Professional Documents
Culture Documents
200 PMP Mock Questions
200 PMP Mock Questions
BY
TABLE OF CONTENTS
1. Your agile project team is struggling to complete work within the iteration
time box. What approach should you take to address this issue?
C) Collaborate with the team to identify and address the root cause of the issue
2. Your agile project team has identified a major risk that could impact the
project timeline. What action should you take to mitigate the risk?
3. The product owner on your agile project team has requested a significant
change in requirements during iteration planning. How should you respond to
this change request?
B) Negotiate with the product owner to reduce the scope of the change request
C) Work with the team to evaluate the impact of the change request on the project
D) Deny the change request and proceed with the iteration as planned
4. Your agile project team is having difficulty breaking down user stories into
smaller pieces. What action should you take to address this challenge?
A) Work with the team to identify and address the root cause of the issue
B) Accept the user stories as they are and proceed with the iteration
5. The daily stand-up meetings on your agile project team have become
unproductive. What can you do to improve their effectiveness?
A) End the daily stand-up meetings as they are not adding value
B) Reformat the daily stand-up meetings to make them more interactive and
engaging
D) Assign a facilitator to ensure that the daily stand-up meetings are productive
A) Work with the product owner to establish a process for managing changes to
requirements
7. Your agile project team is facing a technical issue that requires expertise that
is not available within the team. What can you do to address this issue?
8. Your agile project team is having difficulty achieving the desired level of
quality in the product. How can you address this quality issue?
B) Work with the team to identify the root cause of the quality issue and address it
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 5
9. The product owner on your agile project team has requested a new feature
that is not in scope for the upcoming release. What can you do to handle this
request?
A) Accept the change request and include the new feature in the release
B) Deny the change request and proceed with the release as planned
C) Work with the product owner to evaluate the impact of the new
10. Your agile project team is struggling to meet the project deadline. What can
you do to address this issue?
C) Collaborate with the team to identify and address the root cause of the issue
11. The agile team is facing issues in delivering the product on time. What
should the Scrum Master do to address this issue?
12. During the sprint review meeting, the stakeholders provide feedback that
requires major changes to the product. What should the product owner do?
B) Discuss the feedback with the team and identify a way to incorporate it in the
product
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 6
13. An agile team is not meeting its sprint goals consistently. What should the
Scrum Master do?
C) Work with the team to identify the root cause of the issue and develop a plan to
address it
D) Increase the sprint duration to give the team more time to meet the goals
14. During the sprint planning meeting, the team identifies that a critical team
member will be unavailable for the sprint duration. What should the team do?
C) Reduce the scope of the sprint to accommodate the team member's absence
D) Collaborate with the team member to identify a way to complete their tasks
before their absence
15. The product owner has added a new requirement to the product backlog in
the middle of the sprint. What should the team do?
B) Add the requirement to the current sprint without adjusting the sprint goal
D) Delay the product release until the new requirement can be addressed
16. During the daily Scrum meeting, a team member expresses that they are
struggling with their assigned task. What should the team do?
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 7
A) Ignore the team member's concerns and continue with the current plan
B) Collaborate with the team member to identify a way to complete the task
D) Reduce the scope of the sprint to accommodate the team member's struggles
17. The team has identified a major issue that requires a change in the project
plan. What should the team do?
18. During the sprint review meeting, the stakeholders express their
dissatisfaction with the product. What should the team do?
19. The team is facing issues in completing their tasks due to external factors
beyond their control. What should the Scrum Master do?
C) Work with the team to identify a way to adapt to the external factors and
complete their tasks
20. You are leading an agile project, and the team has been working on an
important feature for several weeks. During the sprint review, the stakeholders
provide feedback that the feature is not meeting their expectations. What
should you do first?
a) Tell the stakeholders that the team will fix the issue in the next sprint.
b) Schedule a meeting with the stakeholders to discuss the feedback and identify
the root cause of the problem.
c) Reassign team members to work on the feature full time until the issue is
resolved.
d) Cancel the current sprint and start a new one focused solely on fixing the feature.
B) Sprint planning.
C) Retrospectives.
D) Backlog grooming.
early value to the customer. Which agile practice can the project manager use
to achieve this goal?
D) Burn-down charts.
24. A project manager is leading an agile team that is in the early stages of the
project. The team is struggling to define the acceptance criteria for user stories.
Which agile practice can the project manager use to facilitate the creation of
clear and measurable acceptance criteria?
A) Story mapping.
B) Refactoring.
C) Pair programming.
ANSWERS
1. Answer: C) Collaborate with the team to identify and address the root cause of
the issue.
Rationale: As a project manager, the best approach to address the issue of the Agile
project team struggling to complete work within the iteration time box is to work
with the team to identify and address the root cause of the issue. This can be done
by collaborating with the team to evaluate their current processes, identifying
bottlenecks and areas for improvement, and implementing changes to help the team
complete work within the iteration time box.
Rationale: It is important to take action to mitigate the risk identified by the Agile
project team. As the project manager, the best course of action is to work with the
team to develop a risk mitigation plan that identifies the potential impact of the risk
on the project, and outlines steps to be taken to minimize its impact.
3. Answer: C) Work with the team to evaluate the impact of the change request on
the project.
4. Answer: A) Work with the team to identify and address the root cause of the issue.
Rationale: Breaking down user stories into smaller pieces is an important aspect of
Agile project management. If the team is having difficulty in doing so, the project
manager should work with the team to identify and address the root cause of the
issue, rather than accepting the user stories as they are or escalating the issue to
senior management.
5. Answer: B) Reformat the daily stand-up meetings to make them more interactive
and engaging.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 11
Rationale: The daily stand-up meetings are an important part of Agile project
management. If they have become unproductive, it is important to take action to
improve their effectiveness. As the project manager, you can reformat the daily
stand-up meetings to make them more interactive and engaging, which will help to
improve their effectiveness.
6. Answer: A) Work with the product owner to establish a process for managing
changes to requirements.
Rationale: Frequent changes in requirements can impact the project schedule and
scope. As the project manager, it is important to work with the product owner to
establish a process for managing changes to requirements. This can help to ensure
that changes are evaluated and implemented in a way that minimizes their impact
on the project.
Rationale: When facing a technical issue that requires expertise that is not available
within the team, the project manager should consider hiring an external consultant
to address the issue. This will help to ensure that the issue is addressed in a timely
and effective manner.
8. Answer: B) Work with the team to identify the root cause of the quality issue and
address it.
9. Answer: B) Deny the change request and proceed with the release as planned.
Rationale: When a new feature is requested that is not in scope for the upcoming
release, the project manager should evaluate the impact of the new feature on the
release and determine whether it is feasible to incorporate the change into the
release. If it
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 12
10. Answer: C) Collaborate with the team to identify and address the root cause of
the issue.
11. Answer: B) Review the team's process and identify areas for improvement
Rationale: As the Scrum Master, it's important to continuously evaluate the team's
processes and identify areas for improvement. Assigning more work, increasing
sprint duration, or reducing scope may not address the root cause of the issue.
12. Answer: B) Discuss the feedback with the team and identify a way to incorporate
it in the product
13. Answer: C) Work with the team to identify the root cause of the issue and develop
a plan to address it
Rationale: As the Scrum Master, it's important to work with the team to identify the
root cause of the issue and develop a plan to address it. Blaming the team or
assigning more work may not address the root cause of the issue.
14. Answer: B) Reassign the team member's tasks to other team members
Rationale: In Agile, it's important to be flexible. Therefore, the team should reassign
the team member's tasks to other team members to ensure the sprint can be
completed without delay.
15. Answer: C) Collaborate with the product owner to identify a way to incorporate
the requirement in the product
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 13
16. Answer: B) Collaborate with the team member to identify a way to complete the
task
Rationale: In Agile, the team works together to complete tasks. Therefore, the team
should collaborate with the team member to identify a way to complete the task.
17. Answer: C) Collaborate to identify a solution and update the project plan
accordingly
19. Answer: C) Work with the team to identify a way to adapt to the external factors
and complete their tasks
20. Answer: B) Schedule a meeting with the stakeholders to discuss the feedback
and identify the root cause of the problem.
Rationale: In Agile, feedback from stakeholders is essential. Therefore, the first step
should be to schedule a meeting with the stakeholders to discuss the feedback and
identify the root cause of the problem before determining the next steps.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 14
Rationale: Retrospectives are Agile practices that allow the team to reflect on their
performance and identify areas for improvement. By conducting retrospectives, the
project manager can address the challenges in self-organization and decision-
making, promoting continuous improvement within the team.
Rationale: The Three Amigos meeting is an Agile practice that involves collaboration
among the product owner, the development team, and the QA/tester. This meeting
helps to ensure a shared understanding of the user stories and facilitates the
creation of clear and measurable acceptance criteria.
1. During the project planning phase, the project manager realized that a key
stakeholder was not included in the project charter. What should the project
manager do to address this?
2. The project manager is responsible for creating the project charter. Which of
the following should be included in the project charter?
3. During project execution, the project manager realizes that the project is not
progressing according to the plan. What should the project manager do?
c) Identify the root cause of the issue and take corrective action
4. The project manager needs to obtain approval from the project sponsor for a
change request. What should the project manager do first?
5. During the project monitoring and controlling phase, the project manager
realizes that the project is behind schedule. What should the project manager
do?
b) Identify the root cause of the delay and take corrective action
d) Cut down the project scope to make up for the lost time
6. During the project closing phase, the project manager realizes that a key
deliverable was not completed. What should the project manager do?
7. During the project planning phase, the project manager identifies a risk that
may impact the project budget. What should the project manager do?
8. The project manager needs to identify the stakeholders for the project. What
should the project manager do first?
9. The project manager is developing the project scope statement. What should
be included in the project scope statement?
10. During the project execution phase, the project manager realizes that the
project team is not following the project plan. What should the project manager
do?
11. The project manager needs to identify the project constraints. What should
the project manager do first?
12. During the project planning phase, the project manager identifies a risk that
may impact the project schedule. What should the project manager do?
13. The project manager needs to develop the project budget. What should the
project manager do first?
14. The project manager needs to identify the project assumptions. What should
the project manager do first?
15. During the project planning phase, the project manager realizes that a key
stakeholder was not included in the stakeholder management plan. What
should the project manager do to address this?
ANSWERS
1. Answer: A) Update the project charter to include the stakeholder
Rationale: The project charter is a high-level document that outlines the purpose,
objectives, and scope of the project. It also includes information on the project
stakeholders, roles and responsibilities, and high-level risks.
3. Answer: C) Identify the root cause of the issue and take corrective action
5. Answer: B) Identify the root cause of the delay and take corrective action
Rationale: If a project is behind schedule, the project manager should identify the
root cause of the delay and take corrective action to get the project back on track.
Developing a new project schedule, continuing with the current schedule, or cutting
down the project scope may not address the underlying issue.
6. Answer: C) Develop a plan to complete the deliverable after the project is closed
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 20
Rationale: If a key deliverable was not completed during the project closing phase,
the project manager should develop a plan to complete the deliverable after the
project is closed. Completing the deliverable before closing the project or assigning
the incomplete deliverable to a different project team may not be feasible.
Rationale: If a risk is identified that may impact the project budget, the project
manager should develop a contingency plan to address the risk. Ignoring the risk or
requesting more funds to cover the risk may not be feasible.
Rationale: The project scope statement outlines the project objectives, deliverables,
and boundaries. It also includes any constraints and assumptions that may impact
the project.
10. Answer: C) Take corrective action to ensure the team follows the plan
Rationale: If the project team is not following the project plan, the project manager
should take corrective action to ensure that the team follows the plan. Firing the
team members and hiring new ones may not be necessary or feasible.
Rationale: The project charter provides information about the project objectives,
scope, and constraints. Constraints are limitations that can impact the project in
terms of scope, schedule, budget, or quality. Therefore, reviewing the project
charter is the first step in identifying project constraints.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 21
Rationale: The project charter provides information about the project objectives,
scope, stakeholders, and high-level budget. Therefore, reviewing the project charter
is the first step in developing the project budget, as it provides an understanding of
what is included in the project and what needs to be budgeted for.
Rationale: The project charter provides information about the project objectives,
scope, and constraints. Assumptions are factors that are considered to be true, real,
or certain for the purpose of planning the project but are not guaranteed to be
correct. Therefore, reviewing the project charter is the first step in identifying
project assumptions.
