1 TABLE OF CONTENTS TECHNICAL SPECIFICATIONS

2 Division Project No. 18B2M


3 TITLE PAGE 1
4 TABLE OF CONTENTS TC-8
5
6
7 VOLUME 2
8 DIVISION 02 – EXISTING CONDITIONS
9 Section Title Pages Thru
10 02 05 00 Common Work Results for Existing Conditions 02 05 00-4
11 02 32 00 Geo Technical Investigation 02 32 00-30
12 02 41 13 Demolition 02 41 13-5
13
14 DIVISION 03 - CONCRETE
15 Section Title Pages Thru
16 03 10 00 Concrete Formwork 03 10 00-6
17 03 20 00 Reinforcing Steel 03 20 00-8
18 03 30 00 Cast-In-Place Concrete 03 30 00-31
19 03 35 00 Concrete Hardener/Sealer 03 35 00-3
20 03 41 00 Precast Prestressed Concrete 03 41 00-10
21
22 DIVISION 04 - MASONRY
23 Section Title Pages Thru
24 04 08 00 Commissioning of Masonry 04 08 00-7
25 04 20 00 Unit Masonry 04 20 00-13
26
27 DIVISION 05 - METALS
28 Section Title Pages Thru
29 05 05 19 Post-Installed Anchors for Concrete and Masonry 05 05 19-8
30 05 10 00 Structural Steel 05 10 00-15
31 05 50 00 Metal Fabrications 05 50 00-10
32 05 50 16 Miscellaneous Metals for Utilites 05 50 16-3
33 05 51 00 Metal Stairs and Railings 05 51 00-4
34
35 DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
36 Section Title Pages Thru
37 06 09 00 Rough and Finish Carpentry 06 09 00-9
38 06 10 53.01 Miscellaneous Rough Carpentry – Roofing 06 10 53.01-2
39 06 16 43 Gypsum Board Sheathing 06 16 43-3
40 06 17 00 Gang-Nailed Wood Trusses 06 17 00-6
41 06 40 00 Architectural Woodwork 06 40 00-11
42 06 61 00 Solid Surfacing Material Fabrication 06 61 00-5
43
44 DIVISION 07 - THERMAL AND MOISTURE PROTECTION
45 Section Title Pages Thru
46 07 08 00 Commissioning of Thermal and Moisture Protection 07 08 00-22
47 07 10 16 Waterproofing for Utilities 07 10 16-5
48 07 13 00 Membrane Waterproofing 07 13 00-4
49 07 21 00 Building Insulation 07 21 00-7
50 07 27 26 Air Barrier – Vapor Retarder 07 27 26-8
51 07 27 26.13 Air Barrier Transition Membrane 07 27 26.13-4
52 07 31 13 Asphalt Shingles 07 31 13-21
53 Roofing Guarantee
54 07 42 00 Soffit Panels 07 42 00-2
TC-1
1 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 07 53 23-16
2 Roofing Guarantee
3 07 60 00 Architectural Sheet Metal Work 07 60 00-9
4 07 63 00 Sheet Metal Roofing Specialties 07 63 00-11
5 07 81 00 Spray Applied Fireproofing 07 81 00-5
6 07 81 20 Intumescent Fire Resistive Material 07 81 20-5
7 07 84 00 Fire Stopping 07 84 00-9
8 07 90 00 Sealants 07 90 00-5
9 07 92 16 Security Sealant 07 92 16-2
10 07 95 00 Expansion Control 07 95 00-6
11
12 DIVISION 08 - OPENINGS
13 Section Title Pages Thru
14 08 08 00 Commissioning of Exterior Building Envelope 08 08 00-7
15 08 11 00 Hollow Metal Doors and Frames 08 11 00-9
16 08 14 00 Wood Doors 08 14 00-6
17 08 41 00 Aluminum Storefront Framing Systems 08 41 00-10
18 Window Guarantee
19 08 70 00 Hardware 08 70 00-8
20 08 71 00 Security Screws 08 71 00-2
21 08 80 00 Glazing 08 80 00-9
22 08 88 53 Security Glazing 08 88 53-6
23
24 DIVISION 09 - FINISHES
25 Section Title Pages Thru
26 09 21 16 Gypsum Board Assemblies 09 21 16-18
27 09 30 00 Tiling 09 30 00-11
28 09 51 00 Acoustical Ceilings 09 51 00-9
29 09 65 00 Resilient Flooring 09 65 00-17
30 09 68 13 Tile Carpeting 09 68 13-5
31 09 69 00 Access Flooring 09 69 00-7
32 09 84 00 Acoustical Wall Panels 09 84 00-2
33 09 90 00 Painting and Coating 09 90 00-13
34 09 91 16 Painting for Utilities 09 91 16-4
35 09 96 56 Waterborne Epoxy Coating 09 96 56-3
36
37 DIVISION 10 - SPECIALTIES
38 Section Title Pages Thru
39 10 21 13 Solid Plastic Toilet Partitions 10 21 13-4
40 10 21 23 Cubicle, Privacy, and Shower Curtains Including Track 10 21 23-5
41 10 26 00 Corner Guards 10 26 00-5
