ManPro Crashing
ManPro Crashing
ManPro Crashing
Waktu/mg
Normal Crash Normal Crash
a Merencanakan 10 - 10 10 500,000 500,000 -
b Memesan Mesin 2a 2 1 5,000,000 6,000,000 1,000,000
c Penyesuaian Mesin 8b 8 4 4,000,000 6,500,000 625,000
d Memesan Material dan Kerangka 4a 4 2 700,000 1,500,000 400,000
e Pembuatan Kerangka 3d 3 2 2,000,000 2,500,000 500,000
f Penyelesaian Kerangka 1e 1 1 1,000,000 1,000,000 -
g Memesan Mesin pada rangka sekaligu 5 c,f 5 4 500,000 600,000 100,000
13,700,000 18,600,000
11
1 7 C-4
B- 11
0 A - 10 10 15 G-4 19
1 2 5 6
0 10 D- 15 19
2 E-2 1
12 14 F-
3 4
Kegiatan Biaya Biaya Tambahan/mg 12 14
Normal Crash Biaya Normal 13,700,000
a 500,000 500,000 - Biaya Percepatan
b 5,000,000 6,000,000 1,000,000 b 1 Minggu 1,000,000
c 4,000,000 6,500,000 625,000 c 4 Minggu 2,500,000
d 700,000 1,500,000 400,000 d 2 Minggu 800,000
e 2,000,000 2,500,000 500,000 e 1 Minggu 500,000
f 1,000,000 1,000,000 -
g 500,000 600,000 100,000 g 1 Minggu 100,000
13,700,000 18,600,000 18,600,000