Rationale: The stakeholder management plan is a key document that outlines the
approach to managing stakeholders and their communication needs. If a key
stakeholder is not included in the plan, the project manager should update the
stakeholder management plan to include them. This will ensure that the stakeholder
is engaged and their needs are considered throughout the project.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 22
1. Imagine you are the project manager and have identified a stakeholder who
was not included in the scope statement. Which of the following actions would
be appropriate to address this issue?
2. As a project manager, you have completed the scope definition process and
need to ensure that the project team understands the scope. What would be
your next step?
3. During project execution, the project manager realizes that the project scope
is not clear and is causing confusion among team members. What action should
the project manager take to address this issue?
4. The project manager needs to identify the project deliverables. What would
be an appropriate first step?
5. As a project manager, you need to ensure that the project deliverables meet
the quality standards. What would be your next step?
6. During the project planning phase, the project manager realizes that the
project scope is too broad and needs to be narrowed down. What action should
the project manager take to address this issue?
7. The project manager needs to identify the project constraints. What would
be an appropriate first step?
8. During project execution, the project manager realizes that a deliverable has
been missed in the scope statement. What action should the project manager
take to address this issue?
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 24
9. The project manager needs to ensure that all project deliverables are
completed on time. What would be an appropriate first step?
10. As a project manager, you need to ensure that the project deliverables meet
the customer's expectations. What would be your next step?
11. During the project planning phase, the project manager identifies a risk that
may impact the project scope. What action should the project manager take to
address this issue?
12. The project manager needs to identify the project assumptions. What would
be an appropriate first step?
13. The project manager needs to develop the project budget. Which of the
following should the project manager do first to ensure an accurate budget?
14. The project manager needs to identify the project assumptions. What is the
best way for the project manager to identify these assumptions?
15. The project manager is reviewing the project scope statement and realizes
that a deliverable was not included. What is the best course of action for the
project manager?
D) Wait for the sponsor to request the deliverable before adding it to the scope
statement.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 26
ANSWERS
1. Answer: A) Update the scope statement to include the stakeholder
Rationale: To address the issue of a stakeholder who was not included in the scope
statement, the appropriate action would be to update the scope statement to include
the stakeholder. This ensures that the project team has a clear understanding of the
stakeholder's needs and expectations.
Rationale: After completing the scope definition process, the next step would be to
communicate the scope statement to the project team. This ensures that the team
understands the project scope and can work towards achieving the project
objectives.
Rationale: If the project manager realizes during project execution that the project
scope is not clear and is causing confusion among team members, the appropriate
action would be to develop a new scope statement. This ensures that the project
team has a clear understanding of the project scope and can work towards achieving
the project objectives.
Rationale: The first step in identifying the project deliverables would be to review
the project charter. The project charter provides an overview of the project and
helps identify the high-level deliverables.
Rationale: After defining the project scope, the next step to ensure that the project
deliverables meet the quality standards would be to develop a quality management
plan. This plan outlines the processes and procedures that will be used to ensure
that the project deliverables meet the required quality standards.
Rationale: If the project manager realizes during the project planning phase that
the project scope is too broad and needs to be narrowed down, the appropriate
action would be to develop a new scope statement. This ensures that the project
team has a clear understanding of the project scope and can work towards achieving
the project objectives.
Rationale: The first step in identifying the project constraints would be to review
the project charter. The project charter provides an overview of the project and
helps identify the high-level constraints.
Rationale: The first step in ensuring that all project deliverables are completed on
time would be to develop a project schedule. The project schedule outlines the
timeline for completing all project deliverables.
Rationale: After defining the project scope, the next step to ensure that the project
deliverables meet the customer's expectations would be to develop a quality
management plan. This plan outlines the processes and procedures that will be used
to ensure that the project deliverables meet the customer's expectations.
scope. The best course of action for the project manager would be to develop a
contingency plan to address the risk and minimize its impact on the project scope.
14. Answer: A) Review the project charter and previous similar projects
Rationale: A project scope statement defines the project's goals, deliverables, and
boundaries. In this scenario, the project manager has identified a deliverable that
was not included in the project scope statement. The best course of action for the
project manager would be to add the deliverable to the project scope statement to
ensure that it is included in the project plan and that all stakeholders are aware of
it.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 29
C) The activity that can happen at the same time as the current activity
D) The activity that has the same duration as the current activity
2. As a project manager, you are trying to determine the critical path of the
project schedule. Which of the following activities would be considered critical?
3. During project execution, the project manager realizes that the project
schedule is behind schedule. What is the best course of action for the project
manager?
4. The project manager needs to determine the earliest start time for an
activity. Which of the following is an example of a forward pass calculation?
A) Subtracting the duration of the activity from the latest finish time
C) Subtracting the duration of the activity from the earliest finish time
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 30
6. The project manager needs to determine the latest start time for an activity.
Which of the following is an example of a backward pass calculation?
A) Subtracting the duration of the activity from the latest finish time
C) Subtracting the duration of the activity from the earliest finish time
A) It represents the amount of time an activity can be delayed without delaying the
project finish date
B) It represents the amount of time an activity can be delayed without delaying the
project start date
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 31
9. The project manager needs to determine the critical path of the project
schedule. Which of the following is true about the critical path?
10. A project has a duration of 90 days and a budget of $500,000. The project
manager determines that the earned value of the project at the end of the first
month is $50,000. What is the schedule performance index (SPI) for the
project?
A) 0.56
B) 1.11
C) 0.90
D) 1.25
11. A project has a duration of 6 months and a budget of $500,000. At the end
of the first month, the project manager determines that the actual cost of the
project is $75,000 and the earned value of the project is $80,000. What is the
cost performance index (CPI) for the project?
A) 1.07
B) 0.94
C) 1.20
D) 0.80
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 32
12. A project has a duration of 100 days and a budget of $200,000. At the end of
day 60, the project manager determines that the actual cost of the project is
$120,000 and the earned value of the project is $140,000. What is the estimate
at completion (EAC) for the project assuming a linear projection?
A) $216,000
B) $220,000
C) $240,000
D) $260,000
13. A project has a duration of 12 months and a budget of $1,000,000. At the end
of the first quarter, the project manager determines that the actual cost of the
project is $250,000 and the earned value of the project is $300,000. What is
the schedule variance (SV) for the project?
