Professional Documents
Culture Documents
PM SLB
PM SLB
PROJECT IDENTIFICATION
DRMS
Agency or organization name
1 071 Drill seed Irrigated Cropland No Release Green REVEGE 1 111 92 34 373 71
Manure
1 075 Mobilize equipment for inital reclamation MOBILIZE 1 25 77 51 121 55
breakdown re d
076 Mobilize large equipment for pond and ditch MOBILIZE 1 25 77 4 761 35
reclamation
71b Drill seed Irrigated Cropland No Release Seed REVEGE 1 111 92 36 399 85
Mix 7
71c Drill seed Irrigated CR No Release Seed Mix 7 REVEGE 1 111 92 36 399 85
Yr 6
71d Drill seed Irrigated CR No Release ASG Seed REVEGE 1 111 92 33 543 66
Yr 6
75b Mobilize smaller equipment for initial reclamation MOBILIZE 1 11 77 17 509 61
76b Mobilize equip for ponds and ditches no MOBILIZE 1 11 77 7 375 98
breakdown
76c Mobilize grader annually ten times for site MOBILIZE 1 2 80 3 311 34
maintenance
INDIRECT COSTS
CONTINGENCY 0 00 Total 0 00
PROJECT IDENTIFICATION
OUANTITY I UNIT
Blast Area Configuration Wedge shaped mass highwall reduction using balanced cut fill
Blasting Method Description Cast blast fra mentation lateral movement
Highwall or Bench Face Angle 0 00 h lv
Regraded Slope Angle 3 00 h lv
Highwall or Bench Length 2 500 feet
Highwall or Bench Width 48 feet
Highwall or Bench Height 79 0 feet
Depth to Base of Cut at Highwall 16 0 feet
UANTITY UNIT
Total Volume of Dimensional Mass to be Shot 35 556 cubic yards
Blast Volume to Subdrill Grade and Blast Pattern Lines 26 253 cubic yards
Blast Volume to Finish Grade and Blast Pattern Lines 26 253 cubic yards
QUANTITY UNIT
Recommended Blasthole Diameter 2 133 inches
Selected Blasthole Diameter 6 000 inches
Subdrillin Allowance 0 0 feet
Blasthole Depth 9 0 feet
Density of Rock Low Density Rock ANFO rock density
Basis
Burden to Charge Diameter Ratio 28 times diameter
Burden 14 0 feet
Spacing to Burden Ratio 1 1 times burden
Spacing 15 0 feet
Cubic Yards of Rock per Blasthole 88 15 cubic yards
QUANTITY UNIT
Total Quantity of det cord fuse wire Required 8 796 linear feet
Drilling MiscTruck
Number of Units 1 0 0 0 1 0
MATERIALS COST
Miscellaneous 0 000 0 00
Drill bits Bit life 2 600 Linear feet 1 639 00 1 149 1 883 59
5 700 feet
Site Altitude
0 95 DRMS est
Altitude Adjustment
0 67 CH Exc HB
Job Efficiency Factor
feet hour
Adjusted Drilling Rate 119 03
57 93 hours
Explosives Prep Time
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
Source
Job Condition Correction Factor
Operator Skill 0 750 AVG
BULLDOZER WORK
PROJECT IDENTIFICATION
Attachment NA
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
BULLDOZER WORK
Task description Grade spoil side material and coal stockpile into pit
Permit Action Phase II III Bond
Release SL 12 and
PR 6 Permit Job C1981008
Site New Horizon Mine
PROJECT IDENTIFICATION
Attachment NA
Shift Basis 1 per day
Data Source CRG
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
Source of estimated volume WFC Fence Diagram 3 348 long Cut 96 4 000 Icy coal
Source of estimated swell factor Cat Handbook
HOURLY PRODUCTION
PROJECT IDENTIFICATION
OUANTITY I UNIT
Blast Area Configuration Wedge shaped mass hi hwall reduction using balanced cut fill
Blasting Method Description Cast blast fragmentation lateral movement
Highwall or Bench Face Angle 0 00 h lv
Regraded Slope Angle 5 00 h lv
Highwall or Bench Length 400 feet
Highwall or Bench Width 40 feet
Highwall or Bench Height 79 0 feet
Depth to Base of Cut at Highwall 8 0 feet
QUANTITY UNIT
Total Volume of Dimensional Mass to be Shot 2 370 cubic yards
Blast Volume to Subdrill Grade and Blast Pattern Lines 1 052 cubic yards
Blast Volume to Finish Grade and Blast Pattern Lines 1 052 cubic yards
UANTITY UNIT
Recommended Blasthole Diameter 1 067 inches
Selected Blasthole Diameter 6 000 inches
Subdrilling Allowance 0 0 feet
Blasthole Depth 5 2 feet
Density of Rock Low Density Rock ANFO rock density
Basis
Burden to Charge Diameter Ratio 28 times diameter
Burden 14 0 feet
Spacing to Burden Ratio 1 1 times burden
Spacing 15 0 feet
Cubic Yards of Rock per Blasthole 51 33 cubic yards
1 primer s
Quantity of Primers per Blasthole
Total Quantity of Primers Required 26 primers
MiscTruck
Drilling
Utilization machine 100 NA NA NA 15 NA
54 87 NA NA NA 67 53 NA
Ownership cost hour
99 19 NA NA NA 12 31 NA
Operating cost hour
NA NA NA NA 0 00 NA
Ripper op cost hour
Operator cost hour 25 37 NA NA NA 19 49 NA
Number of Units 1 0 0 0 1 0
179 43 0 00 0 00 0 00 99 33 0 00
Group Subtotals
Total work team cost hour 278 76
MATERIALS COST
MS connectors non
Delays electric systems Each 4 914 27 000 132 68
Miscellaneous 0 000 0 00
1 14 hours
Drilling Time
CH Exc HB
Job Efficiency Factor 0 67
