Schedule Fire Water (Site)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Name Duration Start Finish Predecessors March 2024 April 2024 May 2024 June 2024 July

ation Start Finish Predecessors March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024
25 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12
1 Pekerjaan Site Fire Water Tank 102 days Fri 3/1/24 Mon 6/10/24
2 Incoming material ( 1st & 2nd Delivery ) 1 day Fri 3/1/24 Fri 3/1/24
3 Unloading Material (By Other) 3 days Fri 3/1/24 Sun 3/3/24 2SS
4 Installation of the asphalt membrane on the tank foundation 3 days Sun 3/3/24 Tue 3/5/24 3SS+2 days
5 Transfer material bottom plate 1 day Tue 3/5/24 Tue 3/5/24 4FF
6 Setting & Welding bottom plate 5 days Tue 3/5/24 Sat 3/9/24 5SS
7 Inspection visual welding & NDT test plate bottom 3 days Fri 3/8/24 Sun 3/10/24 6SS+3 days
8 Built Pipe pole for chain block support 3 days Fri 3/8/24 Sun 3/10/24 7SS
9 Inspection 1 day Sun 3/10/24 Sun 3/10/24 8FF
10 Transfer material & setting plate shell 5, top angel, step stair, plate roof 3 days Sun 3/10/24 Tue 3/12/24 9SS
11 Welding plate shell 5 & top angel (external & internal) 6 days Wed 3/13/24Mon 3/18/24 10
12 Inspection visual welding & NDT test plate sheell 5 4 days Sat 3/16/24 Tue 3/19/24 11SS+3 days
13 Setting rafter , top angle, center drum, plate roof 6 days Mon 3/18/24Sat 3/23/24 12SS+2 days
14 Inspection 2 days Fri 3/22/24 Sat 3/23/24 13FF
15 Welding plate Plate Roof (external & internal) 6 days Fri 3/22/24 Wed 3/27/2414SS
16 Inspection visual welding & NDT test plate roof 2 days Tue 3/26/24 Wed 3/27/2415FF
17 Setting Top Railing, Step Stair 3 days Tue 3/26/24 Thu 3/28/24 16SS
18 Painting plate shell 5, roof & Railing (external & internal) 4 days Thu 3/28/24 Sun 3/31/24 17SS+2 days
19 Erection shell 5 up to 1,8 Meter 1 day Sun 3/31/24 Sun 3/31/24 18FF
20 Incoming Material ( 3th Delivery ) 1 day Sun 3/31/24 Sun 3/31/24 19SS
21 Unloading material ( By Other ) 3 days Sun 3/31/24 Tue 4/2/24 20SS
22 Transfer material & setting plate shell 4 & step stair 2 days Tue 4/2/24 Wed 4/3/24 21SS+2 days
23 Inspection 1 day Wed 4/3/24 Wed 4/3/24 22FF
24 Welding vertical & horizontal plate shell 4 to shell 5 (external & interna6 days Wed 4/3/24 Mon 4/8/24 23SS
25 Inspection visual welding & NDT test plate sheell 4 to shell 5 3 days Mon 4/8/24 Wed 4/10/2424FS-1 day
26 Painting plate shell 4 (external & internal) 4 days Tue 4/9/24 Fri 4/12/24 25SS+1 day
27 Erection shell 3 & 4 up to 1,5 Meter 2 days Fri 4/12/24 Sat 4/13/24 26FS-1 day
28 Inspection 1 day Sat 4/13/24 Sat 4/13/24 27FF
29 Transfer material & setting plate shell 3 to shell 4 & step stair 3 days Sat 4/13/24 Mon 4/15/24 28SS
30 Inspection 2 days Mon 4/15/24Tue 4/16/24 29FS-1 day
31 Welding vertical & horizontal plate shell 3 to shell 4 (external & interna6 days Tue 4/16/24 Sun 4/21/24 30SS+1 day
32 Inspection visual welding & NDT test plate shell 3 to shell 4 3 days Sat 4/20/24 Mon 4/22/24 31FS-2 days
33 Painting plate shell 3 (external & internal) 4 days Mon 4/22/24Thu 4/25/24 32FS-1 day
34 Erection shell 3, 4, 5 up to 1,5 Meter 3 days Thu 4/25/24 Sat 4/27/24 33FS-1 day
35 Incoming Material ( 4th Delivery ) 1 day Sat 4/27/24 Sat 4/27/24 34FS-1 day
36 Unloading material ( By Other ) 3 days Sat 4/27/24 Mon 4/29/24 35SS
37 Transfer material & setting plate shell 2 to shell 3 & step stair 3 days Sun 4/28/24 Tue 4/30/24 36FS-2 days
38 Inspection 1 day Tue 4/30/24 Tue 4/30/24 37FF
39 Welding vertical & horizontal plate shell 2 to shell 3 (external & interna6 days Tue 4/30/24 Sun 5/5/24 38SS
40 Inspection visual welding & NDT test shell 2 to shell 3 4 days Fri 5/3/24 Mon 5/6/24 39FS-3 days
41 Painting plate shell 2 (external & internal) 4 days Sun 5/5/24 Wed 5/8/24 40FS-2 days
42 Erection shell 2, 3, 4, 5 up to 1,5 Meter 3 days Tue 5/7/24 Thu 5/9/24 41FS-2 days
43 Transfer material & setting plate shell 1 to shell 2, step stair 3 days Thu 5/9/24 Sat 5/11/24 42FS-1 day
44 Inspection 2 days Sat 5/11/24 Sun 5/12/24 43FS-1 day
45 Welding vertical & horizontal plate shell 1 to shell 2 (external & interna6 days Sat 5/11/24 Thu 5/16/24 44SS
46 Inspection visual welding & NDT test 4 days Thu 5/16/24 Sun 5/19/24 45SS+5 days
47 Painting plate shell 1 (external & internal) 4 days Sun 5/19/24 Wed 5/22/2446FS-1 day
48 Setting & Welding Accessories Nozzle 6 days Tue 5/21/24 Sun 5/26/24 47SS+2 days
49 Finishing , Top Coat Painting 6 days Sun 5/26/24 Fri 5/31/24 48FS-1 day
50 Radiograohy Test 2 days Sat 6/1/24 Sun 6/2/24 49
51 Leak Test Tank ( water by other ) 7 days Mon 6/3/24 Sun 6/9/24 50
52 Hand Over 1 day Mon 6/10/24Mon 6/10/24 51
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Sch Ws Fire Water Tank
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 5/21/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1