42 10 26 23 Rigid Vinyl Sheet Wall Protection 10 26 23-3
43 10 28 00 Toilet Accessories 10 28 00-3
44 10 28 25 Electric Hand Dryers 10 28 25-3
45 10 44 00 Fire Extinguishers and Cabinets 10 44 00-4
46
47 DIVISION 11 - EQUIPMENT
48 Section Title Pages Thru
49 11 19 00 General Requirements for Detention 11 19 00-9
50 11 19 10 Detention Doors and Frames 11 19 10-11
51 11 19 15 Detention Furniture 11 19 15-2
52 11 19 20 Detention Equipment Hardware 11 19 20-6
53 11 23 00 Laundry Equipment 11 23 00-8
54 11 40 00 Food Service Equipment 11 40 00-14
TC-2
1
2 DIVISION 12 - FURNISHINGS
3 Section Title Pages Thru
4 12 24 00 Roller Shades 12 24 00-6
5
6 DIVISION 14 - CONVEYING SYSTEMS
7 Section Title Pages Thru
8 14 08 00 Commissioning of Conveying Systems 14 08 00-4
9 14 24 20 Hydraulic Elevators 14 24 20-19
10
11
12 VOLUME 3
13 DIVISION 21 – FIRE SUPPRESSION
14 Section Title Pages Thru
15 21 05 00 Common Work Results for Fire Protection 21 05 00-9
16 21 05 29 Hangers and Supports for Fire Protection Piping and Equipment 21 05 29-6
17 21 08 00 Commissioning of Fire Protection 21 08 00-13
18 21 10 00 Water-Based Fire Protection Systems 21 10 00-10
19
20 DIVISION 22 - PLUMBING
21 Section Title Pages Thru
22 22 05 00 Common Work Results for Plumbing 22 05 00-11
23 22 05 13 Common Motor Requirements for Plumbing 22 05 13-3
24 22 05 14 Plumbing Specialties 22 05 14-5
25 22 05 15 Piping Specialties 22 05 15-3
26 22 05 23 General Duty Valves for Plumbing Piping 22 05 23-5
27 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 29-6
28 22 07 00 Plumbing Insulation 22 07 00-6
29 22 08 00 Commissioning of Plumbing 22 08 00-44
30 22 11 00 Facility Water Distribution 22 11 00-9
31 22 13 00 Facility Sanitary Sewerage 22 13 00-7
32 22 14 00 Facility Storm Drainage 22 14 00-7
33 22 30 00 Plumbing Equipment 22 30 00-6
34 22 42 00 Commercial Plumbing Fixtures 22 42 00-7
35
36 DIVISION 23 - HEATING, VENTILATING AND AIR CONDITIONING
37 Section Title Pages Thru
38 23 05 00 Common Work Results for HVAC 23 05 00-7
39 23 05 13 Common Motor Requirements for HVAC Equipment 23 05 13-4
40 23 05 14 Variable Frequency Drives 23 05 14-5
41 23 05 15 Piping Specialties 23 05 15-7
42 23 05 23 General Duty Valves for HVAC 23 05 23-7
43 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 29-4
44 23 05 48 Vibration and Seismic Controls for HVAC Piping and Equipment 23 05 48-4
45 23 05 93 Testing, Adjusting and Balancing for HVAC 23 05 93-5
46 23 07 00 HVAC Insulation 23 07 00-10
47 23 08 00 Commissioning of HVAC 23 08 00-168
48 23 09 14 Pneumatic and Electric Controls 23 09 14-18
49 23 09 15 Direct Digital Control Input/Output Point Summary Tables 23 09 15-8
50 23 09 24 Direct Digital Control System for HVAC (Informational Purposes Only) 23 09 24-14
51 23 09 93 Sequence of Operation for HVAC Controls 23 09 93-12
52 23 11 00 Facility Fuel Piping 23 11 00-6
53 23 21 13 Hydronic Piping 23 21 13-10
54 23 21 23 Hydronic Pumps 23 21 23-4
TC-3
1 23 22 13 Steam and Condensate Heating Piping 23 22 13-7
2 23 22 23 Steam Condensate Pumps 23 22 23-3
3 23 23 00 Refrigerant Piping 23 23 00-3
4 23 25 00 HVAC Water Treatment 23 25 00-4
5 23 31 00 HVAC Ducts and Casings 23 31 00-8
6 23 33 00 Air Duct Accessories 23 33 00-5
7 23 34 00 HVAC Fans 23 34 00-3
8 23 36 00 Air Terminal Units 23 36 00-5
9 23 37 13 Diffusers, Registers and Grilles 23 37 13-3
10 23 41 00 Particulate Air Filtration 23 41 00-3
11 23 57 00 Heat Exchangers for HVAC 23 57 00-2
12 23 62 13 Packaged Air-Cooled Refrigerant Compressor and Condensing Units 23 62 13-4
13 23 72 00 Air-To-Air Energy Recovery Equipment 23 72 00-5