feet hour
Adjusted Drilling Rate 119 03
hours
Explosives Prep Time 4 45
PROJECT IDENTIFICATIOI
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
7 7 r Q r t 7P m f Maintenance Fouinment
75 NA NA NA NA
Utilization machine 100
62 45 84 80 NA NA NA NA
Ownership cost hour
117 76 86 98 NA NA NA NA
Operating cost hour
NA 0 00 NA NA NA NA
Ripper op cost hour
22 29 38 67 NA NA NA NA
Operator cost hour
202 50 210 45 NA NA NA NA
Unit Subtotals
4 1 0 0 0 0
Number of Units
MATERIAL QUANTITIES
HOURLY PRODUCTION
Truck Capacity
Truck Payload weight Basis
Material weight 2 900 Pounds LCY
Description Decomposed rock 50 Rock 50 Earth
Loading Tool Cycle Time Number of Loading Tool Passes Required to Fill Truck 4 passes
Wheel and Track Loaders Unadjusted Basic Loader Cycle Time load dump maneuver 0 575 minutes
Truck Exchange Time 0 70 Minutes Adjusted for site altitude 0 700 Minutes
Truck Load Time 1 585 Minutes Adjusted for site altitude 1 585 Minutes
Truck Maneuver and Dump Time 1 10 Minutes Adjusted for site altitude 1 100 Minutes
Truck Travel Haul Return Time Road Condition Firm smooth rolling dirt It surfaced watered
maintained 3 0
llaUl XIMU
1 30 3 00 1 70 3448 1 655
1 4000 00
3448 2 900
2 10000 00 1 30 1 3 00 1 1 70
Haul Time 4 555 minutes
1 Gilulll 1 V UV
1 30 3 00 4 30 3540 3 087
1 10000 00
1 30 3 00 4 30 3540 1 130
2 4000 00
W W N U7
n
N
n
N A U
W
W
W
co
W N
A W O O A
O
O j N
C 0 0 cn
o W C
n D
V
N N n O W OD N N f
23 3 D0 N0 n O
C
O
Q Q n
O CL
O TO r
7
CL
n Q 0 0 0 0
m w v
CL CD
A co OD W 00 V W W W
CT OD
W C y
O A CA A N N Cn N W p A N V V cn O Co
Cl OD C O A O A 0 co Co A O A A M Cn O
co N N 0 CA V W OD V N CO W W W W O V Cn OD Co A
69 n r o
m c o
Cn
CL
io O
co
4
V
Cn A
n
69 En
W
N V
69 Cn
A 69 69 69 69 69 69 69 69 69 69 69 69 6 69 69 69 6 W cn N
O O O O 0 0 0 0 0 0 0 0D N
N 0 0 0 0 0 0
W 0 0 0 0 0 0 00 O C 0 0 0 0 0 0 0 0 W
O Cl O O 0 0 0 0 0 0 0 Cn CA 0
W 0 0 0 0 0 Cl
tAcnvv
N C C o
V r
O
D
W 0 m
n
3
699 69
v y
N 69 69 63 0 69 69 69 to 69 69 to fA 69 69 69 69 69 NI i0D
V 0 0 0 Cl 0 0 O O O O Cl 0 0 0 0 0 0 O O G
O 0 0 0 i7 0 o C Cn O O
CT
00
0
0
0
0
0
0
0
Cl
Cl
0
0
0
0
0
o
0
O
O O 0 0 0 0 0 0 0 OD 0 0
O
Z
D
C
N
7
0 A
0 W W A N O W
Cn z O
O CD W C CO 0 d 2
CWO OD W A A 4 Cn V N CO
O
O 4
W O N Cn Co Cn V
ao M
OD Cn W
A O W
cn CA O W
Cn O cn
A cn CA
O Cn OD
O cAn W
O W
cn N
Cn O
A rn
ZM
O C
9 OW
4 A 69 69 69 69 69 K O
OD V OD W o Q
PO
69 rA h D N mo
A W COD Cn O OD W
CT
o
V
co
V n
A OD W
V A O A 69 69
CD
N 69 69 O C O D
O O O 9 A V W 9 N Cn V N W CA Cn O O O N rt
3
i7 c CO OD m O V A O O O D
CA
co O O A V
N
N Co Co O
N W
O Co
Cn b CA Cn W O O
Cn
CU
N D
V 0 W Cn W C O
0
in N W N cn
N v
cn co V Co A V
W V
V N W io
rI
co O o A O w 0 o W A A n w
Cn W n W Cn Cn 0 W O Cn Cn Cn OD W W Cn Cn O FN
n
o
fill
GA 69 69 69 69 y
6 69
W N N A O O W O
Cn fa A W O A
N
O
A
V
OD 0 4
A 0
W OD
A i0 OD
W O 6969
A O
9j V W
W 0
W Cn
CO 0 4 W D n A V O N CT N V OD O O
N OD A W A OD o 8 O m O O
A
Cn
00
4 N
O
Cn
0 W W W CD V m A
O V W W W O O O
O
69
N 69 69 69 69 69 N
O 69 to 69 69 69 69 69 69 N W W 69 A 69
C A Cn N o O Co V A 69 Cn n
W 69 63 69 N 69
A W N A A N D O W N W W N O
N Cn O Cn n N N
W
V V
W V W Cn W O Cl
D
W
A W A
A L V
V W 0 O W V A @ V A O 0 Cn 0 C
OD 8
0 CA Cn O O Cn 0 Cn W N V W A 0 0 0 Cn Co
X X X X X x X X x w x w x 3 0 000
O O O o
i O o
DDN
0 0 O Ov O
Q O O O O v 0
N 0
N 0
N 0
o m N
aaaa CQ CCL a
N a
CD Daaaaaaa 3 co mIR 3
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 cn N ram
C C 9 T T 9 m to N to N
7
N
7
m w m m w v 0 Cn cn 7
ox 7 7 0 7 7 7 7 7
7 7 7 7 n o 0 0 N
or CD N CD N D D N CD
D CD N D CD CD N fD p O O
n n 7
N N N
7 N
7 N N
7 7 N7 D
7 N
7 N
7 7
N 7
N 7
N 7U 7
N Cn DC
0 0
C0D C0D 0D 0
W
00
D CD COD COD C0D 0CD 0CD 0CD O O ON o NO 06 00
D N
O Cn
Cn O OW U7
O O Cn
Cn C O
N O
Cn 0 Cn
Cn 0 Cn
0 Cn
0 Cn
0 Cn
0 Cn
0 c N
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 c
a a
o Cli N
N
CL Dpi Dpi
00
N
N
O n
N co
Page 1 of 2
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
Ownership Cost Hour 72 40 NA
Operating Cost Hour 140 68 100
Ripper op Cost Hour 0 00 0
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
39 30 NA
Ownership Cost Hour
67 12 100
Operating Cost Hour
0 00
Ripper Operating Cost Hour
Operator Cost Hour 24 47 NA
MATERIAL QUANTITIES
468 60 acres
Total Area to be graded or ripped
HOURLY PRODUCTION
Source
1 00 CAT HB
Altitude Adj
0 90 1sh d fay
Job Efficiency
Net Correction 0 9000 multiplier
PROJECT IDENTIFICATION
Abbreviation None
Task 010 State Colorado
Filename C008 010
10 21 2011 County Montrose
Date
User SLB
DRMS
Agency or organization name
Cost Breakdown
Utilization
42 77 NA
Ownership Cost Hour
67 12 100
