Professional Documents
Culture Documents
Ch01 1 14
Ch01 1 14
Introduction
to Underbalanced
Drilling Operations
Advanced Underbalanced Well Operations and Pressure Control
• Mud properties, The total effect of this division is not fully realized until the
• Regulatory Requirements. operational procedures are developed.
Well planners must consider equipment deployment
procedures in an attempt to identify conflicts that arise due
to this division of equipment usage.
Another key design point is that most rotating control
heads, with the exception of the Shaffer PCWD, are not API
certified annular preventers. Often it becomes essential to
reduce BOP component height if possible. Some operators
elect to remove the conventional annular preventer and
use the control head as a substitute. This is not good
design practice, as it reduces the redundancy required for
emergency well control situations.
For most underbalanced operations the number of rams
used is the same as for conventional operations; however,
layout of the rams requires special consideration. The
placement of the blind rams should be considered within the
overall operational plan. The blind rams will be the wellbore
isolation valve when the drill string is out of the hole, unless
a down hole isolation valve is employed. If height allows,
consideration should be made to use an additional blind
ram that is placed directly above the wellhead. This will give
additional lubrication height to get the bottom hole assembly
Figure 3: BOP stack into and out of the hole. All UBD BOP systems should have
an equalizing line that connects the primary flow line and the
lowest BOP.
Although the stack used during UBD operations is much If it is desirable to flow the well when drill pipe is out of
the same, the application, requirements, and configuration the hole (to reduce surface pressure or to perform a flow
is altered to accommodate the various activities specific test), a mud cross should be placed below the blind rams.
for UBD operations. BOP stack configuration for UBD If constrained by the equipment division noted above, two
operations is based on the following factors: blind rams may be needed to meet the requirements, one for
routine UBD operations, and one for well control.
• Maximum anticipated surface pressure, If the well site is near public areas, a slotted liner or
• Layout of rig substructure or platform to expandable sand screen is to be run or if H2S is a concern,
accommodate the stack, the use of blind shear rams should be considered. Many of
• Composition of produced fluid (i.e. H2S, CO2, the heavy wall drill strings used today are too thick to allow
aromatics, etc.), shearing. The operator must know the limitations of the rams
• Additional hardware components to be run in the employed. Once the drill string has been chosen, consult the
well after drilling, BOP manufacturer with regards to shearing capability. The
• Regulatory requirements. shear rams must also be able to shear the slotted liner or
expandable sand screen to be run.
The working pressure of the UBD BOP stack should Drilling BOPs are not designed for sustained production.
be rated to the maximum anticipated surface pressure as a BOPs for UBD operations should be evaluated for seals
minimum. When most operators design BOP stacks for UBD and elastomers to assure they are suitable for service.
operations (critical wells) they divide the design criteria into In addition, most BOPs used for conventional drilling are
two categories: seldom tested with gas. It is suggested that the BOP stack
and rigs injection manifold be tested with gas prior to
1) conventional components for well control only and, commencing underbalanced operations, especially if a gas
2) components used for both well control and UBD media is present.
normal operations.
This separation of roles ensures that the quality
of equipment used for secondary well control is not
compromised by over-use in normal UBD operations.
Where:
The Barrier Concept
BHP =bottom hole pressure All drilling operations are designed with control of the
SP =surface pressure well as the primary criteria. Controlling a well includes
∆PGravity =hydrostatic pressure due to mud weight casing design, BOP configuration, fluid densities and in
∆PFriction =friction pressure due to circulation some cases, hole and drill string dimensions. A consistent
∆PAcceleration =pressure due to acceleration barrier policy, which requires a minimum of two barriers
for all operations, is maintained for most conventional and
Conventional drilling uses hydrostatic pressure to underbalanced operations.
maintain adequate bottom hole pressure. Since the well Conventional operations use fluid density as the
remains open in conventional drilling, the hydrostatic primary well control barrier. The fluid density is maintained
pressure must balance the formation when circulation stops. such that the hydrostatic pressure exerted by the fluid
Friction pressure and acceleration pressure do not come in column exceeds the reservoir pressure. The rig’s well
to play. control equipment, BOPs and choke manifold, serve as the
Underbalanced wells are controlled dynamically. An secondary barrier for well control. The drilling operations are
underbalanced system is designed to take into account normally conducted with the BOP stack fully open and only
friction, surface pressure and acceleration of the fluids. in the event of unplanned influxes is the stack closed.