A) $50,000
B) $60,000
C) $100,000
D) $150,000
14. The budget at completion for a project is $200,000. The planned value of
the project is $150,000, and the actual cost of the project is $175,000. What is
the cost variance (CV) of the project?
16. A project has a planned duration of 12 weeks and a budget of $120,000. After
6 weeks, the project is 50% complete, and the actual costs incurred are
$60,000. What is the estimate at completion (EAC) for the project if the current
performance continues?
A) $120,000
B) $140,000
C) $160,000
D) $180,000
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 34
ANSWERS
1. Answer: B) The activity that comes before the current activity
2. Answer: D) Activities that, if delayed, would impact the project finish date
Rationale: The critical path is the longest sequence of activities in a project schedule
that must be completed on time to ensure that the project is completed on time.
Therefore, activities that, if delayed, would impact the project finish date are
considered critical.
Rationale: Crashing the schedule involves adding resources to the critical path
activities to speed up their completion. This is the best course of action when the
project schedule is behind schedule and there is a need to catch up.
4. Answer: B) Adding the duration of the activity to the earliest start time
Rationale: The forward pass calculation is used to determine the earliest start and
finish times for each activity in a project schedule. To calculate the earliest start
time for an activity, the duration of the previous activity is added to its earliest start
time.
Rationale: The schedule baseline is the approved project schedule, against which
actual project performance can be measured. It represents the original approved
project schedule and is used as a reference point to track changes and performance.
6. Answer: A) Subtracting the duration of the activity from the latest finish time
Rationale: The backward pass calculation is used to determine the latest start and
finish times for each activity in a project schedule. To calculate the latest start time
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 35
for an activity, the duration of the activity is subtracted from the latest finish time
of its successor activity.
Rationale: Float, also known as slack, represents the amount of time an activity can
be delayed without delaying the project finish date. Activities on the critical path
have zero float, while activities not on the critical path have positive float.
Rationale: The critical path is the longest path through the network diagram, which
includes all activities with zero float or slack. Activities on the critical path must be
completed on time to ensure that the project is completed on time.
10. Answer: C) The schedule performance index (SPI) is earned value divided by
planned value. SPI = EV / PV. In this case, SPI = $50,000 / ($500,000/3) = 0.90.
Rationale: The cost performance index (CPI) is earned value divided by actual cost.
CPI = EV / AC. In this case, CPI = $80,000 / $75,000 = 1.07.
Rationale: The schedule variance (SV) is earned value minus planned value. SV = EV
- PV. In this case, SV = $300,000 - ($1,000,000/4) = $60,000.
Rationale: Cost Variance (CV) is calculated as Earned Value (EV) minus Actual Cost
(AC). In this case, EV = $150,000 and AC = $175,000, so CV = $150,000 - $175,000
= -$25,000. A negative CV indicates that the project is over budget.
Rationale: Schedule Variance (SV) is calculated as Earned Value (EV) minus Planned
Value (PV). In this case, PV is 50% of the planned budget, or $100,000. EV is 50%
of the budget, or $100,000. Therefore, SV = $100,000 - $100,000 = $0. The project
is on schedule, with 0 days of variance.
A) Analogous estimating
B) Bottom-up estimating
C) Parametric estimating
D) Three-point estimating
A) Cost aggregation
C) Forecasting
D) Variance analysis
A) Analogous estimating
B) Bottom-up estimating
C) Parametric estimating
D) Three-point estimating
A) Analogous estimating
B) Bottom-up estimating
C) Parametric estimating
D) Three-point estimating
A) Cost aggregation
C) Forecasting
D) Variance analysis
A) Analogous estimating
B) Bottom-up estimating
C) Parametric estimating
D) Top-down estimating
7. The project manager is initiating a new project and is developing the Project
Management Plan. One of the key components of the plan is cost management.
Which process is specifically responsible for defining how costs will be
estimated, budgeted, managed, and controlled throughout the project?
A) Estimate Costs
B) Determine Budget
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 39
D) Control Costs
A) Analogous Estimating
B) Bottom-up Estimating
C) Parametric Estimating
D) Three-point Estimating
9. The project manager is in the process of developing the budget for a software
development project. The project manager wants to set aside a specific amount
of money to address known risks and uncertainties. Which technique should
the project manager use to estimate the budget reserve?
A) Analogous Estimating
B) Bottom-up Estimating
C) Parametric Estimating
D) Reserve Analysis
A) Benchmarking
B) Reserve Analysis
C) Cost Aggregation
D) Cost-Benefit Analysis
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 40
11. The project manager is initiating a new project and is developing the Project
Management Plan. One of the key components of the plan is cost management.
Which process is specifically responsible for defining how costs will be
estimated, budgeted, managed, and controlled throughout the project?
A) Estimate Costs
B) Determine Budget
D) Control Costs
12. The project manager is working on a large construction project. They are
developing the project budget and need to allocate costs to individual work
packages or activities. Which process is responsible for determining the cost
baseline for the project?
A) Estimate Costs
B) Determine Budget
D) Control Costs
13. The project manager is developing the cost management plan for a research
project. The project manager wants to ensure that cost variances are identified
and addressed in a timely manner. Which tool or technique should the project
manager use to monitor and control costs?
B) Cost Aggregation
C) Variance Analysis
D) Forecasting
14. The project manager is in the process of developing the cost baseline for a
software development project. The project manager needs to allocate costs to
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 41
specific time periods for tracking purposes. Which tool or technique should the
project manager use to determine the distribution of costs over time?
B) Cost Aggregation
C) Variance Analysis
D) Cost-Performance Baseline
15. The project manager is developing the cost management plan for an
engineering project. The project manager wants to ensure that all costs,
including indirect costs, are considered in the budget. Which tool or technique
should the project manager use to identify and allocate indirect costs?
A) Analogous Estimating
B) Bottom-up Estimating
C) Parametric Estimating
ANSWERS
1. Answer: A) Analogous estimating.
Rationale: In the given scenario, the project manager is using historical data from
previous projects to estimate the cost of the current project. This technique is
known as Analogous Estimating, which is based on the analogy of similar projects.
