Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Transportation Geotechnics 20 (2019) 100250

Contents lists available at ScienceDirect

Transportation Geotechnics
journal homepage: www.elsevier.com/locate/trgeo

Ground temperature characteristics during artificial freezing around a T


subway cross passage

Wenhu Fan1, Ping Yang
Department of Civil Engineering, Nanjing Forestry University, Nanjing 210037, China

A R T I C LE I N FO A B S T R A C T

Keywords: Artificial ground freezing (AGF) has been extensively used in the construction of subway cross passages in soft
Artificial ground freezing ground to ensure the safety of excavation. The temperature characteristics during freezing are of great interests,
Cross passage as it can be used to determine whether the frozen wall satisfies the design requirements in terms of dimension
Temperature characteristics and strength. This paper presents a detailed case study of a cross passage including the temperature variations in
Thermal model
brine and selected monitoring points around the passage based on the field testing results during freezing and
frozen wall maintenance. In particular, temperature data was collected at various depths along settlement ob-
servation holes installed on top of the frozen wall. It was found that the frozen wall development rate toward the
cross passage is 1.43 times faster than that away from the passage in the silt. A three-dimensional numerical
model was used to analyse the temperature distribution and was able to accurately reflect the temperature
distribution within the entire frozen zone with uneven distribution of the freezing pipes during freezing. This
paper provides a valuable case study of the temperature characteristics of a cross passage with uneven freezing
pipe distribution and a thermal model with complete thermal properties at both frozen and unfrozen status,
which can be useful for thermal model calibration and/or temperature field prediction in artificial freezing
engineering.

Introduction the safety of manual excavation. Currently, several approaches have


been used for investigating temperature characteristics, such as phy-
There are many risks in the construction of subway tunnels in soft sical model test, field investigation, and/or numerical simulation (e.g.
ground, especially when the tunnel boring machine starts or exits a [6,3,17]). However, very limited studies exist for the ground tem-
shield tunnel, or during cross passage excavation (e.g. [12,5,3,14]). perature characteristics around a cross passage, and little field mon-
Manual excavation is commonly used in the construction of a cross itoring data is available. Previous studies presented temperature data
passage, which results in more risks. Artificial ground freezing (AGF) collected from observation holes installed from subway tunnels (e.g.
with brine has been widely applied in the construction of cross passages [7,8]), but few studies paid attention to the temperature distribution on
to provide ground reinforcement and waterproof sealing to ensure the top of the frozen wall [11]. The thickness and strength of frozen
safety in manual excavation [1]. The freezing pipes used in AGF typi- wall on the top are of great importance to ensure safety in manual
cally contain two concentric pipes, as illustrated in Fig. 1. The outer excavation of cross passage. Furthermore, even though in-situ mon-
pipe with a closed conical end can be used to drill into the ground easily itoring can help reveal temperature information in selected locations,
and the inner one is open. The cold brine enters the inner pipe and then the overall thermal status of the whole frozen zone is still unclear and
returns through the gap between the outer pipe and inner pipe when it simplified finite element models such as a two-dimensional model are
reaches the tip of the inner pipe. Heat exchanging occurs between the often used to estimate temperature distribution along the transverse
cold brine and warmer soils. direction of a cross passage. Such simplified models are difficult to
The temperature characteristics at the frozen wall is among the most reflect the actual thermal status along the longitudinal direction of a
important information in artificial freezing engineering (AFE) as it is cross passage, especially when the freezing pipes are unevenly dis-
used to determine if the frozen wall satisfy the design requirements, tributed (e.g. [15]).
often prescribed in terms of dimension and strength, in order to ensure This paper presents a detailed case study of the in-situ thermal


Corresponding author at: No. 159 Longpan Road, School of Civil Engineering, Nanjing Forestry University, Nanjing, Jiangsu Province 210037, China.
E-mail address: yangping@njfu.edu.cn (P. Yang).
1
No. 159 Longpan Road, School of Civil Engineering, Nanjing Forestry University, Nanjing, Jiangsu Province 210037, China.

