Professional Documents
Culture Documents
PMP Post Test - 50 Questions
PMP Post Test - 50 Questions
PMP Post Test - 50 Questions
Marks - ________ / 50
Q.
Question Content Option1 Option2 Option3 Option4 Answer
No.
An input to A tool for A technique for
A make or buy analysis is used as An input for
1 solicitation solicitation procurement
___________. solicitation
planning planning planning
Consult the
In your role as a contract project manager, you
intellectual
are asked to review the plans and satisfactions
Write the article Write the article property clause of
for a new product for company A.
but leverage only and name your contract and
Representatives of technical publication have
2 high level Write the article company A as a consult your
asked you to write a paper on industry and
information from reference in employer prior to
product trends in the same field in which
company A. your paper leveraging any
company A operates. How should you
information from
proceed?
company A
Which of the following methods is least likely
Project Office Project office Project team Formal project
3 to be used for explaining project planning
Memo directive meeting report
guidelines to the team?
"A Project Manager is at the project kick-off
meeting. He confidently states the vision and
4 Hierarchal Authoritarian Charismatic Associative
mission for the project. This PM is exhibiting
the following leadership style:
The expected accuracy level of estimates
5 during the initiation phase of project should 25% to +75% 10% to +25% 35%to +75% 10%to +10%
be:
__________ , a well-known motivational
theorist , stated people can’t ascend to the
6 Maslow McGregor Herzberg Aldelfers
next level of needs until the levels below have
been fulfilled
_________ must be measured regularly to Stakeholder Project Schedule
7 Cost and schedule
identify variance from the plan. requirements performance progress
____ involves clarification and mutual
agreement on the structure and requirements Evaluation Contract
8 Screening System Weighting System
of the contract prior to the signing of the Criteria Negotiation
contract
the contract
money must be there must be an
“For Consideration” in contract management the contract must must be agreed
9 paid from one exchange of
means ____________. be signed to buy both
party to another things
parties
A fixed-price-plus-incentive-fee (FPI) contract
has a target cost of $130,000, a target profit of
$15,000, a target price of $145,000, a ceiling
10 $10,000 $15,000 $0 $5,000
price of $160,000, and a share ratio of 80/20.
The actual cost of the project was $150,000.
How much profit does the seller make?
1
Cognitel - PMP Preparatory Classroom Training Post Test – 50 Questions (60 Minutes)
1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000
Assumed is a discount rate of 5 % per year.
Looking at the present values of these projects'
revenues in the first 3 years, what is true?
2
Cognitel - PMP Preparatory Classroom Training Post Test – 50 Questions (60 Minutes)
A contract where the buyer reimburses the
Schedule and Cost Plus
seller for the cost incurred by the seller, and Cost Plus Cost Plus Fixed
21 Material Percentage of
also provides for a fixed amount of profit is Incentive Fee Fee
Contract cost
also called:
A contractor is working on a fixed price
contract that calls for a single, lump sum
payment upon satisfactory completion of the
contract. About halfway through the contract, Making no
Negotiating a
the contractor project manager informs their Starting partial payments
Paying for work change to the
contract administrator that financial problems payments for because it would
22 accomplished to payment
are making it difficult for them to pay their work violate the
date. conditions in the
employees and subcontractors. The contractor accomplished. conditions of the
contract
asks for a partial payment for work contract
accomplished. Which of the following actions
by the buyer is most likely to cause problems
for the project?
A control chart for a major project process The process No action is This is consider
The process is
shows that seven consecutive data points of average is moving required because abnormal
out of control
23 the nine sample averages are above the to the upper the points are still behaviour and
and should be
process average within the control limits. What values and needs within the control should be
investigated.
is indicated by the phenomenon? to be corrected. limits. investigated
3
Cognitel - PMP Preparatory Classroom Training Post Test – 50 Questions (60 Minutes)
When team
When major
members are When formal
A strong matrix problems delay
accountable to training plans
33 A key barrier to team development is: management the project
both functional cannot be
structure completion date
and project implemented.
or budget targets
managers.
