GUARDRAIL POST GI PIPE

3.81m
(4")
GUARDRAIL BOLT NUT & WASHER
(5/8"Ø X 6")

0.4500m 0.2250m
METAL BEAM GUARDRAIL
(12")

1.2000m

0.5250m
0.3000m
1.0500m

0.7500m 0.7500m 0.7500m 0.7500m

DETAIL OF GUARDRAIL

300

200

5m m. 170

5m mx2
MFER 2
CHA

220
500

675

360

150
50 50
PLAN
250

2 -12MM DIA RSB 250

25 50

25
750

750

250
750
300

PERSPECTIVE 1

150
NOTES ON WHEELGUARD: 300
SHEAR KEYS 75 x 200 x 250 MM. O.C. SHALL BE FORMED AT THE
CONSTRUCTION JOINT OF LINE CANAL / SLOPE PROTECTION AND 2 -12MM DIA RSB
WHEELGUARD. ELEVATION

DETAILS OF WHEELGUARD

PROJECT NAME & LOCATION: SHEET CONTENTS: PREPARED BY: CHECKED/SUBMITTED BY: RECOMMENDING APPROVAL : APPROVED : SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION IV-B MIMAROPA REPAIR / MAINTENANCE OF ROAD SLOPE
DPWH ROAD
ALONG CALAPAN SOUTH ROAD K0048+900 SLOPE
MINDORO ORIENTAL DISTRICT ENGINEERING OFFICE CY - 2024
OFFICE OF THE DISTRICT ENGINEER
L/S, SOCORRO, ORIENTAL MINDORO AS SHOWN JOHN ERIC C. ROMASANTA LUIS B. BERON ALBIEN M. MAHIA SALVADOR E. ABAD
ENGINEER - II CHIEF, MAINTENANCE SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER MODEO 4 5
MASIPIT, CALAPAN CITY ORIENTAL MINDORO
SOCORRO, ORIENTAL MINDORO
DATE: DATE: DATE: DATE: