MBS SOP-122 Non Conformance
MBS SOP-122 Non Conformance
Contents
1. Introduction......................................................................................................................................................................................................... 2
2. Scope and Purpose.............................................................................................................................................................................................. 2
3. Who Does What and How Summary Table..........................................................................................................................................................4
4. Flowchart of Key Activities................................................................................................................................................................................... 5
5. Description of Key Activities and Responsibilities................................................................................................................................................6
6. KPI........................................................................................................................................................................................................................ 8
7. Documents and Records Management................................................................................................................................................................9
8. Review & Improvement..................................................................................................................................................................................... 10
9. Appendices - Insert details as required..............................................................................................................................................................10
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 1 of 11
1. Introduction
Throughout the duration of construction projects where project management is outsourced; and where non-complying with any of contractual or statutory
requirements pertaining to the project are detected; then the person/ party who detects this non-compliance with requirements “The Originator” can issue an
NCR to the person/ party who commit this non-compliance with the requirements “The Receiver” who is bound to conduct a proper, approved remedial action
and come back to the Originator for verification and closing this NCR.
This SOP is applicable to all construction projects which are managed in house by an outsourced Project Manager
This SOP defines the approach to be followed to record, communicate and address any construction 'non-conformance'
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 2 of 11
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 3 of 11
Originator (Employer, PMC or Detects a case of non-compliance with project By checking work in progress/ completed works against
Engineer) contractual or statutory requirements. Contractual and statutory requirements.
Originator Issues a Non Conforming Report (NCR) to the By using approved form for a particular project.
“Receiver”.
Receiver (PMC, Engineer or Receives NCR and propose a proper remedial By using “NCR Closure Sheet”.
Contractor) action.
Originator Reviews the proposed remedial action and By filling in the same “NCR Closure Sheet”
approve/ reject the same prior to implementation.
Receiver (In case of a rejected Reviews the core subject of NCR to propose By using a new “NCR Closure Sheet”.
proposed remedial action) another remedial action
Receiver (In case of an approved Implements approved proposed remedial action In line with contractual and statutory requirements.
proposed remedial action)
Receiver Submits the implemented remedial action for the By filling in the space designed for this purpose in the “NCR
Originator for review and approval. Closure Sheet”
Originator Checks implemented remedial action(s) for Using the specified space in the NCR Closure Sheet
suitability and approves the same
Originator Close out NCR Upon giving approval to implemented remedial action,
Originator will close NCR using NCR form.
Originator & Receiver Update NCR log sheet(s) accordingly and notify NCR log sheet will be updated by both parties. Originator will
other project partners notify other project parties
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 4 of 11
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 5 of 11
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 6 of 11
The ‘Responsibility Matrix’ defined below illustrates key leadership and management responsibilities related to this procedure.
These responsibilities are defined as follows:
Other Project
Originator
Activity
Receiver
Parties
Key Activities Description
ID
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 7 of 11
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 8 of 11
6. KPI
Key Measurement
KPI Calculation Frequency Target KPI
Description
[KPI / PI calculation method
[KPI / PI title] [KPI / PI Description] [measurement frequency] [agreed KPI / PI target]
and/or equation]
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 9 of 11
Insert small description of who is responsible to update and revise this SOP and also communicate the SOP to the concerned stakeholders.
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 10 of 11
All division heads shall review the effectiveness of the systems, processes and procedures related to business activities within their specific area of control at
least once each year.
In completing their review the respective division heads shall ensure that feedback and recommendations are provided by relevant technical specialists.
As an outcome of the review, Construction Director shall recommend potential improvements to Musanada Building Services Executive Director.
Musanada corporate management will review the summarized performance relating to corrective and preventive actions throughout Business and Support
divisions to verify the overall effectiveness of the Musanada Integrated Management System and initiate actions applicable to business and support divisions
MBS SOP 122 3.0 Construction - Non Conformance - Outsourced PM, Standard Operating Procedure Effective date 5/16/2012 4:03:00 PM Page 11 of 11