CONSTRUCTION, COMPLETION, FURNISHING AND MAINTENANCE FOR


KUWAIT INTERNATIONAL AIRPORT
NEW PASSENGER TERMINAL
(TERMINAL II)

Inspection and Test Plan – Metal Wall Cladding System of Fixed Bridge Type C
& Type F @ T2 (Type: EWS-501 & EWS-502)

Doc. No: LKW-FCD-ITP-000010 Rev.01

LİMAK İNŞAAT SANAYİ ve TİCARET A.Ş.


Date
Signature of Contractor or authorized
06.10.2022 representative required as per contract
documents Section 01 78 39 Clause 1.04
and section 01 33 00 accordingly.
Revision History

Subcontractor Doc. Number: WHLY-FCD-ITP-000010 Rev.01

APPROVAL
Prepared
Rev. Description / by Checked by Approved by
No Date Reason for
Subcontractor Technical Office Deputy Construction
Issue Limak Engineer QAQC Manager HSE Manager
Manager Manager
1st Issue for Mohammed
A 25.06.2022 Internal Sahin Sevgi Selcuk Bekir Oghzan Yenilmaz Evren Bingol
Fetoh
Revıew
1st Official Mohammed
00 27.06.2022 Sahin Sevgi Selcuk Bekir Oghzan Yenilmaz Evren Bingol
Submission Fetoh
Wuhan
2nd official Mohammed
B 29.09.2022 Sahin Sevgi Selcuk Bekir Oghzan Yenilmaz Evren Bingol
Submissions Fetoh

2nd Official Mohammed


01 06.10.2022 Sahin Sevgi Selcuk Bekir Oghzan Yenilmaz Evren Bingol
Submission Fetoh
Comments.
1-This ITP must be revised if any changes in the sequence of inspection and any physical inspection
required
Construction, Completion, Furnishing, and Maintenance for Kuwait
International Airport New Passenger Terminal II
SPA/214

COMMENT RESPONSE SHEET

Doc. Title: Inspection and Test Plan – Metal Wall Cladding System of Fixed

Bridge Type C & Type F @ T2 (Type: EWS-501 & EWS-502)


Date: 22/09/2022

Response for Doc. No: WHLY-FCD-ITP-000010 Rev.00


SN Consultant Comments Contractor's Response
General Comments:
Refer to the comments on the document and
Noted, all comments have been addressed in
1 revise including all required inspection check
related activities.
point to avoid any abortive work at the site.
Refer to the comments on the related MAS,
2 calculation and drawing provide mock-up to Noted.
execute the work.
Comments:
1 Page 16.Include bend test. Noted and revised in related activity.
2 Page 16.IRF though ACONEX. Revised in related activity.
Page 18.F.3.Surface Preparation and Primer
3 Touch up Application (welding area) Noted and revised in related activity.

4 Page 18.Each welded area Noted and revised in related activity.


Page 18.Compliance with AWS D1.1,Clause
5 Noted and revised in related activity.
7.7.3&7.7.5

6 Page 18.H.H.W.W.S/R Noted and revised in related activity.

Page 18.3r party paint report report through


7 Noted and revised in related activity.
Aconex LKW-QAC-CHL -000288
Page 18.
1. F.4 Checks Survey Inspection of Installed
Stud prior to installed Bracket.
8 Survey Inspection will be for the installed panels
2. Each section
3. H.H.H.H.H
4. IRF Through Aconex Survey Report
Page 18.F.5 Split item#F.5 for physical
9 Noted.
inspection as required
Page 19.
1. F.6 Bolt Tightening of Bracket and Aluminum
frame
2. Spec.07 42 13, Part-3, CI.3.02Bc
Noted.Approved third party will do bolt tightening
3. Each Section
10 for brackets and 3rd bolt tightening report will be
4. Torque valus subject to manufacturer
submit through ACONEX.
technical data sheet
5. H.H.H.H.W
6. IRF through Aconex Bolt Tightening report
by 3rd pariy

Form No: PSF-QAC-030 page 1 Rev.01


Construction, Completion, Furnishing, and Maintenance for Kuwait
International Airport New Passenger Terminal II
SPA/214

COMMENT RESPONSE SHEET

Page 20.
1. F.8 Survey check of installed Aluminum
Panel (Line & Level)
2. Spc. 07 42 13,part-3 Cl.3.03 A.1
11 Noted and revised in related activity.
3. Each Section
4. Refer clause and provide values
5. H.H.H.H.H
6. IRF through ACONEX Survey Report

