KegiatanKeterangan Pred Waktu Waktu Biaya Biaya Tambahan/mg

Waktu/mg
Normal Crash Normal Crash
a Merencanakan 10 - 10 10 500,000 500,000 -
b Memesan Mesin 2a 2 1 5,000,000 6,000,000 1,000,000
c Penyesuaian Mesin 8b 8 4 4,000,000 6,500,000 625,000
d Memesan Material dan Kerangka 4a 4 2 700,000 1,500,000 400,000
e Pembuatan Kerangka 3d 3 2 2,000,000 2,500,000 500,000
f Penyelesaian Kerangka 1e 1 1 1,000,000 1,000,000 -
g Memesan Mesin pada rangka sekaligu 5 c,f 5 4 500,000 600,000 100,000
13,700,000 18,600,000

11
1 7 C-4
B- 11
0 A - 10 10 15 G-4 19
1 2 5 6
0 10 D- 15 19
2 E-2 1
12 14 F-
3 4
Kegiatan Biaya Biaya Tambahan/mg 12 14
Normal Crash Biaya Normal 13,700,000
a 500,000 500,000 - Biaya Percepatan
b 5,000,000 6,000,000 1,000,000 b 1 Minggu 1,000,000
c 4,000,000 6,500,000 625,000 c 4 Minggu 2,500,000
d 700,000 1,500,000 400,000 d 2 Minggu 800,000
e 2,000,000 2,500,000 500,000 e 1 Minggu 500,000
f 1,000,000 1,000,000 -
g 500,000 600,000 100,000 g 1 Minggu 100,000
13,700,000 18,600,000 18,600,000

Kegiatan Biaya Biaya Tambahan/mg PredWaktWaktu


Waktu/mg
Normal Crash Biaya Normal 13,700,000 NormCrash
a 500,000 500,000 - Biaya Percepatan 10 - 10 10
b 5,000,000 6,000,000 1,000,000 b 1 Minggu 1,000,000 2a 2 1
c 4,000,000 6,500,000 1,250,000 c 2 Minggu 1,250,000 8b 8 2
d 700,000 1,500,000 - - - - 4a 4 2
e 2,000,000 2,500,000 - - - - 3d 3 2
f 1,000,000 1,000,000 - - - - 1e 1 1
g 500,000 600,000 100,000 g 1 Minggu 100,000 5 c,f 5 4
13,700,000 18,600,000 16,050,000
CP = a-d-e-f-g
11
7 C-2
1 13
B-
0 A - 10 10 15 G-4 19
1 2 5 6
0 10 D- 15 19
2 E-2 1
3
12
4
14 F-
12 14