Operating Cost Hour
3 25 100
Ripper Operating Cost Hour
Operator Cost Hour 24 47 NA
MATERIAL QUANTITIES
acres
Total Area to be graded or ripped 20 00
HOURLY PRODUCTION
Source
1 00 CAT HB
Altitude Adj
Job Efficiency 0 90 1 sh d fay
Net Correction 0 9000 multiplier
PROJECT IDENTIFICATION
UNIT COSTS
cost only
2 7 2 00 bag 9 74 19 48
N37 cement Portland cement grout
PROJECT IDENTIFICATION
DRMS
Agency or organization name
UNIT COSTS
4 7 2 00 bag 9 74 19 48
N3 cement Portland cement grout
cost only
4 7 2 00 bag 9 74 19 48
N41 cement Portland cement grout
cost only
Portland cement grout 4 7 2 00 bag 9 74 19 48
N42 cement
Borehole Worksheet Cont d Task TTT Page 2 of 2
PROJECT IDENTIFICATION
UNIT COSTS
PROJECT IDENTIFICATION
DRMS
Agency or organization name
UNIT COSTS
6 49 14 00 bag 9 74 136 36
7 cement plugs Portland cement grout
PROJECT IDENTIFICATION
DRMS
Agency or organization name
UNIT COSTS
4 7 2 00 bag 9 74 19 48
N17P1 cement Portland cement grout
Bag material cost
only 94 lb bag
4 98 14 01 bag 9 80 137 30
N17P 1 bentonite Granular bentonite Bag
material cost only 50 lb
bag
4 1 22 2 22 LF 5 75 12 77
N 17P 1 casing Exposed casing removal
4 to 6 in diameter steel
pipe LF
Borehole NA NA 1 00 EA 2 75 2 75
N17P1 marker
location identification
marker EA material
cost only
N18P1 cement Portland cement grout 4 7 2 00 bag 9 74 19 48
location identification
marker EA material
cost only
2 man crew 2 Flatbed Truck 6x4 45K NA NA 4 00 EA 85 64 342 56
PROJECT IDENTIFICATION
DRMS
Agency or organization name
UNIT COSTS
Location adjustment 96 90
Total Cost
Subtotal adjusted for
Job Hours 0 00 unadjusted 7 627 70 location 7 391 24
Laborer rate based on Means Site Work and Landscape Cost Data
Task 027 SLB Addendum to New Horizon Mine Reclamation Cost Estimate
C 1981 008 5 11 2011 Replace Power Lines
Task 028 SLB Addendum to New Horizon Mine Reclamation Cost Estimate
C 1981 008 5 11 2011 Replace Telephone Lines
PROJECT IDENTIFICATION
DRMS
Agency or organization name
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck 1 NA
100 NA NA NA NA NA
Utilization machine
NA NA NA NA NA
Ownership cost hour 101 01
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
24 95 NA NA NA NA NA
Operator cost hour
355 70 NA NA NA NA NA
Unit Subtotals
4 0 0 0 0 0
Number of Units
Work 1 422 80 Support 0 00 Maint 0 00
Group Subtotals
MATERIAL QUANTITIES
HOURLY PRODUCTION
Scraper Bowl volume Basis
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 350 00 0 00 I 3 00 1 3 00 2800 1 0 36
Haul Time 0 36 minutes
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 350 00 0 00 3 00 3 00 2949 0 26
PROJECT IDENTIFICATION
quipment Description
Scraper Cat 637G
Dozer NA
Support Equipment Load Area NA
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
101 01 NA NA NA NA NA
Ownership cost hout
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
Number of Units 4 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance t Grade Roll Res Total Res Travel Time
Velocity fpm
fin
1 500 00 0 00 3 00 3 00 2800 0 41
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 500 00 0 00 3 00 3 00 2949 0 31
PROJECT IDENTIFICATION
Abbreviation None
Task 30C State Colorado
Filename C008 30c
Date 11 18 2011 County Montrose
User SLB
Dump Area NA
o 1C Maintenance Fouinment
v vin a a aiii r
t ost DreaKuown
Motor Grader Water Truck
Scraper Dozer Load Area Dump Area
NA NA NA NA
Utilization machine 100 NA
NA NA NA NA
101 01 NA
Ownership cost hour
NA NA NA NA
229 74 NA
Operating cost hour
NA NA NA
NA NA NA
Ripper op cost hour
NA NA NA NA
Operator cost hour 24 95 NA
NA NA NA NA
Unit Subtotals 355 70 NA
0 0 0 0
Number of Units 4 0
Support 0 00 Maint
Work 1 422 80
Group Subtotals
MATERIAL QUANTITIES
HOURLY PRODUCTION
Scraper Bowl volume Basis
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 800 00 0 83 3 00 3 83 2394 0 51
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 800 00 0 83 3 00 2 17 2960 0 40
PROJECT IDENTIFICATION
Equipment Description
Scraper Cat 637G
Dozer NA
Support Equipment Load Area NA
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
101 01 NA NA NA NA NA
Ownership cost hour
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
355 70 NA NA NA NA NA
Unit Subtotals
Number of Units 4 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 600 00 0 00 3 00 3 00 2800 0 45
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 600 00 0 00 3 00 3 00 2949 0 34
PROJECT IDENTIFICATION
Equipment Description
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
100 NA NA NA NA NA
Utilization machine
101 01 NA NA NA NA NA
Ownership cost hour
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA
Ripper op cost hour NA
NA NA NA NA NA
Operator cost hour 24 95
355 70 NA NA NA NA NA
Unit Subtotals
4 0 0 0 0 0
Number of Units
Work 1 422 80 Support 0 00 Maint 0 00
Group Subtotals
MATERIAL QUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Seg Haul Distance Ft Grade Roll Res Total Res Travel Time
Velocity fpm
ndn
1 500 00 0 00 3 00 3 00 2800 0 41
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Travel Time
Velocity fpm
1 500 00 0 00 3 00 3 00 2949
I fin
1 0 31
Return Time 0 31 minutes
PROJECT IDENTIFICATION
101 01 NA NA NA NA NA
Ownership cost hour
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
24 95 NA NA NA NA NA
Operator cost hour
Number of Units 2 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Scraper Bowl volume Basis
Cycle Time
Travel Time
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 375 00 0 00 3 00 3 00 2800 0 37
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 375 00 0 00 3 00 3 00 2949 0 27
PROJECT IDENTIFICATION
Dump Area NA
101 01 NA NA NA NA NA
Ownership cost hour
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
355 70 NA NA NA NA NA
Unit Subtotals
Number of Units 4 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 500 00 0 00 3 00 3 00 2800 1 0 41
Haul Time 0 41 minutes
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 500 00 0 00 3 00 3 00 2949 1 0 31
Return Time 0 31 minutes
PROJECT IDENTIFICATION
100 NA NA NA NA NA
Utilization machine
NA NA NA NA NA
Ownership cost hour 101 01
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
24 95 NA NA NA NA NA
Operator cost hour
355 70 NA NA NA NA NA
Unit Subtotals
4 0 0 0 0 0
Number of Units
Work 1 422 80 Support 0 00 Maint 0 00
Group Subtotals
Total work team cost hour 1 422 80
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt it surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 400 00 0 00 3 00 3 00 2800 0 38
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 400 00 0 00 3 00 3 00 2949 0 27
PROJECT IDENTIFICATION
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
NA NA NA NA NA
Utilization machine 100
101 01 NA NA NA NA NA
Ownership cost hour
NA NA NA NA NA
Operating cost hour 229 74
NA NA NA NA NA
Ripper op cost hour NA
24 95 NA NA NA NA NA
Operator costihour
355 70 NA NA NA NA NA
Unit Subtotals
4 0 0 0 0 0
Number of Units
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Road Condition Firm smooth rolline dirt it surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Travel Time
Velocity fpm
nun
1 200 00 0 00 3 00 3 00 2800 0 30
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Travel Time
Velocity fpm
ndn
1 200 00 0 00 3 00 3 00 2949 0 21
PROJECT IDENTIFICATION
Dump Area NA
r c v f Maintenance F nuinment
v 1 r
Ubt Ica UVVII
NA NA NA NA
Utilization machine 100 NA
NA NA NA NA
101 01 NA
Ownership cost hour
NA NA NA NA
229 74 NA
Operating cost hour
NA NA NA NA
NA NA
Ripper op cost hour
NA NA NA NA NA
Operator cost hour 24 95
NA NA NA NA
Unit Subtotals 355 70 NA
0 0 0 0 0
Number of Units 4
Support 0 00 Maint 0 00
Work 1 422 80
Group Subtotals
Total work team cost hour 1 422 80
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
1 3350 00 3 00 3 00 6 00 1477
I fin
1 2 33
Haul Time 2 33 minutes
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
1 3350 00 3 00 3 00 0 00 2965 1 23
PROJECT IDENTIFICATION
Abbreviation None
Task 046 State Colorado
Montrose Filename C008 046
Date 11 18 2011 County
User SLB
DRMS
Agency or organization name
Dump Area NA
Mnintenance Fouinment
0 11 rr r
Obt I Ft HrUOVVl1
Motor Grader Water Truck
Scraper Dozer Load Area Dump Area
NA NA NA NA
utilization machine 100 NA
NA NA NA NA
101 01 NA
Ownership cost hour
NA NA NA NA
229 74 NA
Operating cost hour
NA NA NA NA
NA NA
Ripper op cost hour
NA NA NA NA
Operator cost hour 24 95 NA
NA NA NA NA
Unit Subtotals 355 70 NA
0 0 0 0
Number of Units 4 0
Support 0 00 Maint 0 00
Work 1 422 80
Group Subtotals
MATERIAL QUANTITIES
HOURLY PRODUCTION
Scraper Bowl volume Basis
Cycle Time
Travel Time
Road Condition Hard smooth stabilized surfaced watered maintained 2 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
0 min
1 600 00 0 00 2 00 2 00 2939 0 42
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 600 00 0 00 2 00 2 00 2960 0 33
PROJECT IDENTIFICATION
101 01 NA NA NA NA NA
Ownership cost hour
NA NA NA NA
Operating cost hour 229 74 NA
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
Number of Units 4 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 350 00 1 25 3 00 4 25 2394 0 34
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 350 00 1 25 3 00 1 75 2960 0 24
PROJECT IDENTIFICATION
quipment Description
Scraper Cat 637G