Form No: PSF-QAC-030 page 2 Rev.01


MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No
A Document Review
Confirm approval of  Spec. 07 42 13 Before the work  Document and Drawing Review All documents and
A.1 documentation for works  Spec. 05 41 00 commencement Status(All Status shall comply A/B) H R H H R reports to be reviewed
described herein; Company Approval  All B Status comments are addressed through ACONEX WF
 Company Approval  LET-MPW-LKW-12-0114
 Inspection and Test Inspection and Test Plan
Plan (ITP)  LKW-FCD-ITP-000010
 All Approved Material Material Approval Submission
Submissions along with  MAS-LKW-MPW-000862
Samples  MAS-LKW-MPW-001270
 Approved Shop  MAS-LKW-MPW-001897
Drawings  MAS-LKW-MPW-002345
 Third Party Approvals  MAS-LKW-MPW-002176
 Method Statements  MAS-LKW-MPW-000666
 Structure Calculations Approved Shop Drawings
 Thermal Calculations  WHLY-FCD-DWG-02-900-XX-
 Table top mock up 2750059
 LEED Compliance  WHLY-FCD-DWG-02-900-XX-
Certificates along for 2750065
each specific Material  WHLY-FCD-DWG-02-900-XX-
Submittal 2750067
 WPS/PQR  WHLY-FCD-DWG-02-900-XX-
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072
Third Party Approvals
 LET-MPW-LKW-18-0142
 LET-MPW-LKW-19-0548
 LET-MPW-LKW-19-0474
 LET-MPW-LKW-19-0603
Method Statement
Page 1 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 LKW-FCD-MST-000009
Structure Calculation Report
 WHLY-FCD-CAL-000114
Thermal Calculation Report
 WHLY-FCD-CAL-000115
Table top mock up(EWS-501)
 MAS-LKW-MPW-001195
WPS/PQR
 LKW-STR-PRO-000043
 ISO 9001:2015
 SBT-WTRAN-000016
 SBT-WTRAN-000015
 LKW-WTRAN-174364

B Testing Prior to Construction(in China)

Page 2 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

B.1 Metal Wall Cladding  Spec. 07 42 13 Before the work Pre-load at 50% of the positive design wind Material Test Certificate
System(PMU test for EWS- o Part 1 Clause 1.04 commencement load H H R W H Test Reports Through
101 with Fixed Bridge C,H,I,J,K • Pre-load the specimen at + 618 Pa ACONEX WF.
interface):  Spec. 05 41 00 (50% of the higher positive design wind
 Pre-load at 50% of the o Part 1 Clause 1.04 C,F load) for 10 seconds.
positive design wind  ASTM E 283 • No separation, plastic deformations or
load  ASTM E331 deleterious should be observed.
 Air infiltration  AAMA 501.1
 Static water  ASTM E 330 Air infiltration
penetration test  AAMA 501.4 • Positive static pressure + 600 Pa.
 Dynamic Water  AAMA 501.5 • Air leakage of fixed wall area shall not
Penetration test  NFPA 251 exceed 1.5m³/Hr/sqm.
 100% Structural  ISO 10140 -2: 2010
performance Test  LKW-FCD-MST-000009 Static Water Penetration Test
 Seismic Racking Test  WHLY-FCD-REP-000013 • Test shall be in accordance with ASTM
 Thermal cycling test E331, this pressure to be+600
 Structural safety test Pa.Adjust the water spray to the
with 1.5 times wind specified rate of 3.4L/m2.min.
pressure • The total time of test is no less than 15
 Impact test according minutes with water flow rate
to ANSI Z97.1 .for class 3.4L/m2.min. Remove the air pressure
A glazing difference and stop the water spray.
 Safety event Seismic
performance test Dynamic Water Penetration Test
• Dynamic water penetration testing is
conducted at the specified air pressure
differential by utilizing a wind
generator employing an 84" diameter
propeller.Water is simultaneously
sprayed on to the exterior face of the
Page 3 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

assembly at the required rate of


3.4L/m2 .min.
• The total time of test is no less than 15
minutes.
• Dynamic wind speed shall be
equivalent to a static air pressure
difference of +600 Pa.
• There shall be no water infiltration.

100% Structural performance Test


• Apply 50% of the design wind load and
maintain for 10s; Apply 100% of the
design wind load and maintain for
10s. Record transducer readings.
• Reduce the pressure differences to
zero and after a recovery period to
allow stabilization of the test
specimen, record permanent
deformation. The recovery period for
stabilization shall not be less than 1
min nor more than 5 min at zero load.
• No permanent distortion of anchors,
frames, panels.
• Structural silicone shall experience no
adhesive and/or cohesive failure along
any glass or panel edge. Glazing
gaskets may not disengage and
weather seals must not fail.
• Maximum Deflection at wind Load:
L/175 or 19mm (which is less) of the
Page 4 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

clear span of the component part, L/60


or 25mm which is less for the glass.