Although underbalanced systems allow the reservoir fluids In the UBD mode, the density of the fluid is reduced
to flow into the well, this does not mean that there is less to allow the formation to flow. Parameters such as friction
control over bottom hole pressure. Although bottom hole and pump rates are modified to alter the effective density
pressure is maintained below the formation pressure, control in the wellbore. To accomplish this, the rotating head and
of the bottom hole pressure is still critical and must not be choke assembly is used to provide control of fluids exiting
allowed to fall below a pre- determined value. Allowing the the wellbore. In UBD operations, the use of rotating heads
bottom hole pressure to fall outside the designed operating facilitates transfers the primary control from the hydrostatic
window could result in wellbore stability problems, excess column to the rotating head and surface equipment,
surface pressure, production rates that exceed the capacity making them the primary barrier. Control of the well in
of the surface separation equipment or temporary over underbalanced operations is dependent upon the integrity of
balanced conditions that can cause formation damage. The the surface flow system. The primary BOP system remains
control of bottom hole pressure must account for pressure the secondary barrier in emergency well control situations.
fluctuations that occur during connections, slugs of gas The BOP stack is exposed to higher pressures for longer
or liquid in the well, and other transient effects caused by periods of time. It is for this reason that the quality of the
having compressible fluid in the annulus. In UBD operations, BOP stack must be ensured.
optimum bottom hole pressure ensures that the resulting
formation fluid flow rates and pressures are within the limits
of the equipment, and that the wellbore remains stable
Redundant Barrier
throughout the interval. A major issue with underbalanced drilling is the ability
to maintain a two-barrier policy throughout all operations.
It must be noted that there will only be a single barrier
Health, Safety & Environmental Issues (HSE) at the wellhead to BOP connection and at the BOP body
Health, safety and environmental (HSE) issues below the lowest ram. This is similar to the single barrier
are the paramount concern for both conventional and associated with producing wells below the master valve of
underbalanced operations. Both systems must be designed the Christmas tree. Although this risk has been noted and
so that the health and safety of those working on the rig and accepted in production applications, particular care must be
the general public are protected. Both systems must also made to mitigate the risks associated with this area.
In addition, operations that require equipment that from the formation. If this is true, then the definition of a kick
bypass one of the two barriers create the potential problem. must change.
Slotted liners effectively bypass the primary barrier (rotating For underbalanced well control, a kick, or more
diverter cannot seal around slots) and the secondary accurately, a well control incident may be defined as
barrier (slots allow flow past BOP). Procedures have anytime:
been developed to allow the running of slotted liners and
completion equipment, but a true two-barrier policy is difficult • Higher formation pressure than expected is
to maintain. Particular care must be used in the design of the encountered,
well to mitigate the risks associated with running this type of • Higher permeability than expected is encountered;
equipment in underbalanced conditions. • Poor choke control that results in pressure or
flow rate that exceeds the design window for the
operation,
• Errors in engineering that result in pressure or
flow rate that exceeds the design window for the
operation.
Common Features of Underbalanced Additional costs related to the massive losses amounted
to more than $1.3 MM. The loss of fluids to the formation
Drilling and the LCM pills resulted in lost productivity and formation
Design specifics for drilling underbalanced are damage.
determined by various factors. Some important factors are: Underbalanced drilling was considered due to these
problems. Since the wells were generally successful oil
• The reasons for drilling underbalanced; producers with production rates averaging 2500 BOPD, an
• The make-up of the produced fluids; underbalanced foam system was the most viable option.
