Professional Documents
Culture Documents
Method Statement For Testing of Busduct
Method Statement For Testing of Busduct
TABLE OF CONTENTS
SCOPE 3
PURPOSE 3
DEFINITIONS 3
TOOLS AND EQUIPMENT 4
RESOURCES 4
RESPONSIBILITY 4
ACTIONS AND METHODS 5
QUALITY CONTROL 9
HEALTH, SAFETY AND ENVIRONMENT 9
REFERENCES 10
1. SCOPE
This Method Statement will serve as guideline in Testing of Busduct in Sevina Apartment Project
Contract Package - 02. With reference standard as per Electrical System Specification, Section
262500 “Enclosed Bus Assemblies”, made to ensure that the works will be carried out safely for
humans, equipment and materials throughout the Residential Apartments.
2. PURPOSE
The purpose of this Method Statement (MS) is to define the Testing Procedure for the Busduct
and to ensure that the work will be carried out in compliance to the Project Specification
requirements and conformity with approved drawings and applicable standards.
3. DEFINITIONS
5. RESOURCES
CONTRACTOR'S MANPOWER
ITEM STAFF QUANTITY
1 SITE ENGINEER 1
2 QUALITY CONTROL ENGINEER 1
3 SAFETY OFFICER 1
4 FOREMAN 1
5 ELECTRICAN 2
6 ELECTRICAN HELPER 3
7 WAREHOUSEMAN 1
6. RESPONSIBILITY
6.1. Project Manager is responsible for managing the execution of all works within this
project in accordance with the contract requirements.
6.2.Construction Manager shall lead instruct and supervise all operational aspects of site
construction and ensures that all operations personnel achieve planned production in
conformity with safety and quality.
6.3. MEP Manager shall lead, instruct and supervise all MEP contractors' operational
aspects of site construction and ensures that all MEP operations personnel achieve
planned production in conformity with safety and quality.
6.4. Project In-Charge/Project Superintendent shall study and review all necessary
documents for the installation works in the area and to include the technical scope of
works, specifications, bill of quantities, plan the milestone dates and construction
procedure in support to his electrical supervisor. Monitor the implementation of work
plan and on schedule and coordinate with QC personnel for all non-conformances report
and undertake remedial action.
6.5. QC Manager leads the QC team (team of engineers and inspectors and is responsible
for the works complying with the Design and Specifications. He controls the Change and
Non-Conformance processes. His responsibilities include On and Off-site inspection,
monitoring and reporting on testing, administering non-conformances through his
Document No. CP02-CMD-006 Rev. 0 Page 4
7F Arthaland Century Pacific Tower, 5th Avenue Corner 30th Street
Bonifacio Global City, 1634 Taguig City, Philippines
Tel # (632) 8 403 6910 | www.arthaland.com
control register, reviewing all Quality Plan & Procedures, Method Statement &
Inspection Test Plan.
6.6. QC Engineer/Inspector shall be coordinating with Project In-Charge (PIC)/Project
Superintendent on all quality issues and responsible for the verification and inspection
works and ensures that the work is performed and properly documented in accordance
with project specifications and project standards.
6.7. Environmental Manager shall be responsible for managing and monitoring of
environmental compliances specially noise, dust control and disposal of waste during
chipping works.
6.8. MEP Engineer responsible for the On and Off-site coordination with Consultants when
there is a query for specifications, drawings and method of work for MEP activities. He
shall ensure that the approved work procedure will be carried out.
6.9. Site Engineer shall study and review all necessary documents for the works in the area
to include specifications, bill of quantities and construction procedures. He shall monitor
the availability of materials in accordance with the schedules and construction analysis.
6.10. Electrical Foreman shall be directly responsible for the work supervision at site during
installation following all schedules and specific work activities, ensuring that the works
are performed in accordance with project requirement and based on the latest
approved For Construction Drawings (FCD).
6.11. Safety Manager shall manage his safety officers, conduct safety meetings, audits, and
led inspections to ensure work is done in accordance with project safety procedure and
guidelines. Evaluate performance, identify corrective action, and implement follow up
assessments.
6.12. Safety Officer shall be responsible in monitoring safety aspects ensuring that work is
done in accordance with project safety procedure and guidelines. He shall discuss to the
workers the characteristics of related materials and status of work area and ensure all
personnel have undergone safety orientation and toolbox meeting giving reminders as
an additional point to avoid injury and make incident free environment.