https://doi.org/10.1016/j.trgeo.2019.100250
Received 28 February 2019; Received in revised form 12 May 2019; Accepted 4 June 2019
Available online 05 June 2019
2214-3912/ © 2019 Published by Elsevier Ltd.
W. Fan and P. Yang Transportation Geotechnics 20 (2019) 100250

temperature observation holes (i.e. C3, C10, C12 and C13) were in-
stalled for monitoring the temperature on the top of the passage. Note
that, C12 and C13 were drilled from the ground surface, which were
used for settlement observation [11]. C11 was placed to monitor the
temperature changes in the area of drainage sump. It is worth noting
that the monitoring points were distributed at varying depths of holes
C12, C13, and C6 through C9, as indicated in Fig. 3.
The temperature of brine was set to less than −28 °C during
Fig. 1. Schematic of freezing pipe. freezing and was then set to be between −25 °C and −28 °C during
frozen wall maintenance for manual excavation. The design calls for a
freezing period of no less than 45 days, an average temperature of
status of a cross passage, during artificial ground freezing. Beside ob-
frozen wall of lower than −10 °C, and an effective thickness of no less
servation holes arranged at the sides of the cross passage, two ob-
than 1.8 m. The inlet and outlet temperature of the brine were also
servation holes on the top of frozen wall designed to for settlement
recorded during freezing and frozen wall maintenance.
monitoring were also used for temperature observation. Furthermore, a
three-dimensional numerical model is used to analyze the temperature
distributions of the cross passage along its longitudinal and transverse
Results and discussion
directions.
Temperature of the brine
Project overview
Fig. 4 presents the temperature of brine in the main freezing pipe.
The cross passage was located in silt and silt with sand, with poor The total freezing time was about 79 days, including 45 days during
stability during excavation if no treatment was performed. Therefore, freezing and 34 days of frozen wall maintenance for manual excavation.
the brine freezing method was utilized to reinforce the ground around During freezing, the temperature at both the inlet and outlet decreased
the cross passage. As shown in Fig. 2, a total of 66 freezing pipes rapidly and difference between them decreased from 2.1 °C to 0.8 °C.
(89 mm in diameter and 8 mm in wall thickness) were installed at After freezing for 22 days, the inlet temperature remained between
spacing varying from 215 mm to 1000 mm and 13 temperature ob- about −28 °C and −30 °C and the difference between inlet and outlet
servation holes labelled as C1 through C13 were prepared by using temperature was about 0.6 °C. During frozen wall maintenance, the
welded steel pipes. In the excavation, the temperature distribution on inlet temperature slowly warmed up to −26 °C for easier manual ex-
the sides and top of a cross passage should be closely monitored. Eight cavation and the difference was still about 0.6 °C.
temperature observation holes (i.e. C1, C2, and C4 through C9) were
utilized to monitor temperature development at both sides and four

Fig. 2. Arrangement of freezing pipes and temperature observation holes: (a) plan view, and (b) cross section.

2
W. Fan and P. Yang Transportation Geotechnics 20 (2019) 100250

Fig. 3. Monitoring locations: (a) C12 and C13, and (b) C6 through C9.

however, after the formation of closed frozen wall (stage III), the
temperature decreased with increasing depth of monitoring point. The
reason for that is the convection at the surface of concrete segments.
Compared with the temperature changes in C7 and C8 during frozen
wall maintenance, the temperature fluctuations of monitoring points in
C7 were more obviously than that in C8 due to the distance between
monitoring point and excavation face. The less the distance between
temperature observation hole and excavation face, the greater the
changes of temperature in monitoring points.