Seismic Racking Test


• Horizontal drift in plane: (Left and
Right) ±10mm @ top of steel structure.
• All functions remain unimpaired with
no visible damage.
• No glass breakage or glass fallout is
allowed.
• Post design displacement performance
for air infiltration, water leakage and
structural performance shall be
attained without adjustments or
repair.

Thermal cycling Test


• During the first hour, increase the
weather side conditions to60±3℃.
• Maintain these conditions for a
minimum of two hours.
• Adjust the weather side temperature
to 24±3℃ in a minimum of one hour.
• Repeat this cycle 3 times.
• There shall be no permanent damage
due to expansion and contraction.
• The test specimen should be able to
comply with the project specified
requirements for air leakage and water

Page 5 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

resistance after the thermal cycling


test.

Structural safety test with 1.5 times wind


pressure
• Apply 75% of the design wind load and
maintain for 10s; Apply 150% of
the design wind load and maintain for
10s. Record transducer readings.
• There shall be no metal failure, gasket
dislodgment, glass breakage, glass
disengagement from frame.
• Residual net deflections to be less than
0.2% of clear span.

Impact test according to ANSI Z97.1 .for class


A glazing
• Remove all masking and protective
material from the test pieces. The
specimens condition to a uniform test
temperature between 18-29 °C for at
least 4 hours to ensure uniform
temperature throughout each
specimen at the time of test.
• Raise the impactor to the drop height
between 1219mm and 1232mm and
stabilize it, the suspension device shall
be taut and axes of the impactor and
cable shall be in line.

Page 6 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

• The impactor,stabilized in launch


position in a vertical plane normal to
the test specimen, is release and falls
without initial velocity or axial rotaion.

Safety event Seismic performance test


• Horizontal drift in plane: (Left and
Right)±15mm@ top of steel structure.
• Displacement in horizontal test shall
consist of 3 cycles.
• Hold specimen at maximum
displacement for each stroke to
perform thorough inspection of the
exterior and interior surfaces.
• Some failure of vertical panes of
tempered or heat strengthened glass.
• Cracking of laminated glass but glass
remains in place.
• All glass is retained completely in the
glazed opening with no glass fallout
and no wall components fall off.

Fire resistance test


• Fire Resistance: The measure of the
ability of a material, product, or
assembly to withstand fire or give
protection from it.
• The underside of the specimen will be
exposed to fire test condition during
the test.
Page 7 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

• Not more than 5 min before the


commencement of the test, the initial
temperatures recorded by all
thermoplastic shall be checked to
ensure consistency and the datum
values shall be established. Similar
datum values shall be obtained, e.g. for
deflection, as appropriate, and the
initial condition of the test specimen
shall be noted.
• The initial average temperature of the
internal thermocouples, if used, and of
the unexposed surface temperature of
the specimen shall be in the range of
10。C to 40。C and shall not differ
from the initial ambient temperature
by more than 5 K.
• Prior to the commencement of the
test, the furnace temperature shall be
less than 50 °C.The commencement of
the test shall be considered the
moment when the programme to
follow the heating curve has been
initiated (igniting the burners). The
elapsed time shall be measured from
this point and all manual and
automatic systems for measurement
and observation shall begin or shall be
in operation at this time, and the

Page 8 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

furnace shall be controlled to comply


with the temperature conditions.

C Material
C.1 Shear stud  MAS-LKW-MPW-000862 Upon Delivery  Type:Types:M12*40 H - H H H  MIR
 Spec. 07 42 13  Steel grade:Grade 4.8  Delivery Note
o Part-1 Clause 1.03 F,8  Tensile strength:min. 490MPa  Material Certificate
 WHLY-FCD-DWG-02-900-XX-  Yield strength :min. 245MPa (MTC)
2750059  Elongation(G=2in):min.40%
 WHLY-FCD-DWG-02-900-XX-  Material confirming to approved MAS
2750065
 WHLY-FCD-DWG-02-900-XX-
2750067
 WHLY-FCD-DWG-02-900-XX-
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072

Page 9 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 ASTM A 307
 AWS D1.6/D1.6M: 2017
 LKW-FCD-MST-000009

C.2 Aluminum panel (#240 PVDF)  MAS-LKW-MPW-001270 Upon Delivery  Thickness:3mm H - H H H  MIR
 Spec. 07 42 13  Yield Strength:min.125MPa  Delivery Note
o Part-2 Clause 2.01 A  Tensile strength:145~185MPa  Material Certificate
 WHLY-FCD-DWG-02-900-XX-  Elongation:≥5% (MTC)
2750059  Material confirming to approved MAS  3RD Party Certified
 WHLY-FCD-DWG-02-900-XX- Fabrication Reports
2750065  Material test report
 WHLY-FCD-DWG-02-900-XX- certified by 3rd
2750067 party
 WHLY-FCD-DWG-02-900-XX-
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072
 AAMA 611
 ASTM B209
 LKW-FCD-MST-000007
 LET-LKW-MPW-01355

