TVET CURRICULUM DEVELOPMENT, ASSESSMENT AND CERTIFICATION
COUNCIL (TVET CDACC)
WRITTEN ASSESSMENT
Time: 3 Hours
INSTRUCTIONS TO CANDIDATES
1. This paper has TWO sections A and B.
2. You are provided with a separate answer booklet.
3. Marks for each question are indicated in the brackets ().
4. Do not write on the question paper.
SECTION A:
SHORT ANSWER QUESTIONS (30 MARKS)
1. Outline THREE measures you will put in place in ensuring procurement plan is approved as per organizations policy. [3 Marks] 3. Justify the importance of establishing the availability of funds before embarking on a procurement process [3 Marks] 4. In your own view, what is awarding procurement bids to the most responsive bidder? [4 Marks] 5. What are the recommended conditions that procured goods can be stored in? [4Marks] 6. Which five aspects should be included in the development of procurement contracts [5 marks] 7. How to you develop a list of prequalified suppliers for procurement [2 marks] 8. Why is procurement planning so important to an organization [4 marks] 9 .What is a specification of requirement and how do you go about in establishing requirements of the organization [4 Marks] SECTION C: EXTENDED RESPONSE QUESTIONS (50 MARKS) 1. Procurement managers develop procurement plans. Describe the contents of prepared procurement plan [14 Marks] 2. Outline the procedure for dispatching procured and received goods to user departments [8Marks] 3. “Contract should be managed by both parties as per agreement” Explain key processes and activities involved in contract management [6 Marks] 4. Evaluating procurement bids is critical according to Kenya public procurement Act (2015). Discuss the criteria used by evaluation committee to prequalify suppliers [10 Marks] 5. Explain the stages in a typical procurement process in Kenya [8 Marks] 6. “Conducting market price survey is critical for organizations’ requirements and performance of supplier” 7. Explain possible sources of information about potential suppliers [6 Marks]