Dozer NA
Support Equipment Load Area NA
Dump Area NA
101 01 NA NA NA NA NA
Ownership cost hour
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
0 0 0 0
Number of Units j 4
j 0
0 00
Support 0 00 Maint
Group Subtotals I Work 1 1 422 80
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Timer
Travel Time
Road Condition Firm smooth rollinc dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 275 00 1 25 3 00 4 25 2394 0 31
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 1200 00 1 25 3 00 1 75 2960 0 53
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
DRMS
Agency or organization name
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
o Mn ntPnannP Pnninment
a auya a z a
I VJI nrcanuvn u
Motor Grader Water Truck
Scraper Dozer Load Area Dump Area
NA NA NA NA NA
Utilization machine 100
NA NA NA NA NA
Ownership cost hour 101 01
NA NA NA NA NA
Operating cost hour 229 74
NA NA NA NA
NA NA
Ripper op costihour
NA NA NA NA
Operator cost hour 24 95 NA
NA NA NA NA
Unit Subtotals 355 70 NA
0 0 0 0 0
Number of Units 2
711 40 Support 0 00 Maint 0 00
Work
Group Subtotals
MATERIAL QUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2800 0 30
Return Route
Seg Haul Distance t Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2949 0 21
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
wuinment Descripti
Scraper Cat 637G
Dozer NA
Support Equipment Load Area NA
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
Cost Breakdown Scraper Work beam u port hqummem 1V1211111G11d111 G LJUIF 111G111
100 NA NA NA NA NA
Utilization machine
101 01 NA NA NA NA NA
Ownership cost hour
NA NA NA NA NA
Operating cost hour 229 74
NA NA NA NA NA
Ripper op cost hour NA
NA NA NA NA NA
Operator cost hour 24 95
NA NA NA NA NA
Unit Subtotals 355 70
2 0 0 0 0 0
Number of Units
Work 711 40 Support 0 00 Maint 0 00
Group Subtotals
MATERIAL OUANTITIES
HOURLY PRODUCTION
Scraper Bowl volume Basis
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2800 1 0 30
Haul Time 0 30 minutes
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Travel Time
Velocity fpm
fin
1 200 00 0 00 3 00 3 00 2949 0 21
BULLDOZER WORK
PROJECT IDENTIFICATIOt
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
Ripper op Cost Hour 0 00 0
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
101 01 NA NA NA NA NA
Ownership cost hour
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
Number of Units 2 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Road Condition Firm smooth rolline dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Travel Time
Velocity fpm
min
1 200 00 0 00 3 00 3 00 2800 1 0 30
Haul Time 0 30 minutes
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2949 0 21
BULLDOZER WORK
PROJECT EDENTIFICATIOI
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
Equipment Description
Dump Area NA
NA NA NA NA NA
Utilization machine 100
NA NA NA NA NA
Ownership cost hour 101 01
NA NA NA NA NA
Operating cost hour 229 74
NA NA NA NA NA
NA
Ripper op cost hour
NA NA NA NA NA
Operator cost hour 24 95
NA NA NA NA NA
Unit Subtotals 355 70
2 0 0 0 0 0
Number of Units
Work 711 40 Support 0 00 Maint 0 00
Group Subtotals
Total work team cost hour 7 11 40
MATERIAL OUANTITIES
HOURLY PRODUCTION
Scraper Bowl volume Basis
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance t Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2800 0 30
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2949 0 21
BULLDOZER WORK
PROJECT IDENTIFICATIOI
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
72 40 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
0 00 0
Ripper op Cost Hour
Operator Cost Hour 38 49 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
101 01 NA NA NA NA NA
Ownership cost hour
229 74 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
Number of Units 2 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt lt surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2800 0 30
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 200 00 0 00 3 00 3 00 2949 0 21
BULLDOZER WORK
PROJECT EDENTIFICATIOIN
Cost Breakdown
Utilization
MATERIAL QUANTITIES
HOURLY PRODUCTION
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
Units
Unit Cost Unit Cost Acre
Description Acre
Total Fertilizer
Materials
Cost Acre 1 15 80
A J h0
Cost Acre
Descri tion
Tractor towed spreader MEANS 32 0190 13 0120 50 09
TILLING
Cost Acre
Description
92 35
Disc harrowing 6 deep MEANS 32 91 13 23 6100
SEEDING
Rate
PLS Seeds Cost Acre
Seed Mix
LBS per SQ
FT
Acre
0 80 3 67 1 90
Crested Wheatgrass Fairway
1 30 5 22 7 94
Russian Wildrye Bozoisky
Pubescent Wheatgrass Luna 3 30 6 82 7 23
5 40 15 71