Rationale: In the given scenario, the project manager has created a budget for the
project and is monitoring the project's progress to ensure that it stays within the
budget. This is achieved through the use of Earned Value Management (EVM), a cost
control technique that integrates scope, time, and cost measures to help evaluate
project performance and progress.
Rationale: In the given scenario, the project manager is using a mathematical model
to estimate the cost of the project. This technique is known as Parametric
Estimating, which uses statistical data and mathematical algorithms to estimate
project costs based on specific project parameters.
Rationale: In the given scenario, the project manager uses a formula to estimate the
cost of the project based on certain parameters. This technique is known as
Parametric Estimating, which uses statistical data and mathematical algorithms to
estimate project costs based on specific project parameters.
Rationale: In the given scenario, the project manager has identified that the project
is over budget. Variance Analysis is a cost control technique that compares actual
project performance against the project plan to identify variances, determine their
causes, and take corrective action.
Rationale: In the given scenario, the project manager creates a budget for the
project that includes all the costs associated with the project. This technique is
known as Top-down Estimating, which involves estimating the total cost of the
project first and then breaking down the cost into smaller components.
Rationale: Bottom-up Estimating involves breaking down the work into small,
manageable components (such as activities or work packages) and estimating their
costs individually. It provides a more accurate and detailed cost estimate compared
to other techniques.
Rationale: Reserve Analysis is the technique used to estimate the budget reserve. It
involves setting aside a specific amount of money to address known risks and
uncertainties during the project. The reserve helps to ensure that funds are
available to mitigate potential cost impacts.
Rationale: This question is a duplicate of Question 7, and the correct answer remains
the same. The Plan Cost Management process is responsible for defining how costs
will be estimated, budgeted, managed, and controlled throughout the project.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 44
Rationale: Earned Value Management (EVM) is a tool and technique used for
monitoring and controlling costs. It integrates cost, schedule, and scope
performance to provide insights into cost variances, cost performance, and cost
forecasts.
Rationale: The Cost of Quality (COQ) is the tool or technique used to identify and
allocate indirect costs in the budget. It includes costs related to prevention,
appraisal, and failure that are incurred due to lack of quality in the project
deliverables.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 45
1. The project manager is reviewing the project deliverables to ensure they meet
the defined quality standards. Which quality management technique is the
project manager using?
A) Control Charts
C) Inspection
D) Benchmarking
2. During project execution, the project manager notices that defects are being
found in the deliverables at an increasing rate. Which quality control technique
should the project manager implement to identify the cause of these defects?
A) Flowcharting
B) Pareto Chart
C) Scatter Diagram
A) Control Charts
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 46
C) Inspection
D) Benchmarking
A) Inspection
B) Control Charts
C) Flowcharting
D) Scatter Diagram
6. The project manager wants to determine the most common causes of defects
in the project deliverables. Which quality management technique should the
project manager use?
A) Control Charts
C) Inspection
D) Benchmarking
7. The project manager is analyzing the data collected during quality control
activities to identify trends and patterns. Which quality management technique
is the project manager using?
A) Control Charts
C) Inspection
D) Benchmarking
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 47
8. During project execution, the project manager realizes that the project
deliverables are not meeting the specified quality standards. Which quality
control technique should the project manager use to determine the root causes
of these issues?
A) Flowcharting
B) Pareto Chart
C) Scatter Diagram
A) Control Charts
C) Inspection
D) Benchmarking
11. During the quality control process, a project manager identifies a defect in
a product that does not meet the specified quality standards. What is the most
appropriate next step for the project manager?
A) Pareto chart
B) Cause-and-effect diagram
C) Control chart
D) Scatter diagram
13. During the quality assurance process, a project manager identifies that the
project team is not following the established quality standards. What action
should the project manager take to address this issue?
C) Change the quality standards to align with the team's current practices
A) Checklists
B) Control charts
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 49
C) Pareto analysis
D) Statistical sampling
A) Quality planning
B) Quality control
C) Quality assurance
D) Quality improvement
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 50
ANSWERS
1. Answer: C) Inspection: Inspection involves reviewing the project deliverables to
ensure they meet the defined quality standards.
2. Answer: D) Root Cause Analysis: Root Cause Analysis is used to identify the
underlying causes of defects or issues in order to address them effectively.
3. Answer: B) Verify compliance with quality standards: One of the key objectives
of a quality audit is to verify compliance with quality standards and procedures.
a peer review of the code is a form of inspection, where team members review and
examine the deliverables for quality.
6. Answer: B) Cause and Effect Diagrams: Cause and Effect Diagrams, also known
as Fishbone or Ishikawa diagrams, are used to identify and analyze the potential
causes of defects or issues.
7. Answer: A) Control Charts: Control Charts are used to analyze data collected
during quality control activities to identify trends, variations, and patterns.
8. Answer: D) Root Cause Analysis: Root Cause Analysis is used to determine the
root causes of issues or defects and to develop appropriate corrective actions.
10. Answer: C) Quality control measures the compliance of deliverables with quality
standards, while quality assurance measures the effectiveness of the quality
management system: Quality control focuses on measuring the compliance of
deliverables with quality standards, while quality assurance focuses on measuring
the effectiveness of the quality management system in achieving quality objectives.
11. Answer: A) Document the defect and report it to the appropriate stakeholders.
Rationale: If the project team is not following the established quality standards,
providing additional training is an effective action to address this issue. Training
helps ensure that the team members have the necessary knowledge and skills to
meet the quality requirements and adhere to the established standards.
Rationale: The project manager is engaged in quality control when responsible for
managing the quality of deliverables throughout the project lifecycle. Quality
control involves monitoring and inspecting project deliverables to ensure they meet
the specified quality standards. It focuses on identifying defects, making necessary
corrections, and verifying that the deliverables conform to the established quality
criteria.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 53
B) Acquire Resources
C) Develop Team
2. The project manager is initiating a new project and needs to determine the
availability and skills of resources. They want to utilize historical data and
expert judgment to estimate the resources needed. Which technique should the
project manager use?
A) Bottom-up Estimating
B) Analogous Estimating
D) Resource Calendar
A) Pre-assignment
B) Negotiation
C) Virtual Teams
4. The project manager is managing a complex project and needs to ensure that
the project team members have a clear understanding of their roles and
responsibilities. Which process is responsible for this task?