14 23 73 12 Air Handling Unit Coils 23 73 12-3
15 23 73 13 Modular Indoor Central-Station Air-Handling Units 23 73 13-6
16 23 81 26 Split-System Ductless Air Conditioners 23 81 26-5
17 23 82 00 Heating and Cooling Terminal Units 23 82 00-3
18
19
20 VOLUME 4
21 DIVISION 26 - ELECTRICAL
22 Section Title Pages Thru
23 26 05 00 Common Work Results for Electrical 26 05 00-7
24 26 05 02 Electrical Demolition for Remodeling 26 05 02-3
25 26 05 04 Cleaning, Inspection and Testing of Electrical Equipment 26 05 04-4
26 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 19-5
27 26 05 23 Control-Voltage Electrical Power Cables 26 05 23-3
28 26 05 26 Grounding and Bonding for Electrical Systems 26 05 26-5
29 26 05 29 Hangers and Supports for Electrical Systems 26 05 29-4
30 26 05 33 Raceway and Boxes for Electrical Systems 26 05 33-10
31 26 05 53 Identification for Electrical Systems 26 05 53-3
32 26 05 73 Short Circuit/Coordination Study and Arc Flash Risk Assessment 26 05 73-5
33 26 08 00 Commissioning of Electrical 26 08 00-47
34 26 09 19 Enclosed Contactors 26 09 19-2
35 26 09 43 Distributed Digital Lighting Controls 26 09 43-9
36 26 24 16 Panelboards 26 24 16-4
37 26 27 02 Equipment Wiring Systems 26 27 02-4
38 26 27 26 Wiring Devices 26 27 26-8
39 26 27 28 Disconnect Switches 26 27 28-2
40 26 27 29 Elevator Distribution Equipment 26 27 29-3
41 26 32 13.16 Engine-Driven Generator Sets – Natural Gas (LP) 26 32 13.16-7
42 26 36 00 Transfer Switches 26 36 00-5
43 26 43 13 Surge Protective Devices for Low-Voltage Electrical Power Circuits 26 43 13-3
44 26 51 13 Interior Lighting Fixtures, Lamps, And Ballasts 26 51 13-6
45
46 DIVISION 27 - COMMUNICATIONS
47 Section Title Pages Thru
48 27 05 53 Identification for Communication Systems 27 05 53-4
49 27 08 00 Commissioning of Communications 27 08 00-20
50 27 10 00 Structured Cabling 27 10 00-18
51 27 11 00 Communications Room Equipment Fittings 27 11 00-3
52 27 16 19 Communications Patch Cords, Station Cords and Cross-Connect Wire 27 16 19-4
53 27 52 23 Nurse Call System 27 52 23-11
54
TC-4
1 DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
2 Section Title Pages Thru
3 28 08 00 Commissioning of Electronic Safety and Security 28 08 00-16
4 28 10 00 Access Control System 28 10 00-9
5 28 23 00 Video Surveillance System 28 23 00-7
6 28 26 05 Emergency Communication System 28 26 05-3
7 28 31 00 Fire Detection and Alarm 28 31 00-22
8
9 DIVISION 30 – CIVIL DIVISIONS
10 30 05 00 Common Work Results for All Exterior Work 30 05 00-5
11
12 DIVISION 31 - EARTHWORK
13 Section Title Pages Thru
14 31 00 00 Earthwork for Building 31 00 00-18
15 31 20 00 Earthmoving 31 20 00-6
16 31 23 16.13 Trenching 31 23 16.13-8
17 31 23 19 Dewatering 31 23 19-3
18 31 25 00 Erosion Control 31 25 00-4
19
20 DIVISION 32 – EXTERIOR IMPROVEMENTS
21 Section Title Pages Thru
22 32 11 23.33 Dense Graded Base 32 11 23.33-3
23 32 12 16.13 Plant Mix Asphalt Paving 32 12 16.13-3
24 32 31 13.43 Correctional Chain Link Fencing and Gates 32 31 13.43-7
25 32 91 13 Soil Preparation 32 91 13-3
26 32 92 19 Seeding 32 92 19-3
27
28 DIVISION 33 - UTILITIES
29 Section Title Pages Thru
30 33 30 00 Sanitary Sewerage Utilities 33 30 00-9
31 33 40 00 Storm Drainage Utilities 33 40 00-9
32
33
34 DRAWINGS - Bound Separately
35 Title Sheets Thru
36 Cover Sheet / Index T001
37 Wall Types / Abbreviations and Symbols T002
38
39 Civil C-
40 Project Location and General Notes C110
41 Existing Survey C111
42 Erosion Control Plan C120
43 Demolition Plan C130
44 Site and Utility Plan - Detailed C140
45 Grading and Storm Sewer Plan C150
46 Construction Details C500