Totals Seed Mix 17 07
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
T
Type
e and Size
Common Name Acre Cost Pellet Cost Cost Acre
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
Mofarialc
Units
Description Unit Cost Unit Cost Acre
Acre
Ammonium nitrate 33 0 0 45 00 pound 0 35 15 80
Total Fertilizer
Materials
Cost Acre 1 15 80
Annlicatinn
TILLING
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
Crested Wheatgrass Fairway 0 80 3 67 1 90
15 71
Totals Seed Mix 5 40 17 07
Annlicatinn
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Type and Size Cost Acre
Common Name Acre Cost Pellet Cost
REVEGETATION WORK
PROJECT IDENTIFICATION
DRMS
Agency or organization name
FERTILIZING
A s a 1
Units
Unit Cost Unit Cost Acre
Description Acre
Ammonium nitrate 33 0 0 45 00 pound 0 35 15 80
Total Fertilizer
Materials
Cost Acre 1 15 80
Description
Cost Acre
TILLING
Cost Acre
Description
92 35
Disc harrowing 6 deep MEANS 32 91 13 23 6100
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
Orchardgrass Latar 2 00 24 79 4 32
8 00 30 30
Totals Seed Mix 21 96
A 1 H
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Fertilizer
Type Planting
Common Name Acre Yp and Size Cost Acre
Cost Pellet Cost
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
N4 1
Units
Description Unit Cost Unit Cost Acre
Acre
Ammonium nitrate 33 0 0 45 00 pound 0 35 15 80
Total Fertilizer
Materials
Cost Acre 1 15 80
Annlicntinn
TILLING
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
Orchardgrass Latar 2 00 24 79 4 32
Meadow Brome Regar 6 00 5 51 17 64
30 30
Totals Seed Mix 8 00 21 96
Annlicntinn
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Common Name Type and Size Cost Acre
Acre Cost Pellet Cost
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
Units
Unit Cost Unit Cost Acre
Description Acre
Total Fertilizer
Materials
Cost Acre 1 15 80
Cost Acre
Description
Tractor towed spreader MEANS 32 0190 13 0120 50 09
TILLING
Cost Acre
Description
92 35
Disc harrowing 6 deep MEANS 32 91 13 23 6100
SEEDING
Rate
PLS Seeds Cost Acre
Seed Mix
LBS per SQ
FT
Acre
0 80 3 67 1 90
Crested Wheatgrass Fairway
1 30 5 22 7 94
Russian Wildrye Bozoisky
Pubescent Wheatgrass Luna 3 30 6 82 7 23
15 71
Totals Seed Mix 5 40 17 07
Cost Acre
Description
90 11
Drill seeding DMG
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Common Name Type and Size
Acre Cost Pellet Cost Cost Acre
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
Units
Description Unit Cost Unit Cost Acre
Acre
Ammonium nitrate 33 0 0 45 00 pound 0 35 15 80
Total Fertilizer
Materials
Cost Acre 1 15 80
A h
TILLING
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
5 40 15 71
Totals Seed Mix 17 07
A nnll ti nn
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Type and Size Cost Acre
Common Name Acre Cost Pellet Cost
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
Units
Unit Cost Unit Cost Acre
Description Acre
Ammonium nitrate 33 0 0 45 00 pound 0 35 15 80
Total Fertilizer
Materials
Cost Acre 1 15 80
A 1
Cost Acre
Description
Tractor towed spreader MEANS 32 0190 13 0120 50 09
TELLING
Cost Acre
Description
92 35
Disc harrowing 6 deep MEANS 32 91 13 23 6100
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
6 00 313 13
Totals Seed Mix 27 76
A 1
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Type and Size
Common Name Acre Cost Pellet Cost Cost Acre
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
MAtPri Ale
Units
Description Acre Unit Cost Unit Cost Acre
Total Fertilizer
Materials
Cost Acre 1 15 80
Annlicatinn
TILLING
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
Oats Ajay 75 00 22 38 24 00
Yellow Sweet Clover Madrid 2 00 11 94 5 00
Annlicatinn
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Type and Size Cost Acre
Common Name Acre Cost Pellet Cost
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
Materials
Units
Description Unit Cost Unit Cost Acre
Acre
Ammonium nitrate 33 0 0 45 00 pound 0 35 15 80
Total Fertilizer
Materials
Cost Acre 1 15 80
Annliratinn
TILLING
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
Alfalfa Common 20 00 96 42 50 00
Triticale 30 00 17 22 11 70
Annliratinn
90 11
Total Seed Application Cost Acre 1
MULCHING and MISCELLANEOUS
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Type and Size Cost Acre
Common Name Acre Cost Pellet Cost
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
Units
Unit Cost Unit Cost Acre
Description Acre
Ammonium nitrate 33 0 0 45 00 pound 0 35 15 80
Total Fertilizer
Materials
Cost Acre 1 15 80
Cost Acre
Description
Tractor towed spreader MEANS 32 01 90 13 0120 50 09
TILLING
Cost Acre
Description
92 35