Protect the Make sure they Make sure that
A key role of the project manager during relationship Make sure their get all risks everyone receives
34
negotiations is to _____________ between buyer side wins assigned to the a communication
and seller other side plan
Funding for staff Shared work Commitment Removal of
35 A mandatory prerequisite for team building is: development ethics among from top level troublesome
activities team members management individuals
A matrix organization begins a new project.
Project manager knows that the team is more
Scope Resource
36 responsive to their functional managers than Project plan Project charter
statement management plan
to PM. To overcome this, PM decides to
prepare
A modification of a logical relationship that
37 allows an acceleration of the successor task is Lead Lag Float Buffer
represented by:
data not
A negative cost variance for a period indicates sufficient to
38 cost underrun cost overrun scope creep in
______________. predict the cost
performance
A network diagram that uses nodes to
represent activities and arrows to show the
39 AOA AON ADM GERT
activity dependencies and allows no loops is
called:
She should check
A new project manager has just been assigned She should first
She should the project plan
a project that is in progress. The project is two show sympathy
She should first initially contact for contingencies
weeks behind schedule. The team members with the current
revise the Gantt the steering concerning
40 are about to be distributed to another project team and delay
chart with new committee and resources and
based on original Schedule estimates provided decision making
timelines. begin with a new talk to the
by the functional manager. What is the FIRST for another
team. functional
step the project manager should take? week.
manager
It will take the
The company
It will take the project one and
will receive the
project one and The project will half years to
A project has payback period of 1 and a half of profits for the
41 half years before be completed in cover the
years. What does that mean? first one and
they start to incur less than 2 years investment and
half years of the
costs. start generating
project.
profits
A project has several teams. Team C has
missed several deadlines in the past. This has project project manager
manager of team project manager
42 caused team D to have to crash the critical manager and and the team C
C alone
path several times. As the project leader for management. leader.
team D, you should meet with the:
A project management professional can Forecasted final
Technical
compare earned value performance data to all Critical path Risk mitigation costs and
43 performance
of the following project management tools analysis plans schedule
metrics
EXCEPT: estimates
Project Scope
Project scope Management
The processes,
includes the includes the
tools, and Product scope
work that must processes
techniques used includes features
A project management team discusses what be done in required to
by project scope and functions that
44 scope means in a project. All of the following order to deliver ensure that the
management are are to be included
statements are true except : a product with project includes
mostly depending in a product or
the specified all the work
on the application services.
features and required and only
area.
functions the work
required.
4
Cognitel - PMP Preparatory Classroom Training Post Test – 50 Questions (60 Minutes)
A project management team has
subcontracted work to a service company. The
Control Contract Contract
45 process of ensuring that this service company's Staff Acquisition
Procurements Closeout Negotiation
performance meets contractual requirements
is called:
A process can be
A project management team is evaluating the Normal process Special causes are
Special causes optimized to limit
causes that might contribute to unsatisfactory variation is easier to predict
46 are unusual the bandwidth of
performance and quality. Which of the attributable to and handle than
events variations due to
following statements is not true? random causes. random causes
random causes.
A project manager believes that modifying the Call a meeting Change the
Change the scope Prepare a
47 scope of the project may provide added value of the change project’s
baseline variance report
for the customer. The project manager should: control board objectives
Refrain from
Provide offering or
A project manager disclosed some crucial Maintain and
Prevent conflict of accurate and accepting
48 information to a prospective seller. Which code satisfy the scope
interest truthful inappropriate
of professional conduct did he violate? and objectives
representations payments, gifts
etc.
Weak Matrix
A project Manager has to manage conflict in an Structure with Low position in
Roles that are Work pressure
49 organization. All the following could be sources multiple the organization
not well defined and high stress.
of conflict in an organization except: managers to hierarchy
report to.
A project manager is working with quality Determining if the Determining
Evaluating quality
professionals in the quality assurance phase of right quality what quality
50 Quality control against the
the project. Which of the following activities is standard are standard should
standard.
being performed? being used be used.