6.13. Warehouseman shall be responsible in material handling from warehouse to site.
Responsibilities include material preservation, safe keeping and monitoring of stocks.
6.14.ALCO (Arthaland Personnel) serves as the Consultant representing the Client.
6.15. Foreman shall be directly responsible for the work supervision at site during
installation following all schedules and specific work activities, ensuring that the works
are performed in accordance with project requirements and based on the latest
approved For Construction Drawing (FCD).
6.16. Testing Engineer a representative from the vendor and shall be responsible in testing
the ACS installed at site with the help of the subcontractor.
Figure 1
vendor drawings. Ensure such as the phase sequence of busway corresponds with other
associated equipment such as switchgear and transformer.
7.3.5 Connect the battery box at one end of t the busway:
- 0V to earth
- 4.5V to phase A
- 9V to phase B
- 13.5V to phase C
7.3.6 Using a multimeter, check if at the other end of the busway the voltages for each phase
are correct.
Figure 2
Document No. CP02-CMD-006 Rev. 0 Page 7
7F Arthaland Century Pacific Tower, 5th Avenue Corner 30th Street
Bonifacio Global City, 1634 Taguig City, Philippines
Tel # (632) 8 403 6910 | www.arthaland.com
Figure 3
7.5.9 Before beginning the test, ensure that the Hi-Pot main switch is in off position and that
the voltage control switch is turned to zero position.
7.5.10 Connect the hi-pot safety ground stud to a good electrical ground. Check that the metal
frame of the busway is connected to ground.
7.5.11 Connect the line cable of the hi-pot test set to the desired phase of the busway under
test. Make sure that the connections are tight and without any sharp edges. The line
cable should be short and supported on its entire length so that it is not touching any
grounded materials.
7.5.12 Switch on the hi-pot and select the desired range for the test voltage. The test voltage
value should be as per manufacturer recommendation and should be applied for one
minute.
7.5.13 The AC hi-Pot test is a “go or no go” test. If the hi-pot test voltage is held for one minute
without any failure of the busway insulation, the busway is considered to have passed
the test.
8 QUALITY CONTROL
8.1 All inspection shall be coordinated with ALCO by Inspection and Work Request form.
8.2 Contractor’s QC Engineer shall be responsible to conduct all required inspections,
documentations and to ensure that all applicable requirements, codes, and standards
are compiled prior to ALCO’s inspection.
8.3 All inspections and testing to be perform shall be conducted in accordance with the
approved Inspection Test Plan (ITP).
8.4 Calibration certificate of test instrument used in testing continuity, insulation test,
voltage test and illumination test will be checked before commencement of testing
work for accuracy of test results.
8.5 Renew the calibration certificate if found to be expired prior to the testing of lighting
and small power system.
9.1.1 Safety of all personnel and equipment is the highest priority of the Contractor
during the construction and execution of works.
9.2 Personnel Protective Equipment
9.2.1 Safety Helmet
9.2.2 Safety Goggles
9.2.3 Safety Footwear (steel toes)
9.2.4 Safety Gloves (for material handling)
9.2.5 Safety Vest
9.2.6 Full Body Harness
PERSONAL PROTECTIVE EQUIPMENT
HEAD FOOT HAND REFLECTOR EYE HEARING CHEMICAL FALL
PROTECTION PROTECTION PROTECTION VEST PROTECTION PROTECTION SUIT PROTECTION
9.3.2 Safety Tool Box Talk shall brief the task / subject and shall be given in
languages understandable by multinational workforce.
Document No. CP02-CMD-006 Rev. 0 Page 9
7F Arthaland Century Pacific Tower, 5th Avenue Corner 30th Street
Bonifacio Global City, 1634 Taguig City, Philippines
Tel # (632) 8 403 6910 | www.arthaland.com
9.3.3 Safety Tool Box Talk attendance shall be recorded on a sheet and signed by
attendees
9.7 Housekeeping
Housekeeping shall be maintained by all personnel working at site. Housekeeping for
fabrication and installation shall be as per project safety plan.
9.8 Signage
All necessary safety warning and caution signs shall be displayed at work locations.
8 REFERENCES
https://www.scribd.com/document/327805356/Busduct-test-procedure