On the top of the cross passage


Fig. 6 shows the typical temperature changes in C12. At the be-
ginning of freezing for 18 days, the cooling rate was faster with the
closer to the freezing pipe. The average cooling rate increased from
0.1 °C/d for C12-3 to 2.1 °C/d for C12-1. After freezing for 45 days, the
temperatures of monitoring points were below 0 °C except for C12-3. In
the process of freezing, the temperature in C12-3 was higher than C12-
2, but the lowest was in C12-3. The temperature of C12-2 finally de-
creased to −16.9 °C after freezing for 45 days, which implies that the
Fig. 4. Temperature at the inlet and outlet of the main freezing pipe during the actual thickness of frozen wall was more than the designed value
ground freezing engineering project. (1.8 m). Moreover, the freeze equilibrium time increased from 18 days
for C12-1 to 60 days for C12-3, which indicated that the closer to the
freezing pipes, the less the freeze equilibrium time during freezing was.
Temperature variations at monitoring point
It resulted from different temperature gradient, which can be found in
laboratory tests [9,16]. The temperature data inside and outside of the
At the sides of the cross passage
frozen wall on the top are rarely observed in the previous studies, ex-
Fig. 5 presents the typical temperature changes of monitoring points
cept for Yang et al. [11].
in C7 and C8. C7 and C8 were at the inner side and outer side of the
frozen wall, respectively. It can be seen that the temperature changes of
Average development rate of frozen wall
different monitoring points were the same, which can be divided into
four stages. For example in C7, it lasted 7 days in stage I and the tem-
In the AFE, the average development rate of frozen wall is used to
perature of soils decreased rapidly with the average cooling rate of
estimate the thickness of the frozen wall, which means the average
1.9 °C/d. Then the temperature decreased slowly in stage II due to the
development rate of freezing front. The nearest distance between
formation of ice crystals and ice lenses, the average cooling rate was
temperature observation hole and freezing pipe for C7 and C8 were
about 0.6 °C/d. After 10 days, the closed frozen wall gradually occurred
both 30 cm (refer to Fig. 2). As is shown in Fig. 5, the time of the
and the temperature continued to decrease with the cooling rate of the
temperature reaches the freezing point (Tp) in C7 was 7 days but
decay (stage III). Finally, the temperature rose slightly or maintained
10 days in C8. Therefore, 4.29 cm/d and 3 cm/d were the average de-
unchanged in stage IV because of a slight increase in brine temperature
velopment rate of freezing front for C7 and C8, respectively. That is to
and small temperature difference between inlet and outlet of brine
say, the frozen wall development rate toward the cross passage is 1.43
(Fig. 4). In addition, the temperature increased with an increase in the
times faster than that away from the passage. The reason for this is that
depth of monitoring point at the beginning of freezing (stage I);
the degree of cold loss for outward development was more than that for

3
W. Fan and P. Yang Transportation Geotechnics 20 (2019) 100250

Fig. 5. Variation of temperature with time for monitoring points in C7 and C8.

Fig. 8. A schematic of the model.


Fig. 6. Variation of temperature with time for monitoring points in C12.
Table 1
Thermal parameters of material.
Material ρ Tp λu / λf Cu /Cf β
(kg/m3) (°C) (W/(m·°C)) (×106 J/ (W/(m2·°C))
(m3·°C))

Fill 1940 −0.44 1.60/2.20 2.72/2.13 8.5


Clay 1920 −0.50 1.60/2.20 2.69/2.11 –
Silty clay 1900 −0.40 1.50/2.20 2.66/2.09 –
Silt 1910 −0.31 1.60/2.00 2.29/2.10 –
Silt with sand 1890 −0.33 1.50/2.00 2.84/1.89 –
Concrete 2450 – 1.80 2.65 4.74
segment

inward development.
In order to verify the conclusion above, the typical distribution of
cooling rate at the same depth (e.g. C6-4–C9-4) during freezing is
shown in Fig. 7. It could be easily seen that the cooling rate of C7-4 was
faster than that of C8-4 at different time although they were at the same
distance from the freezing pipe. Besides that, even though C6-4 was far
away from the freezing pipe compared to C9-4, the cooling rate of C6-4
Fig. 7. Soil temperature cooling rate vs. distance from a freezing pipe at dif- still was a little bit higher at different freezing time. All of these in-
ferent freezing time. dicates that the frozen wall development rate toward the cross passage
was faster than that away from the passage.