Page 10 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

C.3 Aluminum Foil  MAS-LKW-MPW-001897 Upon Delivery  Water Vapor Transmission Rate:< H - H H H  MIR
 Spec. 07 42 13 0.02g/(m2·h)  Delivery Note
o Part-3 Clause 3.02 F,1  Performance:<4×10(-9)g/(m2.s.Pa)  Material Certificate
 WHLY-FCD-DWG-02-900-XX-  Thickness:0.6mm (MTC)
2750059  Material confirming to approved MAS
 WHLY-FCD-DWG-02-900-XX-
2750065
 WHLY-FCD-DWG-02-900-XX-
2750067
 WHLY-FCD-DWG-02-900-XX-
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072
 DIN 52123
 ASTM D1000
 ASTM D36
 LKW-FCD-MST-000009

C.4 Gypsum board  MAS-LKW-MPW-002435 Upon Delivery  Fire Rating: 60 Minutes H - H H H  MIR
 Spec. 07 42 13  Total Acoustic Performance: 54db R’  Delivery Note
o Part-2 Clause 2.02 K w  Material Certificate
 WHLY-FCD-DWG-02-900-XX-  Width Of Partition: 100.00 mm (MTC)
2750059  Impact Rating: Severe Duty
 WHLY-FCD-DWG-02-900-XX-  Racking Resistance: Category 1
2750065  Material confirming to approved MAS
 WHLY-FCD-DWG-02-900-XX-
2750067
 WHLY-FCD-DWG-02-900-XX-
2750068

Page 11 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 WHLY-FCD-DWG-02-900-XX-
2750072
 ASTM C1185
 ASTM C1186-08(2016)
 LKW-FCD-MST-000009

C.5 Aluminum Profile  MAS-LKW-MPW-002176 Upon Delivery  Material:6063-T5 H - H H H  MIR


 Spec. 07 42 13  Average thickness:≥20μm  Delivery Note
o Part-1 Clause 1.02 B,3,c  Local thickness:≥18μm  Material Certificate
 WHLY-FCD-DWG-02-900-XX-  Seal mg/d ㎡:≤30 (MTC)
2750059  CASS test of protection(24h):≥9
 WHLY-FCD-DWG-02-900-XX-  Abrasion resistance (f) /(g/μm):≥300
2750065  Material confirming to approved MAS
 WHLY-FCD-DWG-02-900-XX-
2750067
 WHLY-FCD-DWG-02-900-XX-
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072
 ASTM 653M
 LKW-FCD-MST-000009

Page 12 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

C.6 Thermal insulation  MAS-LKW-MPW-000666 Upon Delivery  Thickness:40~150mm H - H H H  MIR


 Spec. 07 42 13  Density:60kg/m³  Delivery Note
o Part-2 Clause 2.01 E  Size(L*W):1200mm*600mm  Material Certificate
 WHLY-FCD-DWG-02-900-XX-  Maximum Service Temperature:450℃ (MTC)
2750059  Water Vapor Absorption ≤ 5%
 WHLY-FCD-DWG-02-900-XX-  Combustion Property:Surface
2750065  Burning characteristics: Smoke
 WHLY-FCD-DWG-02-900-XX-  Development≤ 50,Flame spread≤ 25
2750067  No visible damage during material
 WHLY-FCD-DWG-02-900-XX- transportation
2750068  Please refer to related MAS for more
 WHLY-FCD-DWG-02-900-XX- details about storage and packing
2750072  Materials will deliver to site with
 ASTM C612 protection coverings that are resistant
 ASTM E136 to all weather.
 LKW-FCD-MST-000009  Material confirming to approved MAS

D Site Mock-Up/Benchmark
D.1 Mock-Up  Spec. 07 42 13 Before installation  Site mock up is achieved and found  IRF (Through
o Part-1 Clause 1.05 E,8 work acceptable H H H H H ACONEX)
 Approved Mock-up drawing. commencement  Mock-ups of each Type as shown on  LKW-QAC-CHL-
 WHLY-FCD-DWG-02-900-XX- the Design drawings. 000192
2780015  Build mock-up on temporary
 WHLY-FCD-DWG-02-900-XX- supporting structures that will allow
2780016 inspection of internal and external
 LKW-FCD-MST-000009 surfaces.
Table-top mock-up  Place mock-up outside so that the
 MAS-LKW-MPW-001195 effects of sunlight and shade can be
assessed.
Page 13 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 Mock-ups will be retained for the


duration of the works.