Disc harrowing 6 deep MEANS 32 91 13 23 6100
SEEDING
Rate
Seeds Cost Acre
Seed Mix PLS
LBS per SQ
FT
Acre
Alfalfa Common 20 00 96 42 50 00
Triticale 30 00 17 22 11 70
Application
Description
Cost Acre
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Common Name Type and Size
Acre Cost Pellet Cost Cost Acre
REVEGETATION WORK
PROJECT IDENTIFICATION
FERTILIZING
M o 1
Units
Description Acre Unit Cost Unit Cost Acre
Total Fertilizer
Materials
Cost Acre 1 15 80
Annlivatinn
TILLING
SEEDING
Rate
Seed Mix PLS Seeds Cost Acre
LBS per SQ
FT
Acre
Barley Otis 25 00 8 03 8 75
Oats Ajay 25 00 7 46 8 00
125 00 8437
Totals Seed Mix 38 50
Applicatififn
Materials
Units
Description Acre Unit Cost Unit Cost Acre
Application
No Planting Fertilizer
Type and Size Cost Acre
Common Name Acre Cost Pellet Cost
PROJECT IDENTIFICATION
Truck Tractor Description GENERIC ON HIGHWAY TRUCK TRACTOR 6X4 DIESEL POWERED
400 HP 2ND HALF 2006
Truck Trailer Description GENERIC FOLDING GOOSENECK DROP DECK EQUIPMENT TRAILER
25T 50T AND 100T
Cost Breakdown
2005
Cat D9R 9SU 60 61 49 19 125 45 2 349 27 250 90 500 00
2005
CAT 14H 20 71 34 52 88 67 1 123 19 88 67 500 00
Cat 773D 2002 47 97 52 70 117 55 4 681 00 470 20 1 000 00
ROADABLE EOUIPMENT
Subtotals 1 0 00 0 00
Nearest Major City or Town within project area region GRAND JUNCTION
Total one way travel distance 110 00 miles
Non Roadable
Roadable
Equipment
Equipment
Haul Time Hours 2 44 2 44
Return Time Hours 2 44 2 44
Loading Time Hours 4 00 NA
Unloading Time Hours 4 00 NA
Subtotals 12 89 4 89
PROJECT IDENTIFICATION
Truck Tractor Description GENERIC ON HIGHWAY TRUCK TRACTOR 6X4 DIESEL POWERED
400 HP 2ND HALF 2006
Truck Trailer Description GENERIC FOLDING GOOSENECK DROP DECK EQUIPMENT TRAILER
25T 50T AND 100T
Cost Breakdown
7 000 Gal
Drill Broadcast 25 00 39 59 88 67 l 128 26 88 67 250 00
Seeder with Tractor
Cat 637G 57 28 101 01 125 45 4 905 85 501 80 1 000 00
ROADABLE EQUIPMENT
Machine Description Total Cost hr unit Fleet Size Haul Trip Return Trip
Cost hr fleet Cost hr fleet
Water Tanker 2 500 Gal 63 70 1 63 70 63 70
Flatbed Truck 6x4 45K GVW 68 16 1 68 16 68 16
60 44 1 60 44 60 44
Light Duty Pickup 4x4 1 T Crew
Subtotals 1 192 30 1 192 30
Nearest Major City or Town within project area region GRAND JUNCTION
Total one way travel distance 110 00 miles
Non Roadable
Roadable
Equipment
Equipment
Haul Time Hours 2 44 2 44
Return Time Hours 2 44 2 44
Task description Mobilize large equipment for pond and ditch reclamation
PROJECT IDENTIFICATION
DRMS
Agency or organization name
Truck Tractor Description GENERIC ON HIGHWAY TRUCK TRACTOR 6X4 DIESEL POWERED
400 HP 2ND HALF 2006
Truck Trailer Description GENERIC FOLDING GOOSENECK DROP DECK EQUIPMENT TRAILER
25T 50T AND 100T
Cost Breakdown
ROADABLE EQUIPMENT
Machine Description Total Cost hr unit Fleet Size Haul Trip Return Trip
Cos hr fleet Cost hr fleet
Subtotals 0 00 0 00
Nearest Major City or Town within project area region GRAND JUNCTION
Total one way travel distance 110 00 miles
Non Roadable
Roadable
Equipment
Equipment
Haul Time Hours 2 44 2 44
Return Time Hours 2 44 2 44
Loading Time Hours 4 00 NA
Unloading Time Hours 4 00 NA
Subtotals 12 89 4 89
PROJECT IDENTIFICATION
Truck Tractor Description GENERIC ON HIGHWAY TRUCK TRACTOR 6X4 DIESEL POWERED
400 HP 2ND HALF 2006
Truck Trailer Description GENERIC FOLDING GOOSENECK DROP DECK EQUIPMENT TRAILER
25T 50T AND 100T
Cost Breakdown
ROADABLE EOUIPMENT
Machine Description Total Cost hr unit Fleet Size Haul Trip Return Trip
Cost hr fleet Cost hr fleet
Subtotals 0 00
Nearest Major City or Town within project area region GRAND JUNCTION
Total one way travel distance 110 00 miles
Average Travel Speed 45 00 mph
Non Roadable
Roadable
Equipment
Equipment
Haul Time Hours 2 44 2 44
Return Time Hours 2 44 2 44
Loading Time Hours 0 50 NA
Unloading Time Hours 0 50 NA
Subtotals 5 89 4 89
Task description Mobilize grader annually ten times for site maintenance
Permit Action Phase II III Bond
Release SL 12 and
PR 6 Permit Job C1981008
Site New Horizon Mine
PROJECT IDENTIFICATION
Truck Tractor Description GENERIC ON HIGHWAY TRUCK TRACTOR 6X4 DIESEL POWERED
400 HP 2ND HALF 2006
Truck Trailer Description GENERIC FOLDING GOOSENECK DROP DECK EQUIPMENT TRAILER
25T 50T AND 100T
Cost Breakdown
ROADABLE EQUIPMENT
Machine Description Total Cost hr unit Fleet Size Haul Trip Return Trip
Cost hr fleet Cost hr fleet
Subtotals 0 00 0 00
Non Roadable
Roadable
Equipment
Equipment
Haul Time Hours 0 20 0 20
Return Time Hours 0 20 0 20
Loading Time Hours 0 50 NA
Unloading Time Hours 0 50 NA
Subtotals 1 40 0 40
PROJECT IDENTIFICATION