• The formation pressure; The foam system allowed for the adjustment of both water
• The risk of problems and the difficulty in solving and gas, resulting in the ability to maintain a bottom hole
problems pressure less than that of the reservoir. The foam drilling
technique was capable lifting liquids and suspending these
liquids in a foam emulsion preventing slugging during
Description of High Energy Wells connections. Additionally, the UBD program enabled
A well is planned to drill through a depleted gas reservoir coring, drilling to objective depths, and improved reservoir
in a vugular limestone formation. Underbalanced drilling is evaluation through electric logging.
being considered due to the drilling problems encountered
Robinson, S., Hazzard, V., Leary, M., Carmack, C., “Redeveloping
while drilling conventionally. Formation pressures have
the Rhourde El Baguel Field with Underbalanced Drilling Operations,”
dropped to a point at which the formation can no longer paper SPE 62203 presented at the IADC Conference and Exhibition 2000
support a full column of liquid (water or diesel). Due to held in Houston, Texas, 28-29 August 2000.
the level of depletion, conventional drilling has resulted in
total loss of returns, differential sticking and mechanical Depleted Reservoir Case Study
sticking caused by the inability to circulate drilled solids The Krisna field is located 60 miles offshore Java,
to the surface. The loss of fluids to the formation and the Indonesia. Massive lost circulation in excess of 50,000 bbl
techniques for trying to solve the lost circulation problems of fluid occurred while attempting to drill the first horizontal
has resulted in formation damage and lost productivity. well in the field. The goal for drilling the production interval
Despite the depletion of the reservoir, the formation underbalanced was to eliminate the loss of fluids to the
is still very prolific. Offset wells show that the wells can formation. The ability to maintain underbalanced was a
produce in excess of 100 MMscfd/psi. critical issue for the Krisna project. The existing pore
pressure of 650 psi gave an equivalent density below 3.0
ppg. The oil from the Krisna field has high wax content and a
Description of a Depleted Reservoir high pour point. The reservoir oil thickness posed a problem
An offshore well is to be drilled in a depleted oil reservoir for maintaining circulation and also having the oil set up in
in a fractured carbonate. Previous wells have suffered loss the separator. Potential problems became worse when tests
in excess of 20,000 bbls. and stuck pipe. Clean-up time after between the produced oil and the KCL brine drilling fluid
drilling exceeds 30 days. Underbalanced drilling is being created an emulsion.
used to eliminate drilling problems and reduce clean-up time. Problems were encountered in separating the cuttings
Reservoir fluid has a high asphalteen and wax content. from the fluid. The solids slurry from the four-phase
separator contained oil, which was sent over the shaker and
High Energy Reservoir Case Study to the mud pits. This resulted from the inability to break the
After years of depletion, the reservoir pressure in the KCL/oil emulsion. A decision was made to allow all fluids
Rhourde El Baguel field dropped more than 60%, creating to be pumped to production and have the solids collected
a large secondary gas cap. A redevelopment project in the four-phase separator. After some time drilling ahead,
was started to try and increase recovery. In nine of the the production transfer line was opened up. Large amounts
early redevelopment wells, an attempt was made to drill of drilled solids were found packed in the pipe and transfer
overbalanced with a lighter weight oil based mud. Yet, this pump. This indicated that the KCL/oil emulsion was so
fluid weight reduction was still insufficient and caused an tight that solids were not being separated in the four-phase
overbalance of more than 1900 psi. As a result, massive separator. To fix this problem, a switch was made to a diesel/
lost circulation and differential sticking problems began N2 mist. This reduced the emulsion thickness and allowed
to surface in these wells. Mechanical sticking was also drilling to continue in an underbalanced condition. The
prevalent due to the inability of circulating drilled solids to diesel mist system worked well. Good cuttings separation
the surface. LCM pills containing fiber, nut plug, and mica was achieved in the four-phase separator. Drilling continued
were used without success. Stuck pipe occurred time and until the basement was encountered. The well was tested to
again and sought after coring attempts were abandoned.
obtain stabilized flow rates and a shut in reservoir pressure. IADC UBO Classification
Very high penetration rates were realized throughout the
drilling of the production zone. Control drilling had to be Underbalanced drilling is used for many different
implemented when the rate of penetration exceeded 300 applications. In an effort to quantify the level of risk
feet per hour and hole cleaning became an issue. associated with an underbalanced well, IADC has adopted
a classification system. The classification system has three
Park, D., Brand, P.R., Allyson, B., and Sodersano, G., “Planning tiers. The first tier is used for risk management. Six levels
and Implementation of the Repsol-YPF-MAXUS Krisna Underbalanced are described based on the ability of the well to flow and
Drilling Project,” paper SPE/IADC 67689 presented at the SPE/IADC the comparative pressure rating of the primary barrier to the
Drilling Conference held in Amsterdam, The Netherlands, 27 February maximum anticipated surface pressure.
-1 March 2001.
Tier 1: Risk Management
H2S Case Study
The North Sumatra Offshore (NSO) field is located Level Description
off the coast of Sumatra, Indonesia with reservoir gas 0 Performance enhancement only; no
containing approximately 1.7% H2S and 33.5% CO2. The hydrocarbon containing zones
rock is a chalky reef build up which contains coral fragments
1 Well incapable of natural flow to surface,
with fractures resulting in extremely high permeabilities.
inherently stable, and a low-level risk from a
Historically, the challenges of drilling in this area have
well control point of view
included severe lost circulation followed by gas kicks that
can fully evacuate the borehole. The weak rock makes 2 Well capable of natural flow to surface but
it very difficult to maintain a stable column of liquid in the enabling conventional well control methods
wellbore. Safety risks are great due to the high H2S content and has limited consequences in the case of
in the reservoir gas. catastrophic equipment failure
Historically, the NSO reservoir limestone has been 3 Geothermal and non-hydrocarbon
porous, permeable and weak enough to allow entry of all production. Maximum shut-in pressures are
mud and drilled cuttings into the rock when drilling. In this less than UBD operating pressure rating.
case, blind drilling was used to improve safety and reduce Catastrophic failure has immediate serious
drilling times. Key elements of the drilling system included consequences
a rotating blowout preventer (RBOP) attached above 4 Hydrocarbon production. Maximum shut-
a conventional blowout preventer on a jackup rig. The in pressures are less than UBD operating
RBOP maintained surface pressure during blind drilling with pressure rating. Catastrophic failure has
seawater. During this pressurized mud-cap drilling, seawater immediate serious consequences
is pumped simultaneously down the drillstring and down the
5 Maximum projected surface pressures
annulus. This approach maximizes the chance that sour
exceed UBD operating pressure rating but
reservoir fluids will not enter the wellbore and expose the rig
are below BOP stack rating. Catastrophic
crews to safety risks. The RBOP applies pressure to the fluid
failure has immediate serious consequences.
in the annulus while rotary drilling. Thus, seawater rather
than the expensive mud can be used, as is the case for
conventional mud-cap drilling. The abundant supply of water The second tier is used to describe the well as a true
avoided potential mixing and materials logistic problems. underbalanced project or a near balanced project. The third
With the set up used, surface pressures can be continually tier is used to describe the fluid system being used.
monitored beneath the RBOP to allow liquid injection rates
to be maintained at minimum levels without gas influx. Tier 2: IADC UBO Committee Classification System for
The average time to drill the limestone was 4.7 days per Underbalanced Wells
well at a progress rate of 132 ft/day. This compares favorably Near-balanced A
with the historical appraisal drilling performance of 15.6 days
per well and 42 ft/day. Most importantly, safety was greatly Underbalanced B
improved by using the RBOP and blind drilling practices. MudCap C
Quitzau, R., Brand, P.R., Tarr, B.A., Frink, P.J., and Leuchtenberg, The fluid system selected for a particular project is
C., “System for Drilling an Offshore Shallow Sour Gas Carbonate dependent on the desired BHP, tolerance to water influx,
Reservoir,” paper SPE/IADC 52808 presented at the SPE/IADC Drilling hole cleaning, cost and environmental considerations.
Conference held in Amsterdam, Holland, 9-11 March 1999.
Fluid Design
Liquid - Gas Ratio Gas Mist Foam Gasified Fluid Single Phase
Pressure Flow Drilling Near-balanced Floating Mud Cap Pressurized Mud Cap
Differential
Processing Equipment
Separation Method Blooey 2 Phase Separators 4 Phase Separators
Advantages:
• Conventional MWD can be used
• Conventional motors can be use with no impact on
power
• Eliminates sloughing scale and dried mud
• Faster connections
Disadvantages:
• Limited depth of injection
• Cost
• Impact on BHP and Annular velocities
• Possibly higher gas volume requirements.
• Oscilating pressure (accumulator effect)
Figure 8: Parasite string with clamps • Plugging of the ports
cost of the project (gas requirements, chemical additions, Concentric casing injection has an additional advantage
etc.). in that concerns over damage or loss of the injection method
Another concern of the parasite injection method is the are minimized and include the elimination of the need to
possibility of damage to the parasite string. The parasite modify the wellhead. Injection pressures are also generally
string can be crushed or crimped during the running of the lower utilizing concentric string injection. Due to the smaller
casing. A leak in the string at one of the termination points hole size created by the concentric strings, hole cleaning is
or in the string is also a concern. There is also the possibility generally improved.
that the string can be plugged. In either case, the damage The major disadvantage not seen with parasite string
may cause this method to become ineffective. injection is the cost of pulling the casing string upon
The use of the parasite injection method requires the completion. Concentric casing designs have the additional
modification of the wellhead allowing a path for the gas. As
the parasite string is run as a permanent fixture, there is
always the concern over the creation of a leak path if the
back pressure valve or a leak in the string occurs in the
future.
Other concerns over parasite string injection methods is
the addition cost and time for running the parasite string, the
possible need for larger hole size for running the string, the
higher pressure requirement for gas injection and the limited
volume of gas that may be pumped down the parasite string.
A higher volume of gas may be required to compensate for
the depth of injection to reach the target BHP.
problem of severe pressure oscillations during and after © Press Sol Ltd.
connections if a back pressure valve is not used. The
volume between the casing strings acts as an accumulator
that can cause pressure oscillations for up to an hour after
the connection. Injection ports have also become plugged
with cuttings due to these oscilating pressures.
Liquid Drilling
If the formation pressure is above a normal pressure
Figure 11: Foam structure gradient, an underbalanced state may be achieved with a
single liquid phase. This allows for a simple system in which
foam is that it has a greater tolerance to overbalance before the well is allowed to flow during drilling operations. Liquid
fluid will be lost to the formation. drilling is commonly referred to as flow drilling or production
In addition to the cost of the surfactant and the additional through a productive interval drilling. In many production
equipment required, foam adds a degree of complexity to drilling applications, the produced fluids are captured and
the system. Foams can break down with contamination sent to sales.
from acid gasses, hydrocarbons or brines. Since one or
more of these contaminants are normally present in an
underbalanced system, selection and testing of a foam Special Applications
system is critical. Foams also lose their stability at increased
temperature. Another disadvantage of foam systems is that Mud Cap Drilling
the higher relative viscosity increases the frictional pressure Mud cap drilling is a method used to safely drill through
loss in the wellbore, making it difficult to achieve ultra low producing zones without returns to surface. The technique is
bottom hole pressures. utilized in areas where severe lost circulation problems and
Breaking the foam structure must be accomplished kicks are prevalent and it is unsafe to allow hydrocarbons
when it reaches the surface in order to effectively separate to flow to surface. It is normally associated with fractured or
the fluid constituents (gas, water, liquid hydrocarbons and vugular formations, with a high H2S content. Fluid (usually
solids). Failure to effectively break the foam will cause water) is pumped down the drill pipe at a sufficient rate
separation problems and will overload the separator. Foams to cool the bit and transport cuttings up to the loss zone).
can either be broken chemically or mechanically. In the past, Simultaneously, fluid is pumped down the annulus at a rate
foam systems could not be re-generated after they were sufficient to keep produced fluids from migrating to surface.
broken. This caused high disposal costs and environmental This annular fluid is referred to as the “mud cap” since it
concerns. The introduction of recyclable foams has prevents migration of the drilling and inflow fluids up the
eliminated many of these concerns. annulus to the surface. The cuttings, pumped fluids, and
Most foam systems are anionic. This precludes the uses any produced fluids, are pumped back into the formation
of cationic corrosion inhibitors. Foam systems can be further at the loss zone. Because of the need to pump whole mud
defined as stable foams, which contain only water gas and a and cuttings into the loss zone, the formation must contain
surfactant, and stiff foams, which include gels and polymers fractures or vugs to be successful.
to increase the viscosity of the system. Foam boosters and Depending on the formation pressure, mud cap drilling
foam stabilizers can also be added to the system to increase may or may not be a form of UBD. In general, the annular
the half-life of the foam (time at which half the volume of the fluid pressure is such that overbalanced conditions prevail
foam is lost). in the section between the surface and the loss zone, while
underbalanced conditions are maintained between the
Gasified Liquids bit and the loss zone. There are two methods of mud cap
Gasified liquids are a combination of liquid and gas in
drilling:
which the liquid is the continuous phase. Gasified liquids do
not have surfactants that bind the gas within the liquid. The 1) floating mud cap drilling and,
main advantages of gasified liquids are the lower cost, the 2) pressurized mud cap drilling.
Floating mud cap drilling uses an annular fluid whose The majority of underbalanced snub drilling operations
density is greater than the fracture gradient of the formation, have been done on sidetracks of existing wells.
so that there is fluid loss into the formation.
This simultaneously prevents migration of produced Notes _______________________________________
gas to regions above the loss zone. However, in this
method, maintenance of a proper mud cap is by trial and ____________________________________________
error. Migration of gas to the surface is difficult to detect and ____________________________________________
requires constant vigilance. ____________________________________________
Pressurized mud cap uses an annular fluid density that ____________________________________________
is less than the formation fracture gradient, and uses annular ____________________________________________
surface pressure to force fluid and cuttings into the loss
zone. A pressurized mud cap system must have a rotating ____________________________________________
control head to maintain constant annular pressure. The ____________________________________________
advantage of this system (in comparison with floating mud ____________________________________________
cap systems) is the control of surface pressure to monitor ____________________________________________
the migration of fluids into the loss zone. The rate that fluids ____________________________________________
are pumped down the annulus can be optimized. In addition,
the fluid lost to the formation will be lighter, cheaper and is ____________________________________________
potentially less damaging to the formation. ____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
____________________________________________
Figure 12: Mud cap drilling ____________________________________________
____________________________________________
Snub Drilling ____________________________________________
Snub drilling utilizes a hydraulic work over unit with
a top drive to drill the well utilizing conventional drill pipe. ____________________________________________
It has many of the advantages of coil tubing in that it is ____________________________________________
designed for tripping under pressure, tripping while flowing ____________________________________________
the well and the ability to continuously circulate while drilling. ____________________________________________
Hydraulic workover units are normally compact, allowing a
____________________________________________
smaller footprint. The main disadvantage of snub drilling is
the time required to trip in and out of the hole, as snubbing ____________________________________________
units typically have much lower trip rate, and typically trip in ____________________________________________
singles or doubles. Snub drilling also requires connections, ____________________________________________
which will cause pressure transients. ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________
____________________________________________ ____________________________________________