to decree specific performance is Grant Specific Performance with Specific Terms
discretionary, and the court is not bound to grant any such relief merely - This purely based on the exercise of the court’s discretion.
because it is lawful to do so; but the discretion of the court is not arbitrary - This can be seen in the case of Loo Choo Teng & Anor v Cheok Swee
but sound and reasonable, guided by judicial principles and capable of Lee & Ors, the court allowed and grant specific performance for a sale and
correction by a court of appeal. purchase agreement. The terms for this is that, the defendant should apply
- Case: Lamare v Dixon, Lord Chelmsford stated that “the exercise of the to the court for formal sanction to sell property in accordance with the
jurisdiction of equity as to enforcing the specific performance of agreements, Probate and Administration Ordinance 1959, in relation to clause 8 of the
is not a matter of right in the party seeking relief, but of discretion in the agreement.
Court”.
- Court discretion not to decree specific performance
o Section 21(2)(a) of the SRA: where the circumstances under
which the contract is made are such as to give the plaintiff an
unfair advantage over the defendant, though there may be no
fraud or misrepresentation on the plaintiff’s part;
Injunction prevent the breach complained of, and also to compel
- The very principle of injunction law is that you do not obtain injunctions for performance of the requisite acts.
actionable wrongs for which damages are the proper remedy. § Case: Redland Bricks Ltd v Morris & Anor, the
Definition principles laid down were used as guidelines in granting
- Stroud’s Judicial Dictionary: a judgment or an order to do, or refrain from IMJ:
doing a particular thing • i. The plaintiff at present must show a very
Types strong probability that grave damage will accrue
1. Interlocutory/Interim Injunction to him in the future.
- Section 51(1) of the Specific Relief Act: Temporary Injunction are such • ii. Damages is not an adequate form of remedy.
as are to continue until a specified time, or until the further order of the court. • iii. The court must take into consideration the
They may be granted at any period of a suit, and are regulated by the law cost for the defendant in preventing or
relating to civil procedure mitigating the loss suffered.
- Principles in granting a temporary injunction as in American Cyanamid Co • iv. The defendant must have known exactly
v Ethicon Ltd, whether there is a serious question to be tried, that is, that what he has to do.
the claim is not frivolous and vexatious. If there is a serious question to be o 2. Restraining injunction
tried, the court will consider whether, based on the balance of convenience, § A remedy in the form of an order of the court that
where the justice of the case lies. prohibits a party from doing or continuing to do a
- Affirmed in Keet Gerald Francis Noel John v Mohd Noor Abdullah, the particular act.
court must: § It can be granted in the form of a perpetual injunction as
o Assure that there is a serious question to be tried under Section 52 as the final settlement of the suit to
o Consider where the justice of the case lies, by weighing the harm restrain a party, or a temporary injunction as under
that the injunction would produce by its grant against the harm that Section 51(1)
would result from its refusal (balance of convenience) § Case: Azman bin Mohd Yussof v Vasaga Sdn Bhd,
- Other considerations: the Court allowed the plaintiffs’ application for an
o Case: Associated Tractors Sdn Bhd v Chan Boon Heng & injunction in restraining the defendant from operating a
Anor: disco and pub business on the grounds that the business
§ Duty of disclose disturbed their peace, tranquility and safety resulting
§ Undertaking as to damages from the loud music till late at night as well as the
§ Delay vibration of the buildings and others. The defendant had
§ Public interest claimed that the court should not have granted a
2. Perpetual Injunction prohibitory order which can cause serious losses to the
- Final determination of right defendant if there were other sufficient relief. It seemed
- Section 51(2) of the SRA: A perpetual injunction can only be granted by that the disturbance could not be compensated with
the decree made at the hearing and upon the merits of the suit; the money and there were other remedies besides putting a
defendant is thereby perpetually enjoined from the assertion of a right, or stop to the disturbance
from the commission of an act, which would be contrary to the rights of the When Injunction cannot be granted
plaintiff. - Section 54(a) to (k) of the SRA
- Two categories: - Section 54(f) of the SRA: An injunction cannot be granted to prevent the
o 1. Mandatory injunction breach of a contract which cannot be specifically enforced.
§ Section 53 of the SRA: When, to prevent the breach of o This is applicable in three circumstances:
an obligation, it is necessary to compel the performance § Section 20(1)(b): Where the particular contract is
of certain acts which the court is capable of enforcing, dependent on the personal qualification or volition of the
the court may in its discretion grant an injunction to parties
§ Section 20(1)(g): Where the performance of the contract - The court in Malaysia plays important roles in granting relief but the court
involves a continuous duty for a period of more than in Malaysia seems reluctant in granting the order for breach of contract as
three years it is a coercive remedy.
§ Where the case concerns an illegal agreement - The judge had to take various consideration to ensure that no parties suffer
o Case: Marble Terrazo Industries Sdn Bhd v Anggaran any harm more than it already is
Enterprise Sdn Bhd & Ors - Case: Horizon Film Entertainment Sdn Bhd & ORs v Mohamad Azlan
o Facts: The plaintiffs claimed that the defendants had verbally Norani & Anor
agreed to allow the plaintiffs to extract rocks material from certain - Facts: involved the application for interlocutory Injunction or Interim
land for a period of 20 years. Pending the outcome of the suit, the Injunction with respect to copyright infringement and repudiatory breach of
plaintiffs sought a temporary injunction to restrain the defendants contract disputes relating to movie film production. There was agreement
from allowing other parties to mine the land. made on 1 April 2019 between plaintiff and defendant for film entitled “The
o Held: The High Court held that no such injunction could not be Seventh Flower”. The agreement was terminated on 8 April 2019 where
granted by virtue of section 54(f) of the SRA due to the contract plaintiff claim that defendant breach it and vice versa. The defendant then
being not specifically enforceable under section 20(1)(g). entered into new agreement with another party
- Exception - Held: After all consideration had been made taking into account that the
o Section 55 of the SRA: where a contract comprises an affirmative movie film production is a largely commercial undertaking or venture with
agreement to do a certain act, coupled with a negative agreement, view of profit, damages would definitely be an adequate remedy. The
express or implied, not to do a certain act, the circumstance that plaintiff failed to show that damages would be difficult to assess. The judge
the court is unable to compel specific performance of the found that balance of convenience tilts in favor of not granting interim
affirmative agreement shall not preclude it from granting an injunction.
injunction to perform the negative agreement
o Case: Pertama Cabaret Nite Club Sdn Bhd v Roman Tam
o Facts: A contract was signed between the parties which provided
that the respondent had to perform in the appellant’s nightclub for
a specific number of times (affirmative agreement). It was inferred
from the agreement that the respondent was prohibited from
performing in any other nightclub in Kuala Lumpur during the
contract period (negative agreement). The respondent was in
breach of the agreement and the appellant sought an injunction to
restrain him. The application was rejected at the lower court.
o Held: However, at the Federal Court, it was held that where the
court is unable to compel specific performance of the affirmative
undertaking, it is not precluded from granting an injunction under
the negative undertaking where the appellant had not failed to
perform the contract so far as it is binding upon him.
Relationship between Injunction and Breach of Contract (Damages is not an
adequate remedies)
- One of the main requirement of granting relief injunction is that when breach
had occurred, money is not an adequate relief.
- There are however other relief that may be sought by plaintiff where money
is not an adequate relief such as an order for specific performance.

You might also like