003 Grades oil side material and coal stockpile into pit 423 11 2 100 0 00
5 59 1 80 1 12
004 Drill and shoot pit ramp hi hwall
006 Support Equipment 1 525 50 1 100 0 00
007 55 90 2 100 0 00
1 Grades oil side of pit ramp
008 Grade hi hwall side of ramp 2 57 2 100 0 00
009 Final grade disturbed areas not bond released 110 14 1 75 27 54
14 37 1 100 0 00
010 Rip spoil topsoil interface
012 Seal 2 Wells 12 00 1 100 0 00
081 7 47 1 100 0 00
Rip BB Road Detour
082 Haul BB Road Pavement to pit 2 06 1 100 0 00
083 Haul BB Road Fill Material 4 69 1 0 4 69
084 6 54 1 1 00 0 00
1 Rip NE Haul Road surface 1 1
Net Job Worksheet Cont d Task 077 Page 2 of 2
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
Alternate Methods
HOURLY PRODUCTION
Seismic
Seismic Velocity 4 500 feet second
Area
Average Ripping Depth NA mph
PROJECT IDENTIFICATION
DRMS
Agency or organization name
Eauipment Description
Truck Loader Team Truck Cat 773F
Loader CAT 988H
Support Equipment Load Area NA
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
62 45 84 80 NA NA NA NA
Ownership cost hour
117 76 115 97 NA NA NA NA
Operating cost hour
NA 0 00 NA NA NA NA
Ripper op cost hour
Operator cost hour 22 29 38 67 NA NA NA NA
Number of Units 2 1 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Truck Capacity
Truck Payload weight Basis
Material weight 3 400 Pounds LCY
Description User Provided
Rated Payload 122 520 Pounds
Loading Tool Cycle Time Number of Loading Tool Passes Required to Fill Truck 4 passes
Wheel and Track Loaders Unadjusted Basic Loader Cycle Time load dump maneuver 0 575 minutes
Truck Exchange Time 0 70 Minutes Adjusted for site altitude 0 700 Minutes
Truck Load Time 1 975 Minutes Adjusted for site altitude 1 975 Minutes
Truck Maneuver and Dump Time 1 10 Minutes Adjusted for site altitude 1 100 Minutes
Truck Travel Haul Return Time Road Condition Hard smooth stabilized surfaced watered
maintained 2 0
Seg vNvHaul Distance Grade Roll Res Total Res Velocity Travel
Time
Ft N fpm
0 00 2 00 2 00 3448 2 589
1 7000 00
111 v
0 00 2 00 2 00 3569 2 145
1 7000 00
PROJECT IDENTIFICATION
ipti
Scraper Cat 637G
Dozer NA
Support Equipment Load Area NA
Dump Area NA
Road Maintenance Motor Grader NA
Water Truck NA
103 90 NA NA NA NA NA
Ownership cost hour
232 77 NA NA NA NA NA
Operating cost hour
NA NA NA NA NA NA
Ripper op cost hour
Operator cost hour 24 95 NA NA NA NA NA
Number of Units 4 0 0 0 0 0
MATERIAL OUANTITIES
HOURLY PRODUCTION
Scraper Bowl volume Basis
Cycle Time
Travel Time
Road Condition Firm smooth rolling dirt It surfaced watered maintained 3 0
Haul Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
fin
1 1644 00 1 80 3 00 4 80 1867 1 02
Return Route
Seg Haul Distance Ft Grade Roll Res Total Res Velocity fpm Travel Time
min
1 1644 00 1 80 3 00 1 20 2963 0 67
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
Ownership Cost Hour 80 19 NA
Alternate Methods
Seismic
Area
Average Ripping Depth 2 00 mph
Unit cost 370 719 Per acre Total job cost 1 742 00
CIRCES Cost Estimating Software
Page 1 of 2
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
80 19 NA
Ownership Cost Hour
140 68 100
Operating Cost Hour
Ripper Operating Cost Hour 7 17 100
Operator Cost Hour 38 49 NA
Alternate Methods
HOURLY PRODUCTION
Seismic
Seismic Velocity NA feet second
Area
Average Ripping Depth 2 00 mph
Unit cost 370 719 Per acre Total job cost 1 965 00
CIRCES Cost Estimating Software
Pagel of 2
BULLDOZER WORK
1
Task description Regrade SW Haul Road surface material
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
Alternate Methods
Seismic
Seismic Velocity NA feet second
Area
Unit cost 370 719 Per acre Total job cost 389 00
CIRCES Cost Estimating Software
Pagel of 2
BULLDOZER WORK
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
Ownership Cost Hour 72 40 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
MATERIAL QUANTITIES
Source
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
MATERIAL QUANTITIES
Source
PROJECT IDENTIFICATIOI
Cost Breakdown
Utilization
39 30 NA
Ownership Cost Hour
13 42 20
Operating Cost Hour
Ripper Operating Cost Hour 0 00
Operator Cost Hour 24 47 NA
MATERIAL QUANTITIES
HOURLY PRODUCTION
Source
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
MATERIAL QUANTITIES
HOURLY PRODUCTION
Source
PROJECT IDENTIFICATION
Cost Breakdown
Utilization
MATERIAL QUANTITIES
HOURLY PRODUCTION
Source
Altitude Adj 1 00 CAT HB
samples sample
Total 1 000 00
Task 099 SLB Addendum to New Horizon Mine Reclamation Cost Estimate
C 1981 008 5 26 2009 Site Maintenance
Total 17 424 00
Task 100 SLB Addendum to New Horizon Mine Reclamation Cost Estimate
C 1981 008 10 21 2011 Site Maintenance
Total 26 176 00