D.2 Quality Benchmark  Spec. 07 42 13 Before installation  Approval of quality benchmark  IRF (Through
o Part-1 Clause 1.05 E,9 work installations is required before H H H H H ACONEX)
 LKW-FCD-MST-000009 commencement proceeding with remaining  LKW-QAC-CHL-
 MAS-LKW-MPW-001195 installation. 000192
 Build job site quality benchmark
installations to verify selections made
under sample submittals and to
demonstrate aesthetic effects and set
quality standards for workmanship and
installation.
 Field testing shall be performed on
quality benchmark in accordance with
the Field Testing Activity Section in this
ITP.
 Approved quality benchmark
installations may become part of the
completed Work if undisturbed at time
of Substantial Completion.

Page 14 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

E Site Preparation / Inspection


E.1 Inspecting of existing steel  Spec. Section 07 42 13, Prior to Installation  Check the position of all elements of  Approved Final IRF
structure o Part -2 Clause 2.06 the building structure and verify with H - H S/W S/W from Steel
I.a&b&c&d Activity F.1 subcontractor (AIC)
 LKW-FCD-MST-000009  Proceed with installation only after  LKW-QAC-CHL-
 Approved Shop drawings unsatisfactory conditions have been 000192
 WHLY-FCD-DWG-02-900-XX- corrected. For example, severe
2750059 deformation of steel structure and
 WHLY-FCD-DWG-02-900-XX- excessive error are unacceptable.
2750065 Needs to be corrected.
 WHLY-FCD-DWG-02-900-XX- Tolerance
2750067  Installed steel structure Tolerance +/-
 WHLY-FCD-DWG-02-900-XX- 10 mm in all direction.
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072
 AIC-STR-SHP-02-900-NF-
1150002
 AIC-STR-SHP-02-900-NF-
1150017
 AIC-STR-SHP-02-900-NF-
1150028

F Installation of Metal Wall Cladding System


F.1 Stud installation (Welding  Spec. Section 07 42 13  100% Visual  Stud welding size will follow the  3rd party
Visual Inspection and MT and o Part-2. Clause 2.06 D Inspection approved shop drawing and calculation H H - R R Inspection Report
bend test)  Approved Method Statement  All partial  Welding visually checked for weld Through ACONEX
 LKW-FCD-MST-000009 penetrations defects such as crack, porosity,
Page 15 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 AWS D1.6 and fillet undercut etc as per AWS D1.1 &  3rd Party Certified
 Approved Typical details Shop welds(25%) of inspection is found acceptable Bend Test Report
drawings Studs  Stud welding will use a special Through Aconex
 WHLY-FCD-DWG-02-900-XX- automatic welding machine welding to  LKW-QAC-CHL-
2750059 the steel structure has been 000192
 WHLY-FCD-DWG-02-900-XX- completed, the tolerance control at + /
2750065 - 5 mm
 WHLY-FCD-DWG-02-900-XX-  Visual read-through of studs on the
2750067 front face of panels shall not be
 WHLY-FCD-DWG-02-900-XX- acceptable.
2750068  The weld section shall not exhibit any
 WHLY-FCD-DWG-02-900-XX- tearing or cracking.
2750072  The test studs shall be subjected to a
 WHLY-FCD-WPS-001 30-degree bend test by striking them
 LKW-STR-PRO-000043 with a heavy hammer and the bend
test shall be considered acceptable if
the fracture occurs in the shank not in
the weld.
 Bend Test. Studs shall be tested by
alternately bending 30° in opposite
directions in a typical test fixture until
failure occurs. Alternately, studs may
be bent 90° from their original
axis. The procedure shall be considered
qualified if all studs in the set tested
are bent to 90° with no fractures
occurring in the weld.

Page 16 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

F.2 Weld Repair(If any)  Spec. Section 07 42 13 When Required  Refer AWS D1.1 accordingly.  IRF(Through
o Part-2. Clause 2.06 D  Repairs made by welding shall be done H - H W W ACONEX)
 Approved Method Statement in compliance with the requirements  LKW-QAC-CHL-
 LKW-FCD-MST-000009 of AWS D1.1 Clause 7.7.3&7.7.5 and 000192
 AWS D1.6 the accepted welding procedures
 Approved Typical details Shop  Stud welding:Oxide-free base metal
drawings shielded with argon gas, 99.95% pure.
 WHLY-FCD-DWG-02-900-XX-
2750059
 WHLY-FCD-DWG-02-900-XX-
2750065
 WHLY-FCD-DWG-02-900-XX-
2750067
 WHLY-FCD-DWG-02-900-XX-
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072
 WHLY-FCD-WPS-001
 LKW-STR-PRO-000043