B) Acquire Resources
C) Develop Team
B) Acquire Resources
C) Develop Team
6. The project manager is in the process of estimating the type and quantity of
resources required for each activity. They want to use historical data and
project documents as inputs to this process. Which technique should the project
manager use?
A) Bottom-up Estimating
B) Analogous Estimating
D) Resource Calendar
A) Pre-assignment
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 55
B) Negotiation
C) Virtual Teams
B) Acquire Resources
C) Develop Team
B) Resource Calendar
C) Resource Histogram
D) Resource Leveling
B) Acquire Resources
C) Develop Team
11. The project manager is leading a large software development project. The
project team consists of members from different functional areas who report
to their respective department managers. Which leadership style is the project
manager most likely using?
A) Autocratic leadership
B) Democratic leadership
C) Laissez-faire leadership
D) Transformational leadership
12. During a project team meeting, a team member challenges a decision made
by the project manager. The team member asserts that the decision was made
without proper consultation and presents alternative options. This
demonstrates the exercise of which form of power?
A) Expert power
B) Reward power
C) Legitimate power
D) Referent power
13. The project manager is dealing with team conflicts related to resource
allocation and task priorities. Which conflict resolution technique should the
project manager use to achieve a mutually acceptable solution?
A) Collaborating
B) Forcing
C) Avoiding
D) Compromising
14. The project manager is responsible for controlling the project team's
performance and ensuring that project activities are being completed as
planned. Which tool or technique should the project manager use to assess
individual and team performance?
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 57
A) Performance appraisals
B) Conflict management
C) Lessons learned
15. The project manager has recently joined a project team. They are
establishing a strong working relationship with team members by
demonstrating trust, providing support, and promoting open communication.
Which leadership style is the project manager most likely using?
A) Autocratic leadership
B) Democratic leadership
C) Laissez-faire leadership
D) Servant leadership
16. The project manager is working on a project with a team that includes
members from different countries and cultural backgrounds. Which approach
should the project manager adopt to effectively manage the diverse team?
A) Cross-cultural training
D) Performance appraisals
17. The project manager is leading a project where team members have a high
level of expertise and experience. The project manager encourages team
members to share knowledge and make decisions collectively. Which leadership
style is the project manager most likely using?
A) Autocratic leadership
B) Democratic leadership
C) Laissez-faire leadership
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 58
D) Transactional leadership
18. A team member has consistently been performing below expectations and
failing to complete assigned tasks on time. The project manager decides to have
a private conversation with the team member to address the issue. Which form
of power is the project manager utilizing in this situation?
A) Expert power
B) Reward power
C) Coercive power
D) Legitimate power
A) Video conferencing
B) Email communication
C) Face-to-face meetings
20. The project manager is facing resistance from team members regarding a
change in project requirements. The project manager believes that the change
is necessary for the project's success. Which conflict resolution technique
should the project manager use to address this situation?
A) Collaborating
B) Forcing
C) Avoiding
D) Compromising
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 59
ANSWERS
1. Answer: D) Plan Resource Management.
Rationale: The process responsible for defining how resources will be estimated,
acquired, managed, and released throughout the project is the Plan Resource
Management process. It involves developing a staffing management plan that
identifies the types and quantities of resources required for each activity.
Rationale: The Develop Team process is responsible for enhancing individual and
group competencies to improve project performance. It focuses on clarifying roles
and responsibilities, establishing team dynamics, and building a cohesive project
team.
Rationale: When selecting vendors or external contractors, the project manager can
use Multicriteria Decision Analysis to evaluate and compare potential vendors based
on various criteria, such as cost, quality, expertise, and reputation.
Rationale: In this scenario, the project manager is leading a team with members
reporting to their functional department managers. In an autocratic leadership
style, the project manager has centralized decision-making authority and is likely
to have more control over the team members' actions and decisions.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 61
Rationale: Performance appraisals are a tool used to assess individual and team
performance. They involve evaluating the performance of team members against
predetermined criteria, providing feedback, and identifying areas for improvement.
The project manager can use performance appraisals to monitor and control the
team's performance.
A) Information distribution
B) Communication technology
C) Stakeholder analysis
A) Interactive communication
C) Non-verbal communication
C) Control Communications
D) Monitor Communications
A) Video conferencing
A) Project charter
B) Stakeholder register
D) Subcontractor agreement
A) Active listening
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 65
C) Information retrieval
D) Visual communication
B) Manage Communications
C) Control Communications
D) Monitor Communications
A) Effective listening
B) Tailored communication
C) Information retrieval
B) Stakeholder register
D) Issue log
10. The project manager is working on a project with a large team distributed
across multiple locations. To enhance communication and collaboration, the
project manager decides to implement a communication technology that allows
team members to communicate in real-time through text-based messages,
audio calls, and video conferencing. Which communication tool is the project
manager using?
A) Email
B) Instant messaging
B) Email updates
A) Active listening
B) Nonverbal communication
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 67
C) Translation services
D) Virtual meetings
13. The project manager needs to convey complex technical information to the
project stakeholders. Which communication method would be most effective in
this situation?
A) Face-to-face meetings
B) Written reports
D) Email communication
ANSWERS
1. Answer: C) Stakeholder analysis
Rationale: When language barriers exist among project team members, the most
helpful communication technique is to use translation services. This ensures that
information is accurately conveyed and understood by all team members, regardless
of their native language.
Rationale: When team members are located in different time zones, establishing a
shared project calendar is crucial for effective communication. A shared calendar
helps team members coordinate meetings and activities, considering time zone
differences, to ensure everyone can participate and stay informed.
A) Delphi Technique
B) Brainstorming
C) SWOT Analysis
C) Sensitivity Analysis
3. The project manager is leading a project and has identified a risk that could
potentially delay the project schedule. The project manager wants to
quantitatively analyze the impact of the risk on the project's overall timeline.
Which technique should the project manager use?
A) SWOT Analysis
D) Delphi Technique
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 72
A) Delphi Technique
B) Brainstorming
C) SWOT Analysis
C) Sensitivity Analysis
6. The project manager is leading a project and has identified a risk that could
significantly impact the project's budget. The project manager wants to assess
the financial implications of the risk and determine the range of potential
financial outcomes. Which technique should the project manager use?