47
48 Architectural A-
49 Overall Architectural Site Plan A001
50 Architectural Site Plan A002
51 Architectural Construction Site Plan A003
52 Architectural Site Details A004
53 Demolition Plans A100
54 Life Safety Plan / Code Review A101

TC-5
1 Lower Level Plan A102
2 First Floor Plan A103
3 Furniture Plan (Reference Only) A104
4 Roof Plan A105
5 Lower Level Reflected Ceiling Plan A201
6 First Floor Reflected Ceiling Plan A202
7 Exterior Elevations A301
8 Building Sections A401
9 Building Sections A402
10 Wall Sections A403
11 Wall Sections A404
12 Wall Sections A405
13 Enlarged Lower Level Plan - North A501
14 Enlarged Lower Level Plan – South A502
15 Enlarged First Floor Plan – North A503
16 Enlarged First Floor Plan – South A504
17 Interior Elevations A601
18 Interior Elevations A602
19 Details – Exterior A701
20 Details – Exterior A702
21 Details – Interior A703
22 Details – Casework A704
23 Door and Frame Schedule / Types and Details A801
24 Room Finish Schedule A901
25 Floor Pattern Plan – Lower Level A902
26
27 Food Service / Laundry FS-
28 First Floor – Food Service FS1
29 Lower Level – Food Service FS2
30 Food Service – MEP FS3
31
32 Structural S-
33 Foundation Plan S100
34 First Floor Framing Plan S101
35 Roof Framing Plan S102
36 Details S500
37 Details S501
38 Details S510
39 Details S511
40 Details S520
41 General Notes S900
42 Schedules S901
43
44 Fire Suppression F-
45 Lower Level Fire Protection Plan F100
46 First Floor Fire Protection Plan F101
47 Roof Framing Fire Protection Plan F102
48
49 Plumbing P-
50 Plumbing Schedules and Notes P000
51 Plumbing Demolition Plans P001
52 Enlarged Plumbing Demolition Plans P002
53 Lower Level Foundation Plumbing Plan P100
54 Lower Level Plumbing Plan P110
TC-6
1 First Floor Plumbing Plans P111
2 Enlarged Plumbing Plans P112
3 Plumbing Isometrics P200
4 Plumbing Isometrics P201
5
6 Heating, Ventilating and Air Conditioning M-
7 Mechanical Coversheet M000
8 Site Plan – Mechanical M050
9 Lower Level Demolition – Ventilation M100
10 First Floor Demolition - Ventilation M101
11 Lower Level Demolition – Piping M110
12 Lower Level – Ventilation M200
13 First Floor Plan – Ventilation M201
14 Lower Level – Piping M210
15 First Floor Plan – Piping M211
16 Roof Plan Mechanical M220
17 Mechanical Enlarged Plans M230
18 Mechanical Enlarged Plans M231
19 Section – Mechanical M240
20 Mechanical Details M300
21 Mechanical Details M301
22 Mechanical Details M302
23 Mechanical Details M303
24 Mechanical Flow Diagrams M400
25 Mechancial Flow Diagrams M401
26 Mechanical Schedules M500
27 Mechanical Schedules M501
28
29 Electrical E-
30 Electrical Coversheet E000
31 Site Plan – Electrical E050
32 Lower Level Demolition – Electrical ED100
33 First Floor Demolition – Electrical ED101
34 Lower Level – Lighting EL100
35 First Floor Plan – Lighting EL101
36 Lower Level – Power EP100
37 First Floor Plan – Power EP101
38 Lower Level – Fire Alarm ES100
39 First Floor Plan – Fire Alarm ES101
40 Electrical Details E300
41 Existing One-Line Diagram E400
42 New One Line Diagram E401
43 Electrical Schedules E500
44 Electrical Schedules E501
45
46

TC-7
1 Telecommunications Q-
2 Cover Sheet – Communications and Security Q000
3 Lower Level Demolition – Communications and Security QD100
4 Lower Level – Communications and Security Q100
5 First Floor Plan – Communications and Security Q101
6 Enlarged Plans – Communications and Security Q200
7 Details and Schedules – Communications and Security Q300
8 Details and Risers – Communications and Security Q301
9 General Communications and Security Equipment Schedule Q500
10 ***