F.3 Surface Preparation and  Spec. Section 08 44 13 Each welded area  100 microns shall be applied for H H W W S/R  Related
Primer Touch up Application o Part-2. Clause 2.06 D primer subcontractor IRF
(welding area) Method statement  Use spray application for painting. The ref. No. will be
 LKW-FCD-MST-000009 minimum thickness shall be mentioned.
 LKW-STR-MST-000047 Rev.03 maintained on all corners, edges and
Clause 5.9 and Clause 6 ends of pieces.
 AWS D1.1,Clause 7.7.3&7.7.5  Painted surface no sagging or winking
 The damaged surface shall be cleaned
with power brush / disc sander or by
sandpaper

Page 17 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 Touch up painting shall overlap the


adjacent sound primer by 25 mm
overlap
 Refer to manufacturer's technical
data:It is important that the surface
is completely clean to ensure the
adhesion. Any oil, grease, etc. to be
removed by suitable detergent.
 Sand paper the edges of the intact
paint around the cleaned areas to
feather the edges.
 Touch-up with Hempel Hempadur
Fastdry 17410 to the existing film
thickness using brush

F.4 Installation of Gypsum  Spec. Section 07 42 13 Each Bay  According to approved shop  LKW-QAC-CHL-
Board, C shape steel support o Part-1. Clause 1.04 T,1 drawings/details and method of H - H H W 000192
and Rock Wool for System o Part-3. Clause 3.02 D statement.  IRF(Through
EWS-502. o Part-3 Clause 3.02 E  Size follow the approved shop drawing ACONEX)
o Part-3 Clause 3.02 F and calculation.
 Approved Method Statement  Install all anchors and supports in full
 LKW-FCD-MST-000009 compliance with the performance
 Approved Typical details Shop criteria specified without distress to
drawings any component or assembly or panel
 WHLY-FCD-DWG-02-900-XX- joint integrity.
2750059  Brackets outside or through the vapor
 WHLY-FCD-DWG-02-900-XX- retarder.
2750065

Page 18 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 WHLY-FCD-DWG-02-900-XX-  After located the right place, clamping


2750067 the nuts, and proceed with the torque
 WHLY-FCD-DWG-02-900-XX- test as per the specification.
2750068  Do not install damaged components.
 WHLY-FCD-DWG-02-900-XX-  Rigidly secure non-moving joints.
2750072  Install anchors with separators and
isolators to prevent metal corrosion,
electrolytic deterioration, and
impediments to movement of joints.
 Gypsum boards shall be mold/ fungus
and vermin resistant, moisture
resistant, and resistant to dimensional
changes when exposed to variations in
temperature and moisture.
 Insulation shall be cut/trimmed to fit
between metal deck and gypsum
board.
 Coordinate installing roofing system
components so insulation is not
exposed to precipitation or left
exposed at the end of the workday.
 Comply with insulation manufacturer's
written instructions for installing roof
insulation.
 Cut and fit insulation within 6 mm of
nails, projections, and penetrations.
 Steel frame size will follow the
approved shop drawing and calculation
 Install membrane in accordance with
manufacturer's recommendations

Page 19 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 Ensure surface and free from


punctures.
 Ensure that all aluminum foils are
continuous and are fixed mechanically
and with adhesive to the cement board
and completely sealed.

F.5 Installation of Brackets,  Spec. Section 07 42 13 Each Bay  According to approved shop 
Aluminum Profile, Rock Wool o Part-1. Clause 1.04 T,1 drawings/details and method of
and Aluminum Foil for o Part-3. Clause 3.02 D statement.
System EWS-501. o Part-3 Clause 3.02 E  Size follow the approved shop drawing
o Part-3 Clause 3.02 F and calculation.
 Approved Method Statement  Install all anchors and supports in full
 LKW-FCD-MST-000009 compliance with the performance
 Approved Typical details Shop criteria specified without distress to
drawings any component or assembly or panel
 WHLY-FCD-DWG-02-900-XX- joint integrity.
2750059  Brackets outside or through the vapor
 WHLY-FCD-DWG-02-900-XX- retarder.
2750065  After located the right place, clamping
 WHLY-FCD-DWG-02-900-XX- the nuts, and proceed with the torque
2750067 test as per the specification.
 WHLY-FCD-DWG-02-900-XX-  Do not install damaged components.
2750068  Rigidly secure non-moving joints.
 WHLY-FCD-DWG-02-900-XX-  Install anchors with separators and
2750072 isolators to prevent metal corrosion,
 electrolytic deterioration, and
impediments to movement of joints.