A) SWOT Analysis
D) Delphi Technique
C) Sensitivity Analysis
8. The project manager has identified a high-impact risk that could potentially
delay the project schedule. To address this risk, the project manager decides to
hire additional resources to expedite the project activities in case the risk
occurs. Which risk response strategy is the project manager implementing?
A) Avoidance
B) Mitigation
C) Transfer
D) Acceptance
9. The project manager is developing the risk management plan and wants to
define the criteria for triggering predefined risk responses. Which tool or
technique should the project manager use?
A) Risk Register
10. The project manager has identified a risk that could impact the project's
budget. The project manager decides to purchase insurance to transfer the
financial consequences of the risk to an insurance provider. Which risk
response strategy is the project manager implementing?
A) Avoidance
B) Mitigation
C) Transfer
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 74
D) Acceptance
11. The project manager has identified a risk that could lead to a safety issue
during project execution. To address this risk, the project manager decides to
revise the project plan and remove the activities associated with the risky
process. Which risk response strategy is the project manager implementing?
A) Avoidance
B) Mitigation
C) Transfer
D) Acceptance
12. The project manager is monitoring and controlling project risks. The project
manager notices that a previously identified risk has occurred. The project
team is implementing predefined risk responses to address the risk. Which
process is the project manager performing?
C) Monitor Risks
D) Identify Risks
13. The project manager has identified a risk that could potentially impact the
project's schedule. The project manager decides to adjust the project schedule
by adding contingency buffers to account for the potential delays. Which risk
response strategy is the project manager implementing?
A) Avoidance
B) Mitigation
C) Transfer
D) Acceptance
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 75
14. The project manager is monitoring project risks and notices that the risk
probability and impact have changed since the initial risk assessment. The
project manager decides to update the risk response strategies and actions
accordingly. Which process is the project manager performing?
C) Monitor Risks
D) Identify Risks
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 76
ANSWERS
1. Answer: B) Brainstorming
Rationale: A Probability and Impact Matrix is a tool used in qualitative risk analysis
to assess the impact and likelihood of identified risks using a predefined rating
scale. It helps prioritize risks based on their potential severity.
Rationale: Monte Carlo Analysis is a quantitative risk analysis technique that uses
probability distributions to simulate possible project outcomes and assess the
impact of identified risks on the project's overall timeline.
4. Answer: B) Brainstorming
Rationale: The Probability and Impact Matrix is a tool used in qualitative risk
analysis to assess the probability and impact of identified risks based on expert
judgment. It helps prioritize risks for further analysis and response planning.
8. Answer: B) Mitigation
Rationale: Risk Urgency Assessment is a tool used to establish criteria for triggering
predefined risk responses. It helps project managers determine when specific risk
responses should be implemented.
Rationale: Risk transfer involves transferring the risk and its financial
consequences to a third party, such as an insurance provider. Purchasing insurance
to cover the potential financial impact is an example of a risk transfer strategy.
Rationale: Risk avoidance involves eliminating the risk by removing the activities
associated with the risk. Revising the project plan to remove the activities
associated with the risky process is an example of risk avoidance.
Rationale: Monitoring risks involves tracking identified risks and assessing changes
in their probability and impact. Updating risk response strategies and actions based
on changes in risk probability and impact falls under the Monitor Risks process.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 79
D) Contract
A) Procurement Audits
B) Payment Systems
D) Performance Reviews
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 80
A) Make-or-Buy Analysis
B) Procurement Negotiations
D) Contract
A) Bidder Conferences
C) Independent Estimates
D) Advertising
D) Contract
A) Procurement Audits
B) Payment Systems
D) Performance Reviews
A) Bidder Conferences
B) Procurement Negotiations
A) Bidder Conferences
C) Independent Estimates
D) Advertising
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 83
ANSWERS
1. Answer: C) Firm Fixed Price (FFP).
Rationale: The Firm Fixed Price contract type transfers maximum risk to the seller
because the seller is responsible for delivering the project scope within the agreed-
upon price, regardless of any cost overruns or risks encountered.
Rationale: Risk Analysis and Management is the tool or technique used to identify
and analyze risks associated with procurement activities. By conducting risk
analysis, the project manager can proactively address potential risks and develop
risk responses.
Rationale: The Request for Information (RFI) document is used to provide additional
information and clarify requirements to potential vendors. It serves as a
communication tool to address vendor inquiries and ensure a clear understanding
of project specifications.
Rationale: Inspection and Audit is the tool or technique used to verify that the seller
has delivered the agreed-upon goods or services as per the contract. It involves
conducting physical inspections, reviewing documentation, and performing audits
to ensure compliance with contractual obligations.
Rationale: Risk Analysis and Management is the tool or technique used to analyze
risks associated with the procurement process. It helps identify potential risks,
assess their impact, and develop appropriate risk responses to mitigate their
negative impact on the project.
B) Identify Stakeholders
A) Expert Judgment
B) Data Gathering
C) Stakeholder Analysis
D) Stakeholder Register
A) Active Listening
B) Communication Technology
C) Tailored Communication
D) Two-Way Communication
A) Power/Interest Grid
B) Influence/Impact Grid
C) Salience Model
B) Stakeholder Analysis
C) Stakeholder Register
D) Power/Interest Grid
A) Power/Interest Grid
B) Influence/Impact Grid
C) Salience Model
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 87
A) Power/Interest Grid
C) Two-Way Communication
D) Salience Model
10. The project manager is identifying stakeholders for an IT project. They want
to understand the stakeholders' needs, expectations, and potential impact on
the project. Which tool or technique should the project manager use?
A) Expert Judgment
B) Data Gathering
C) Stakeholder Analysis
D) Stakeholder Register
A) Identify Stakeholders
12. The project team is facing challenges with stakeholder engagement and
needs to develop strategies to increase stakeholder support and minimize
resistance. Which tool or technique should the project team use?
B) Stakeholder Register
C) Stakeholder Analysis
13. The project manager is conducting regular meetings with key stakeholders
to discuss project progress and address their concerns. Which technique is the
project manager using to manage stakeholder engagement?
A) Power/Interest Grid
B) Influence/Impact Grid
C) Issue Log
D) Communication Methods
A) Stakeholder Analysis
C) Issue Log
D) Lessons Learned
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 89
A) Two-Way Communication
B) Communication Methods
D) Power/Interest Grid
16. The project manager is facing challenges with stakeholder engagement due
to conflicting interests and priorities. Which technique can the project manager
use to resolve conflicts and improve stakeholder engagement?