4
W. Fan and P. Yang Transportation Geotechnics 20 (2019) 100250

Fig. 10. Path scheme for numerical analysis.

Boundary and initial conditions


Some assumptions in boundary conditions are used in this numer-
ical model. The convective boundary at the ground surface or concrete
segment surface can be expressed as the following equation:

∂T
λ = β (Tg − Ta)
∂n (1)

where at the ground surface, λ (W/(m·°C)) is thermal conductivity in


the fill, T (°C) is temperature in the fill, n is direction vector at the
ground surface, Ta is constant atmospheric temperature (15 °C) due to
the average atmospheric temperature this city in the construction of
this cross passage and Tg is temperature at the ground surface, β (W/
(m2·°C)) is convection diffusing-thermal coefficient of the ground sur-
face; however, at the surface of concrete segments, λ is thermal con-
ductivity in the concrete segments, T is temperature in the concrete
segments, n is direction vector at the surface of concrete segments, Ta is
constant environmental temperature in the tunnel (10 °C) and Tg is
temperature at the surface of concrete segments, β is convection dif-
fusing-thermal coefficient of the concrete segment surface.
Moreover, the boundary condition of freezing pipe is

T = Tb (2)

where Tb is average brine temperature of the outlet and inlet in the


freezing pipe (Fig. 4).
Other boundaries of the model are adiabatic without heat transfer
and convection, which can be can be indicated as:

∂T ∂T ∂T ⎞
λ⎛ ⎜ + + =0 ⎟

Fig. 9. Measured and numerical results of monitoring points: (a) C7-4, (b) C7-1 ⎝ ∂x ∂y ∂z ⎠ (3)
through C7-4, and (c) C6-4 through C8-4.
where λ and T are thermal conductivity and temperature, respectively.
Besides that, the initial conditions in three-dimensional temperature
Numerical model for thermal analysis during freezing
field are confirmed by the following equations:
Numerical model Tu |t = 0 = T0, Tf |t = 0 = f (x , y, z ) (4)

Fig. 8 shows the model of 40 m in width × 40 m in length × 45 m in where Tu and Tf are temperatures in the unfrozen and frozen zones,
depth built for computer simulation of the thermal field. The size is respectively, T0 is initial temperature of soils (19 °C), and f (x , y, z ) is
considered to be sufficient to minimize the boundary condition effects average temperature of frozen wall obtained by linear interpolation.
on the thermal status of the frozen wall. This model consists of five
different soil layers, subway tunnels and its concrete segments, and
freezing pipes. The numerical simulation was conducted by using Constitutive equation for thermal conduction problem
ADINA software. In the numerical analysis, the temperature field with phase change
and heat generation can be described by the following equation:

5
W. Fan and P. Yang Transportation Geotechnics 20 (2019) 100250

Fig. 11. Temperature distributions along paths: (a) path 1, and (b) path 2.

∂T ∂ 2T ∂ 2T ∂ 2T ⎞ freezing. It can be seen that the numerical results show a similar trend
C = λ⎛ 2 +
⎜ + ⎟
∂t ⎝ ∂x ∂y 2 ∂z 2 ⎠ (5) with the measured ones but relatively small in C7-4 (Fig. 9a). In the
same temperature observation hole for C7, the temperature is much
where C (J/(m3·°C)) is volumetric heat capacity. higher with shorter distance from concrete segment (Fig. 9b). Fur-
In the phase change interface between frozen and unfrozen zone, thermore, the obtained temperature is obviously lower with a decrease
the continuous condition and energy conservation condition should be in distance away from freezing pipe (Fig. 9c).
met, which can be expressed by following equations:
Tf (s (t ), t ) = Tu (s (t ), t ) = Tm (6) Analytical scheme