Page 20 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 Gypsum boards shall be mold/ fungus


and vermin resistant, moisture
resistant, and resistant to dimensional
changes when exposed to variations in
temperature and moisture.
 Insulation shall be cut/trimmed to fit
between metal deck and gypsum
board.
 Coordinate installing roofing system
components so insulation is not
exposed to precipitation or left
exposed at the end of the workday.
 Comply with insulation manufacturer's
written instructions for installing roof
insulation.
 Cut and fit insulation within 6 mm of
nails, projections, and penetrations.
 Steel frame size will follow the
approved shop drawing and calculation
 Install membrane in accordance with
manufacturer's recommendations
 Ensure surface and free from
punctures.
 Ensure that all aluminum foils are
continuous and are fixed mechanically
and with adhesive to the cement board
and completely sealed.
F.6 Bolt Tightening Inspection  Spec. Section 07 42 13 Each Bay  Bolt tightness: Head not spinning with H H W W R  Bolt Tightening
(M12 bolts) hand wrench. Report & 3rd Party
Report

Page 21 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 Torque values shall be as per


manufacture’s torque chart .
 Torque Value 55Nm
F.7 Installation of Aluminum  Spec. Section 07 42 13 Each Bay  According to approved shop  IRF(Through
panel o Part-1. Clause 1.02 B,3,a drawings/details and method of H - H H H ACONEX)
o Part-3. Clause 3.02 D statement.  LKW-QAC-CHL-
o Part-3. Clause 3.03 A,1  Do not install damaged components. 000192
 Approved Method Statement  Rigidly secure non-moving joints.
 LKW-FCD-MST-000009  Where aluminum will contact
 Approved Typical details Shop dissimilar metals, protect against
drawings galvanic action by painting contact
 WHLY-FCD-DWG-02-900-XX- surfaces with primer, applying sealant
2750059 or tape, or installing non-conductive
 WHLY-FCD-DWG-02-900-XX- spacers as recommended by
2750065 manufacturer for this purpose.
 WHLY-FCD-DWG-02-900-XX-  Install components plumb and true in
2750067 alignment with established lines and
 WHLY-FCD-DWG-02-900-XX- grades.
2750068  Provide concealed fasteners where
 WHLY-FCD-DWG-02-900-XX- possible, and set units true to line and
2750072 level as indicated.

F.8 Survey check of installed  Spec. Section 07 42 13 Each Bay  Line: ± 2.0mm of any line expressed by  IRF(Through
Aluminum Panel (Line & o Part-3. Clause 3.03 A.1 the framing or panels in any one storey H H H H H ACONEX)
Level)  Approved Method Statement height, or structural bay width, and ±  Survey Report
 LKW-FCD-MST-000009 5.0mm overall.
 Approved Typical details Shop  Level: ± 2.0mm in any one structural
drawings bay, and ± 5.0mm overall.
 WHLY-FCD-DWG-02-900-XX-
2750059
Page 22 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 WHLY-FCD-DWG-02-900-XX-
2750065
 WHLY-FCD-DWG-02-900-XX-
2750067
 WHLY-FCD-DWG-02-900-XX-
2750068
 WHLY-FCD-DWG-02-900-XX-
2750072

G Field Testing
G.1 Air Infiltration test(For EWS-  Spec. 07 42 13 Min. 3 tests,An area  Areas shall be tested for air leakage of  IRF (Through
501) o Part-3 Clause 3.05 B.3 not less than 6 1.5 m3/hr/m2 of fixed wall area when H H H H H ACONEX)
 ASTM E 783 panels in a 3 x 2 tested at a minimum static-air-  LKW-QAC-CHL-
 LKW-FCD-MST-000009 array. pressure differential of 600 Pa. 000192
 LET-LKW-MPW-01297  If a test fails, the total tested area shall  3rd Party Test
be doubled. Report

H Repairs (If Any)


H.1  Metal Wall Cladding  Spec. 07 42 13 For Element with  Replace damaged finishes with new.  IRF (Through
System o Part-3 Clause 3.04 A minor defect  Replace the damaged aluminum panel. H - H H W ACONEX)
o Part-3 Clause 3.04 B  Rectify any damage that occurs during  LKW-QAC-CHL-
 ASTM A 780 installation progressively. Do not allow 000192
 Zinc rich primers: 20 type it to accumulate.
 MAS-LKW-MPW-001270
 LKW-FCD-MST-000009

Page 23 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

J Completion of Activities
J.1 Final Inspection  Spec. 07 42 13 Each Bay  All above works and test must be  IRF (Through
o Part-3 Clause 3.03 A,1 completed. H - H H H ACONEX)
Approved Typical details Shop  No visible damage.  LKW-QAC-CHL-
Drawings  No evidence of defected materials and 000192
 WHLY-FCD-DWG-02-900-XX- workmanship.
2750059  No penetration of water into the
 WHLY-FCD-DWG-02-900-XX- building.
2750065  No cracking, peeling, flaking of coatings
 WHLY-FCD-DWG-02-900-XX- and no discoloration of fading, and
2750067 excessive non-uniformity.
 WHLY-FCD-DWG-02-900-XX-  All previous approved
2750068 references(Previous IRF reference
 WHLY-FCD-DWG-02-900-XX- numbers, Report numbers, ETC.) shall
2750072 be indicated on final inspection IRF.
 LKW-FCD-MST-000009