A) Negotiation
B) Issue Log
C) Lessons Learned
D) Stakeholder Register
17. The project manager is conducting regular surveys and feedback sessions to
gather stakeholders' opinions and perceptions. Which tool or technique is the
project manager using to monitor stakeholder engagement?
A) Power/Interest Grid
B) Influence/Impact Grid
C) Lessons Learned
B) Stakeholder Register
C) Communication Methods
D) Power/Interest Grid
19. The project manager is using a software tool to track and monitor
stakeholder engagement activities, communication channels, and response
times. Which tool is the project manager using?
A) Issue Log
B) Stakeholder Register
C) Communication Methods
ANSWERS
1. Answer: B) Identify Stakeholders
Rationale: The Stakeholder Engagement Assessment Matrix helps the project team
develop strategies to increase stakeholder support and minimize resistance. It
assesses stakeholders based on their current engagement level and their potential
impact on the project, allowing the team to prioritize their engagement efforts
effectively.
1. You are managing a software development project and have just completed
the design phase. One of your team members informs you that they discovered
a critical flaw in the design that will require significant changes. What should
be your immediate response?
B) Review the design with the team member and evaluate the potential impact on
the project
C) Ignore the team member's concerns and proceed with the project
D) Analyze the impact of the change on the project scope and schedule
2. You are the project manager for a construction project. You have just received
a change request from the client that will significantly increase the project
budget. What should you do before implementing the change request?
C) Request additional funding from the client to accommodate the change request
3. You are managing a project that has encountered a major delay due to
unforeseen circumstances. What should be your immediate action?
B) Notify stakeholders of the delay and its impact on the project timeline
D) Evaluate the cause of the delay and determine the best course of action
4. You are managing a project with a tight deadline. One of your team members
informs you that they are behind schedule and may not be able to complete their
tasks on time. What should be your immediate response?
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 96
A) Work with the team member to identify the cause of the delay
D) Replace the team member with someone who can work faster
5. You are managing a project and have just received a change request from a
stakeholder. The change request has a high impact on the project budget. What
should you do before implementing the change request?
6. You are the project manager for a marketing campaign. One of your team
members has just informed you that they have identified a major flaw in the
campaign strategy. What should be your immediate response?
A) Ignore the team member's concerns and proceed with the campaign as planned
B) Work with the team member to assess the impact of the flaw on the project
objectives
C) Replace the team member with someone who can identify flaws in the strategy
D) Immediately change the campaign strategy based on the team member's input
7. You are managing a project and have just received a change request from a
stakeholder. The change request has a high impact on the project scope. What
should you do before implementing the change request?
8. You are managing a project and have just received a change request from a
stakeholder. The change request has a high impact on the project schedule.
What should you do before implementing the change request?
9. You are managing a software development project and one of your team
members has reported that they are facing issues with a critical software
component. The team member has suggested that it may require significant
changes to the project plan. What should be your immediate response?
B) Review the software component issue with the team member and evaluate the
potential impact on the project
D) Replace the team member with someone who can resolve the software
component issue
10. You are managing a construction project and have just received a change
request from the client that will require significant changes to the project
design. What should be your immediate action?
A) Analyze the impact of the change request on the project scope and budget
ANSWERS
1. Answer: B) Review the design with the team member and evaluate the potential
impact on the project
2. Answer: D) Obtain approval from the project sponsor or change control board
3. Answer: B) Notify stakeholders of the delay and its impact on the project timeline
4. Answer: A) Work with the team member to identify the cause of the delay
Rationale: When a team member reports being behind schedule, the immediate
response should be to work with them to identify the cause of the delay.
Understanding the root cause will enable appropriate action, such as adjusting the
schedule, providing support, or reassigning tasks if necessary.
5. Answer: A) Evaluate the impact of the change request on the project budget
Rationale: Before implementing a change request with a high impact on the project
budget, it is crucial to evaluate its potential effect. This assessment ensures that the
change aligns with the project's financial constraints and can be accommodated
within the approved budget.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 102
6. Answer: B) Work with the team member to assess the impact of the flaw on the
project objectives
Rationale: When a team member identifies a major flaw in the campaign strategy,
the immediate response should be to work with them to assess its impact on the
project objectives. Understanding the implications of the flaw helps in making
informed decisions and adjusting the strategy as needed.
7. Answer: D) Obtain approval from the project sponsor or change control board
Rationale: Before implementing a change request that has a high impact on the
project scope, it is necessary to obtain approval from the project sponsor or change
control board. This ensures that the change is properly evaluated and aligns with
the project's objectives.
8. Answer: A) Evaluate the impact of the change request on the project schedule
Rationale: Before implementing a change request with a high impact on the project
schedule, it is important to evaluate its potential effect. This assessment helps in
understanding the time implications and making informed decisions about
adjusting the schedule.
9. Answer: B) Review the software component issue with the team member and
evaluate the potential impact on the project
Rationale: When a team member reports issues with a critical software component,
it is essential to review the issue with them and assess its potential impact on the
project. Understanding the severity of the issue and its implications will guide the
appropriate response.
10. Answer: D) Obtain approval from the project sponsor or change control board
Rationale: When a change request is received from the client that requires
significant changes to the project design, it is necessary to obtain approval from the
project sponsor or change control board before proceeding. This ensures proper
evaluation and alignment with project objectives.
200 PMP MOCK QUES BY M. ADNAN - PMP®, PMI-SP®, PMI-RMP® 103
11. Answer: A) To provide resources and support for the project team
Rationale: In the initiation phase of the project, one of the key responsibilities of
the project manager is to define the project scope. This involves determining the
boundaries and objectives of the project, as well as identifying the deliverables and
constraints.
Rationale: In the closing phase of the project, one of the key responsibilities of a
project stakeholder is to accept the project deliverables. This signifies the formal
acceptance of the completed work and confirms that it meets the agreed-upon
requirements and quality standards.
Rationale: In the planning phase of the project, one of the key responsibilities of the
project manager is to define the project scope. This involves determining the
project's objectives, deliverables, and boundaries, and documenting them in the
project scope statement.