∂Tf ∂Tu ds (t ) In order to study the temperature characteristics of soils around the
λf − λu =L cross passage, path 1 and path 2 in the middle line of cross passage with
∂n1 ∂n1 dt (7)
different direction are chosen in the typical plan, which is 19 m away
L = L′·ρd ·(w − wu ) (8) from the ground surface (Fig. 10). 5 points and 11 points are selected in
paths 1 and 2, respectively.
where s (t ) is freezing front position at time t, Tm is temperature at the
freezing front position, λ f and λ u are thermal conductivities in the
Modelling results
frozen and unfrozen zones, respectively, n1 is the direction vector at the
frost front position, L (kJ/m3) is latent heat, L' is latent heat from
Fig. 11 shows the temperature distributions of paths 1 and 2. From
crystallizing or melting of water (3.3456 × 105 J/kg), ρd (kg/m3) is dry
Fig. 11a, it can be found that temperature in soils basically increases
soil density, w is total moisture content of soil, wu is unfrozen moisture
from up line to down line. The reason for that is the number of freezing
content of frozen soil.
pipes drilled from up line was more than that from down line and the
Moreover, the thermal conductivity λ and volumetric heat capacity
spacing among freezing pipes drilled from up line increased with an
C were evaluated by the following equations [4,10]:
increase in distance away from the left tunnel. Moreover, temperature
near the concrete segment is a little bit lower during the first 15 days,
⎧ λf (T < Tm − ΔT )
⎪ λu − λf but the result is opposite and becomes obvious after freezing for
λ = λf + [T − (Tm − ΔT )] (Tm − ΔT ⩽ T ⩽ Tm )
⎨ ΔT 25 days. It can be explained that temperature of soils near the concrete
⎪ λu (T > Tm) (9) segment is affected by the convection at the surface of concrete seg-

ment. Finally, temperature is still above 0 °C at the end of freezing,
⎧Cf (T < Tm − ΔT ) which means that soils in the middle of the cross passage were still
⎪ Cf + Cu L unfrozen. Furthermore, temperature along path 2 is similar to sym-
C= + (Tm − ΔT ⩽ T ⩽ Tm )
⎨ 2 ΔT
metrical distribution, in which temperature decreases with shorter
⎪Cu (T > Tm) (10)
⎩ distance away from freezing pipes (Fig. 11b).
where Cf and Cu are volumetric heat capacities in the frozen and un-
frozen zones, respectively, ΔT is temperature change of phase-change Conclusions
interface, the definitions in the interval, Tm − ΔT ≤ T ≤ Tm , may be
assumed [2]. The thermal parameters of materials in this model are This paper describes a detailed case study of the ground thermal
given in Table 1. Except for β used in Yang et al. [12] and Zhang and regime of a subway cross passage during artificial ground freezing. It
Liu [13], others were obtained by laboratory tests. presents the in-situ temperature monitoring results and a three-di-
mensional thermal model for thermal regime simulation during
freezing. The following conclusions can be drawn:
Calibration of the proposed numerical model
(1) Settlement observation hole can be used as temperature observa-
Fig. 9 demonstrates the numerical and measured temperature at
tion hole, and the temperature monitoring points can be distributed
aforementioned monitoring points of C7-1–C7-4 and C6-4–C9-4 during