J.2 Cleaning & Protection  Spec. 07 42 13 Each Bay  On completion of metal wall panel  IRF (Through
o Part-3 Clause 3.06 A installation and after removal of H - H H H ACONEX)
o Part-3 Clause 3.06 B surface protection, clean finished  LKW-QAC-CHL-
o Part-3 Clause 3.06 C surfaces as recommended by metal 000192
o Part-3 Clause 3.08 A wall panel manufacturer.
o Part-3 Clause 3.08 B  After metal wall panel installation,
 Approved Shop drawings clear weep holes and drainage
 WHLY-FCD-DWG-02-900-XX- channels of obstructions, dirt, and
2750059 sealant.

Page 24 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
MINISTRY OF PUBLIC WORKS
Construction, Completion, Furnishing, and Maintenance for Kuwait International Airport New Passenger Terminal
II SPA/214
Inspection and Test Plan for Metal Wall Cladding System Installation of T2
(Type:EWS-501&EWS-502)
ITP No: LKW-FCD-ITP-000010 Issue Date:
02.10.2022
Discipline: Architectural Rev. No: 01
Inspection Type
Activit Inspection/Activity Requirements Frequency Acceptance Sub 3rd Site QC Eng
Reference
y Description Reference Criteria Con Pty Eng Eng. Rep Doc. To Be Verified
No

 WHLY-FCD-DWG-02-900-XX-  Replace metal wall panels that have


2750065 been damaged or have deteriorated
 WHLY-FCD-DWG-02-900-XX- beyond successful repair by finish
2750067 touch-up or similar minor repair
 WHLY-FCD-DWG-02-900-XX- procedures.
2750068 
 WHLY-FCD-DWG-02-900-XX-
2750072
 LKW-FCD-MST-000009

Note:

Page 25 of 25
Legend:
W- Witness Inspection Point, H- Mandatory Hold Point for Inspection,
S-Surveillance Inspection Point (No notification required, but activity may be subjected to the Engineer) R- Record/Review
Construction, Completion, Furnishing, and Maintenance for Kuwait International
Airport New Passenger Terminal II SPA/214
Metal Wall Cladding System (EWS-501/502) Checklist

Subcontractor: □ AIC (Fixed Bridge Steel Structure) □ WHLY(Main Facade)


Ref. IRF No: Date:

Drawing Ref. No:

Area Code: Location: Elevation: Axis:


Subcontractors
Fixed Bridge Main Facade Contractor Consultant
Steel Structure (WHLY)
Sn Checks (AIC)
Inspection status Inspection Status
Yes No Yes No Yes No Yes No

A Preliminary Works Prior to Commencing of Work


1 Check approval of materials, samples, test reports and documents. NA
2 Check testing prior to construction (PMU) has been achieved. NA
3 Check site visual mock-up is achieved. NA
4 Check site quality benchmark is achieved. NA
B Site Preparation Prior to Installation of Metal Wall Cladding System (EWS-501/502)
Check the Existing Steel Structure (Fixed Bridge) has been completed by AIC (As per
1 LKW-STR-ITP-000033 and approved final inspection document received by WHLY) for
the axis to be executed by WHLY.
C Installation of Metal Wall Cladding System (EWS-501/502)
1 Check stud welding visual inspection and MT report submitted. NA
2 Check the bend test is achieved. NA

3 Check weld repair has been completed (if any). NA

4 Check surface preparation and primer touch up application (Welding area). NA


Check the installation of Gypsum Board, C shape steel support and Rock Wool for NA
5
System EWS-502.
Check Installation of Brackets, Aluminum Profile, Rock Wool and Aluminum Foil for NA
6
System EWS-501.
7 Check Bolt Tightening Inspection. NA

8 Check the Installation of Aluminum panel. NA


9 Check the Survey of Aluminum Panel. NA
D File Tetsing
1 Check Air infiltration test. NA
E Completion of Activities
1 Check installation of closures are obtained. NA
2 Check final inspection and release for cleaning and protection. NA
Note: (Items above shall be checked with Consultant; a signed copy shall be provided to Consultant. Once the checklist is signed, it shall be sent back to Limak along with final status
of IRF by Consultant).
Remarks:

Fixed Bridge Steel Subcontractor`s Representative (AIC): Contractor`s Representative: ENGINEER:

Name & Signature: Name & Signature:


Name & Signature:
Date:
Main Facade`s Representative (WHLY):

Name & Signature:


Date: Date: Date:

Document No: LKW-QAC-CHL-000192 page 1 Rev.00