6
W. Fan and P. Yang Transportation Geotechnics 20 (2019) 100250

at the different depths in the holes to identify the thickness of Sons; 2004.
frozen wall on the top. [2] Bonacina C, Comini G, Fasano A. Numerical solution of phase-change problems. Int
J Heat Mass Transf 1973;16(6):1832–52.
(2) The temperature monitoring data demonstrate that the frozen wall [3] Han L, Ye GL, Li YH, et al. In situ monitoring of frost heave pressure during cross
development rate toward the cross passage is faster than that away passage construction using ground-freezing method. Can Geotech J
from the passage. In this study, the frozen wall development rate 2015;53(3):530–9.
[4] Lai YM, Wang QS, Niu FJ, et al. Three-dimensional nonlinear analysis for tem-
toward the cross passage is 1.43 times faster than that away from perature characteristic of ventilated embankment in permafrost regions. Cold Reg
the passage in the silt. Sci Technol 2004;38(2):165–84.
(3) The numerical model can be used to evaluate the temperature [5] Li SY, Lai YM, Zhang MY, et al. Minimum ground pre-freezing time before ex-
cavation of Guangzhou subway tunnel. Cold Reg Sci Technol 2006;46(3):181–91.
distribution of the ground during freezing. The temperature in soils [6] Pimentel E, Papakonstantinou S, Anagnostou G. Numerical interpretation of tem-
increases in the longitudinal direction of a cross passage, while that perature distributions from three ground freezing applications in urban tunnelling.
in the transverse direction is quite symmetrical to the centre line of Tunn Undergr Space Technol 2012;28:57–69.
[7] Qiao WG, Li DY, Wu XZ. Survey analysis of freezing method applied to connected
the passage.
aisle in metro tunnel. Rock Soil Mech 2003;24(4):666–9.
[8] Tan W, Yang P, Jin M, et al. Application and survey of freezing method applied to
The temperature monitoring is very important and necessary in ultra-long Connected aisle in metro tunnel. Chin J Undergr Space Eng
artificial freezing engineering. Evaluation of the cooling rate in soils, 2010;6(5):1065–71.
[9] Wang SF, Yang ZH, Yang P. Structural change and volumetric shrinkage of clay due
and thickness and average temperature of frozen wall all depends on to freeze-thaw by 3D X-ray computed tomography. Cold Reg Sci Technol
the temperature data, which can be used to identify potential problems 2017;138:108–16.
in the application of artificial ground freezing, or determine whether [10] Xu XZ, Wang JC, Zhang LX. Frozen soils physics. Beijing: Science Press; 2001.
[11] Yang P, Chen J, Zhang SG, et al. Whole range monitoring for temperature and
the design parameters of frozen wall meet the requirements of ex- displacement fields of cross passage in soft soils by AGF. Chin J Geotech Eng
cavation. The temperature monitoring data presented here can be used 2017;39(12):2226–34.
to calibrate numerical model for simulating the cooling process of soils [12] Yang P, Ke JM, Wang JG, et al. Numerical simulation of frost heave with coupled
water freezing, temperature and stress fields in tunnel excavation. Comput Geotech
in artificial freezing engineering. 2006;33(6–7):330–40.
[13] Zhang JR, Liu ZQ. A study on the convective heat transfer coefficient of concrete in
Acknowledgements wind tunnel experiment. China Civ Eng J 2006;39(9):39–42.
[14] Zhang T, Yang P, Zhang YX. Investigation of frost-heaving characteristics of hor-
izontal-cup-shape frozen ground surface for reinforced end soil mass in shield
This study was supported by the National Natural Science tunnel construction. Period Polytech Civ Eng 2017;61(3):541–7.
Foundation of China (Grant No. 51478226), the Priority Academic [15] Zhao F, Hu XD. Coupling effect-based thawing of cross passages. J Tongji Univ (Nat
Sci) 2013;41(7):989–95.
Program Development of Jiangsu Higher Education Institutions, the
[16] Zhao XD, Zhou GQ, Lu GL, et al. Thermal gradient dependent deformation behavior
Doctorate Fellowship Foundation of Nanjing Forestry University, the of frozen soil and its mechanism at temperature close to 0 °C. Cold Reg Sci Technol
National First-class Disciplines, and research project of China Railway 2017;135:105–15.
18th Bureau Group Co., Ltd (Grant No. PG0084-2014). [17] Zhou J, Tang YQ. Centrifuge experimental study of thaw settlement characteristics
of mucky clay after artificial ground freezing. Eng Geol 2015;190:98–108.

References

[1] Andersland OB, Ladanyi B. Frozen ground engineering. Hoboken: John Wiley &

You might also like